1 UVA Polarized Target In Hall A Pictures and Cost Paul Brindza Dec 17, 2009

2 UVA/PT in Hall A Outline Some Target area illustrations and Photos Equipment stands Down stream Beam Line and Dump Typical Scattering Chamber customization Cost summary Cost details Conclusions

3

4 CAD World View of UVA/PT GEN Experiment in Hall C

5 Hall A UVA/PT Beam Line Chicane Tungsten calorimeter SEM BPM BCM Moller Target center Fast raster EP Slow raster 85cm 10 m 4 m Chicane Design : Jay Benesh (JLab CASA) Two upstream Dipoles, one with vertical degree of freedom. Reuse the dipoles from the HKS experiment. Utilize open space upstream of target. Minimal interference with existing beamline equipment. UVA/Jlab 5 T Polarized Target Upstream Chicane and supports Slow raster and Basel SEM. Instrumentation for 50-100 nA beam. Local beam dump. Hall A Septa. Major Installation

6 UVA/PT Scattering chamber and end of entrance beam line

7

8

9 UVA/PT Target Platform

10 UVA/PT equipment deck with dewar

11 UVA/PT Overhead View with pump line

12 CAD World View of UVA/PT and related equipment

13 UVA/PT GEN Helium Bag

14 Beam Dump for UVA/PT GEN Experiment

15 Beam Dump Shielding for UVA/PT GEN

16 SANE Scattering Chamber for UVA/PT

17 CAD representation of SANE Scattering Chamber

18 UVA/PT in Hall A Cost Summary Total cost of Beam line & girder 195 K$ Total cost of UVA PT in Hall A 457 K$ Total Experiment Specific costs for the UVA/PT 261 K$ Total cost of Beam line, Pol target and RT septum 913 K$

19 Hall A vertical Beam Chicane Outsource to ACC Div and/or Eng Div LocationEngineeringDesignFabricationRemovalInstallation BZ1 MagnetHall C0.52 BZ2 MagnetHall C0.52 New BZ2 elevator24200002 New articulating beam line48170002 BZ1 DC power supplyHall C0.21 BZ2 DC Power SupplyHall C0.21 DC cablesHall C0.11 New LCW connections150002 New 480 V AC power9000 New BZ controls0.150002 New BZ FSD0.130000.5 New beam vacuum pumps0.150000.3 Alignment2 Girder & Beam Instrumentation Outsource to ACC Div and/or Eng Div New Hall A/UVA Target Beam Girder38200002 Remount existing beam instrumentationHall A20004 Cabling for beam instrumentation100002 New Vacuum pumps0.150000.5 alignment1 EngineeringDesignFabricationRemovalInstallation Subtotals for labor (MW)10.420NA1.527.3 Cost (K$)20.8301012.2540.95 Outsourced sub totalTotal cost of Beamline & girder(K$)195

20 Experiment Specific Costs UVA Target Scattering Chamber LocationEngineeringDesignFabricationRemovalInstallation New Target Scattering chamber for Hall A exit angles26200001 New Target LN2 shield for Hall A exit angles0.1150001 New Target Exit windows1140000.5 Beam line BE exit window and line0.050.320000.05 Target chamber entrance Be window0.0510000.05 Target Chamber exit BE window0.0520000.05 Install UVA PT in Hall A5 alignment1 UVA Target Hall A Downstream beam line LocationEngineeringDesignFabricationRemovalInstallation New Downstream beam line Helium bag3250001 New He bag entrance widnow0.515000.05 New He bag exit window0.540000.1 New He Bag stand12100001 In hall beam dumpAccelerator0.10.2 Beam dump shieldingJLAB0.5 New Yoke for RT Septum LocationEngineeringDesignFabricationRemovalInstallation New Split Yoke for RT septum2430000 New RT septum yoke/coil mechanical support1310000 New RT septum multi angle mount2825000 New RT septum beam tubes110000 New RT septum sieve slits24000 New RT septum entrance windows14000 Modify RT septum24 Install Rt septum4 Alignment2 EngineeringDesignFabricationRemovalInstallation Subtotals for labor (MW)9.2533.3NA2.121.5 Cost (K$)18.549.95157.53.1532.25 Total Experiment Specific costs for the UVA/PT(K$)261.35K$

21 UVA Target mount LocationEngineeringDesignFabricationRemovalInstallation New/modify UVA Target platform for Hall A Pivotstorage28350000.21 New Railings and ladders180000.2 AC power4000 Local lighting2000 alignment1 Target Equipment Platform LocationEngineeringDesignFabricationRemovalInstallation Equipment Platform modifications or newstorage1250000.21 railings and ladders150000.2 New AC power8000 New local lighting2000 Target Vacuum system LocationEngineeringDesignFabricationRemovalInstallation Target Pump lineHall C20.42 New Target Vacuum donut line13200001 New Target vacuum line support12100001 Vane PumpsHall C0.10.20.4 Roots PumpsHall C0.10.20.4 Helium FilterHall C0.10.2 New Helium return line100002 New Target vacuum system skid or platform24100001 New Target Vacuum Pump 480 V AC power8000 New Target vacuum pump cooling water0.540000.5 UVA PT Installation in Hall A

22 Target Cryogenic system LocationEngineeringDesignFabricationRemovalInstallation Buffer DewarStorage0.21 Buffer dewar fill/withdrawal adaptorStorage0.2 Target LHE Delivery tubeStorage0.2 Target He Fill valveStorage0.2 Target He Liquid Level ControlsStorage0.2 New Target He gas return line100002 New Target LN2 Delivery Tube230000.2 Target LN2 Supply Valvestorage0.2 Target LN2 Liquid Level controlstorage0.2 New Target N2 Gas return line50002 New Buffer Dewar Helium Supply tube0.5250000.2 New Buffer Dewar Helium Return tube0.5250000.2 Buffer Dewar Liquid level controlstorage0.2 New Buffer Dewar Helium Supply valve50000.2 New Buffer Dewar Helium Return valve50000.2 New Buffer Dewar Helium cool down valve20000.2 New Buffer Dewar Warm gas return line50001 New siamese adaptor for HRS Q1 cryo supply26200002 Stands and supports for some of the above13150002 Major Hall A item removal work LocationEngineeringDesignFabricationRemovalInstallation Remove upstream girder1 remove US girder stands0.5 remove US beamline between moller and target chamber0.2 remove Hall A target1 remove HRS sieve slits1 remove hall A scattering chamber1 remove downstream beam line2 remove down stream beam line stands2 remove downstream beam instrumentation(lumi's etc etc)0.2 remove down stream beam line vacuum system0.1 as found alignment survey1 Repair of UVA PT SC magnet LocationEngineeringDesignFabricationRemovalInstallation Repair of SC magnet at Oxford Instruments2100000 Shipping60001 EngineeringDesignFabricationRemovalInstallation Subtotals for labor (MW)13.538.2NA10.726.5 Cost (K$)2757.331716.0539.75 Total cost of UVA PT in Hall A(K$)457.1

23 Conclusions UVA/PT in Hall A Installation of UVA/PT in Hall A is Feasible Cost is significant at 913 K$ Total inc. Labor Eng & Design 125 MW (+20% / -0%) Eng and Design is a 12 month effort! Removal &Installation 90 MW ( +20 % / -0%) This can be done in the 6 Month shutdown


Download ppt "UVA Polarized Target In Hall A Pictures and Cost Paul Brindza Dec 17, 2009."