Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 20, 2009 EDUCATE ENGAGE EMPOWER 1.

Slides:



Advertisements
Similar presentations
Capital Program Oversight Committee (CPOC) May 23, 2011 Alok Saha, P.E., Program Manager, CPM Infrastructure and Facilities – Line Equipment, Shops & Yard.
Advertisements

2010 MEASURE C FACILITIES IMPROVEMENT PROGRAM Proposed Implementation Plan September 14, 2010.
Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.
Aubrey Green Community Meeting Issues and Opportunities Vandalism Safety Community Image Community Opportunities and Renewal Who is here and Why PW - Parks.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District July 21, 2008 BUILDING TOMORROW TODAY 1.
SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL.
Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking.
The Greenwood Apartments a partnership between Banc of America Community Development Corporation and Clearwater Neighborhood Housing Services, Inc.
1 Building Use Study Plattsburgh City School District Advisory Committee Meeting September 18, 2013 Castallo and Silky- Education Consultants Bill Silky.
Module Reading Plans and Elevations
MULTIPLE PROFESSIONAL REVIEWS DOCUMENT SOLUTIONS Architectural and engineering review identifies building code and accessibility repairs needed. ($750,000.
MARPLE NEWTOWN SCHOOL DISTRICT FACILITIES. Maintenance & Small Projects Planned for Summer 2007 New carpet at Worralls office New fencing at Worralls.
Recent Bond Accomplishments. Bordeaux Elementary Remodel.
August 2008 WATCH YOUR STEP! CONSTRUCTION PROJECTS UNDERWAY!
ADA Improvements on Administration Buildings Indian Valley Campus (One Stop Project)
Revitalization Plan. Revitalization Plan Goals Increase homeowner value by continuing to Invest in both infrastructure and curb appeal.
Draft FMP Priorities For Discussion Facilities Committee 3/5/13.
June 8, 2011 Irvine Unified School District. What is a Modernization? Eligibility Permanent buildings - 25 years old Portable buildings - 20 years old.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District November 1, 2007 BUILDING TOMORROW TODAY Cordoba Corporation.
COMING NOVEMBER 2012 SHAWNEE HEIGHTS BOND REFERENDUM MORE INFORMATION WILL BE AVAILABLE SOON ON THE SHAWNEE HEIGHTS DISTRICT HOMEPAGE.
April 14, 2009 Los Angeles Valley College Prop J Master Plan Town Hall Presentation.
Bond Program Planning Imperatives Study Session October 12, 2004.
Marin Community College District CIP Briefing – Citizen’s Oversight Committee September 13, 2005.
BOND PROGRAM UPDATE Long Beach Community College District Citizens’ Oversight Committee Meeting October 11, 2004.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 2008 EDUCATE  ENGAGE  EMPOWER 1.
BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District Citizens’ Oversight Meeting October 9, 2006.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District January 31, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Measure G Overview March 9, Measure G School Facility Improvement East Side Union High School District To provide greater security and safety, relieve.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 19, 2009 EDUCATE  ENGAGE  EMPOWER 1.
LOCAL ASSISTANCE 5 – YEAR PLAN Facilities Department Mark Thissell.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District July 20, 2009 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District August 8, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District January 25, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 25, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 25, 2012 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 2, 2008 BUILDING  TOMORROW  TODAY 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 14, 2010 EDUCATE  ENGAGE  EMPOWER 1.
BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District The Long Beach Rotary Flex Day,March 28, 2007 Flex Day, March 28, 2007.
BOND PROGRAM UPDATE Long Beach Community College District Board of Trustees Meeting July 13, 2004.
St. Ambrose University Main Campus Planned Institutional District Application December 15, 2011.
Bond Construction Update Citizens’ Oversight Committee Long Beach Community College District January 28, 2008 BUILDING  TOMORROW  TODAY Cordoba Corporation.
BOND PROGRAM UPDATE Long Beach Community College District Citizens’ Oversight Committee Meeting July 12, 2004.
HIGHLAND PARK BOND WORK The final results will be AMAZING!
Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District Septmeber 24, 2009 EDUCATE  ENGAGE.
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:
Torrance Unified School District Bond Measure Y Bond Measure Z Quarterly Construction Update September 30, 2009.
Paradise Valley Community College CLC Update Jacalyn A Askin, Vice President of Administrative Services May 8, 2009.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 1,
Bond Construction Update Facilities Advisory Committee Long Beach Community College District November 17, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District October 24, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District January 23, 2012 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 6, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District July 26, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 14, 2011 EDUCATE  ENGAGE  EMPOWER 1.
MODERNIZATIONS “The First Five” Golden West Elementary Lathrop Elementary Lincoln Elementary Sequoia Elementary Shasta Elementary December 8, 2015.
MODERNIZATIONS MEASURE G OVERSIGHT COMMITTEE September 8, 2015.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District March 3, 2010 EDUCATE  ENGAGE  EMPOWER 1.
White Pigeon Community Schools
Building Services Summer 2016 Update
Cornwall Central School District
Facilities Update November 17, 2017
MIRACOSTA COMMUNITY COLLEGE DISTRICT
Facilities Modernization Program
Charter Oak Unified School District
Capital Outlay Workshop
Recent Bond Accomplishments
Presentation transcript:

Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 20, 2009 EDUCATE ENGAGE EMPOWER 1

Agenda Completed Construction Projects LAC Central Plant LAC Learning Resource Center Building Q and R Roof Replacement Building P Faculty Restroom Upgrade Current & Upcoming Construction Projects LAC South Quad Complex LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements – Phase 3 LAC Q & R ADA/HVAC Upgrades LAC Q & R ADA/HVAC Upgrades PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide - Master Landscape Plan District Wide - Marquee Signage Plan District Wide - Energy Retrofits District Wide - Energy Retrofits Los Coyotes Property Upcoming Projects Planned Phasing of Future Projects Q & A 2

Construction Complete Adds 10,000 ASF to existing building Substantial Completion Anticipated April 2009 Ribbon cutting scheduled April 24 th, 2009 LAC/Learning Resource Center – Measure E Completed Construction Projects

Central Plant equipment, Public Safety, & Field House for Athletics Final FF&E installation underway Plant ready for operation and awaiting completion of LRC & SQC Construction Complete Anticipated startup 12/05/08 LAC Central Plant – Measure E Completed Construction Projects

5 Construction completed Replaced existing roof with modified bitumen roof system. Existing skylights were removed and installed new skylights. All broken tiles were replaced on all perimeter edging of both buildings. Building Q and R Roof Replacement Measure E 2008

Completed Construction Projects 6 Provides two new ADA compliant restrooms in lieu of the existing staff restrooms. Installation of new wall and framing, redesign layout, finishes, fixtures and doors. New fixtures and restroom accessories have been installed throughout. Finishes will match existing building décor. Building P Faculty Restroom Upgrade Measure E 2008 Measure E 2008

Current and Upcoming Construction Projects Construction approx. 93% Complete Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office suites Multipurpose room State of the art Board Room Substantial completion anticipated Summer 2009 South Quad Complex – Measure E

Current and Upcoming Construction Projects Design Development phase completed Adds 4,000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Spring 2010 LAC Building A – Student Services Retrofit Measure E

Current and Upcoming Construction Projects Completed Schematic Design Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction 2012 LAC Math Technology Building – Measure E

Current and Upcoming Construction Projects LAC Parking Structure – Measure E Planning initiated for approximately 900 Vehicles To be procured under Design Build Delivery method Final Design Criteria completed To be located Southeast corner of Lot J adjacent to the Verizon building Photovoltaic Electrical Generation Array on top level of structure Anticipated start of construction 2010

Current and Upcoming Construction Projects LAC Building O Complex – Measure E Property acquired December 2008 Two structures totaling 87,000 square feet Potential occupants to be ACIT, District Warehouse Facility, ERD, and Foundation Office Warehouse temporarily located in building 2 Foundation Offices under Design Development

Current and Upcoming Construction Projects LAC Infrastructure Improvement Projects Measure E Planning underway with engineers 75% of Design Phase completed Completes chilled water lines to North side of campus Includes other major utility upgrades; Reclaimed Water, Domestic Water, Data, etc. Existing building HVAC systems to be upgraded in synch with infrastructure improvements Coordinated with modernization, quick start projects, and Master Landscape Project

Current and Upcoming Construction Projects 13 Whole building ADA upgrade: includes restrooms, stairlift (Bldg. R) All new infrastructure: new piping, etc. (Bldg. R) Minor renovations to offices (Bldg. R) Total renovations of locker/training room (Bldg. R) HVAC upgrade: includes new air handlers, ductwork, etc. (Bldg. Q & R) Update fire alarm system (Bldg. Q & R) Construction will be done in phases so as to minimize disruption of classes Final construction documents to be submitted to DSA May 2009 Estimated start of construction Spring 2010 LAC Q & R ADA/HVAC - Measure E 2008

Current and Upcoming Construction Projects Modern facility houses Welding Department and other trade programs Construction is 60% complete Replaces existing antiquated structures New Northern face of the campus Completion anticipated late summer 2009 PCC Industrial Technology Center Phase 1 Measure E

Current and Upcoming Construction Projects 90% construction documents submitted Swing space planning completed 9/2008, construction of swing space starts Summer 2009 Anticipated start of MDAB construction Fall 2009 To be completed in two phases PCC MDAB (Multi-Disciplinary Academic Building) Measure E

Current and Upcoming Construction Projects PCC Building CC Retrofit - Measure E To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. FF) To be completed concurrently with MDAB project Anticipated start of construction Spring 2010

Current and Upcoming Construction Projects District Wide – Master Landscape Plan Measure E 2008 Measure E Planning completed December 2008 Plan to be implemented concurrently as each Bond construction project finalizes Designed for long term sustainability of campus and neighborhood

Current and Upcoming Construction Projects District Wide – Marquee Signage Plan Measure E 2008 Measure E District Wide Signage Plan complete Currently in construction document phase Final site location determined Securing city permits at this time Planned completion late Fall 2009

Current and Upcoming Construction Projects 19 Phase 1 – Construction of Central Plants The chillers at the Central Plants were selected to achieve maximum efficiencies both at part load and full load conditions. The plant not only reduces the peak electrical demand at the campus but also offers lower emissions thus reducing the impact on the environment. Received rebates from Southern California Edison LAC Central Plant Designed to have (2) 600 ton centrifugal chillers and (1) 300 ton chiller with space for a future 600 ton chiller. The Central Plant is designed to serve most of the existing buildings and all the new buildings at the campus. PCC Central Plant Designed to have (2) 300 ton centrifugal chillers and (1) 300 ton multi-stack chiller. The Central Plant is designed to serve most of the existing buildings and approximately three new buildings at the campus. District Wide Energy Retrofits - Measure E 2008

Current and Upcoming Construction Projects 20 Phase 2A (99% Complete) Lighting upgrades HVAC upgrades Controls upgrades Pool upgrades Water systems upgrades Hot water system upgrades Re-roofing Phase 2B (Design Phase) HVAC upgrades (Air Handlers, Zone upgrades, tie to Central plant, etc.) Controls upgrades Lighting Upgrades (Interior/Exterior/Lighting controls) Hot water system upgrades Irrigation Controls Window film addition District Wide Energy Retrofits - Measure E 2008

Current and Upcoming Construction Projects 21 Re-design current dirt lot to have 80 parking stalls with new lighting and drainage. (Awaiting City feedback) Re-slurry and re-stripe existing asphalt parking lot. ( Done ) Retrofit hand rails and courtyard entry fencing/gates. (Done) Replace elevator controls to bring them up to new current standards. (In process) Installation of new automated front door. (In process) Building/Monument Signage & Interior Signage upgrade with Tenant/Suite names. (In process) Refinish exterior aluminum mullions. (In process) Building exterior wood/stucco repairs and painting. (In process) 2 nd floor deck repair/resurfacing. (Bids received) Building perimeter landscape upgrade. (In process) Replacement of gutters. (Done) Los Coyotes Property - Measure E 2008

Current and Upcoming Construction Projects 22 LAC Carson Street Median Fence Replacement (Construction starts April 2009) Pool boiler upgrade (In process) Replace current heating system with energy efficient boilers. Bldg. F - Conversions of rooms F104 and F106 to new classroom space. (Awaiting structural calculations) Expansion of Building I (In Design Phase) Bookstore to be relocated here Relocate Bond Management Team Offices to O Building Complex and removal of W trailers (December 2009) Increase parking at Faculty and Lew Davis St. PCC MM (FPP) Exterior renovation (In Process) Paint, windows, replacement of all exterior doors Restroom ADA upgrade (In Process) Upcoming Projects

Planned Phasing of Future Projects 23 Currently Planned Schedule Parking Structure – Design/Build concept Anticipate awarding bid Summer 2009 Moving Warehouse from PCC to Building O at LAC – (Done) LAC/PCC Building Needs Assessment Projects Bathroom Improvement Projects Quick-Start Projects Lighting Projects Classroom Improvement Projects Infrastructure Projects Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC and MM Project at PCC

Planned Phasing of Future Projects Install portables at PCC for Swing Space – Summer 2009 Master Landscaping and Signage plans complete Marquee signage anticipated to be installed Fall 2009 Moving LAC Building A into Swing Space – Spring 2010 Begin construction of Building A at LAC Anticipating start at end of Summer 2010 Begin construction of Buildings CC, DD, and EE at PCC Anticipating Fall 2009 start Begin Schematic Design for Buildings C and F at LAC Submit plans to DSA no later than March 2010 Begin Master Landscaping and Signage Initiatives Continue District Wide Energy Efficiency Improvements Phase IIA (99% complete) Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover, Roof replacement, etc Phase IIB (In Design Phase) Upcoming advancements include connecting current buildings to Central Plant infrastructure Currently Planned Schedule

Planned Phasing of Future Projects Anticipated Construction completion of Building A at LAC – Fall 2011 Submit plans to DSA for Math/Technology Building at LAC Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – late Fall 2011 Construction completion of Buildings CC, DD and EE at PCC Begin construction of Buildings AA and BB at PCC Anticipating Spring 2011 start Currently Planned Schedule

Planned Phasing of Future Projects Begin construction of Math/Technology Building at LAC Submit plans to DSA for M/N Building at LAC Anticipated Construction completion of Buildings C and F at LAC – December 2012 Anticipated Construction completion of Math/Technology Building at LAC – December 2012 Begin construction of Buildings M/N at LAC – January 2013 Anticipated Construction completion of Buildings AA and BB at PCC – June 2013 Currently Planned Schedule

QUESTIONS & ANSWERS EDUCATE ENGAGE EMPOWER 27