Lessons Learned and Earned Value Management System Assessment

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectF-to-F, March, TrackerR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face March Meeting Robert Johnson.
Advertisements

GLAST LAT ProjectLAT Face to Face, July 17-18, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center
GLAST LAT ProjectLAT I&T Subsystem CDR, March 28, 2003 Document: LAT-PR Section 4 - Page 1 GLAST Large Area Telescope: I & T Peer Review Performance.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
GLAST LAT ProjectOctober 14, 2002 Tracker, WBS GLAST Large Area Telescope: Tracker Subsystem WBS Engineering Meeting Tracker Engineering-Model.
GLAST LAT ProjectEngineering Meeting, April 1, GLAST Large Area Telescope Engineering Meeting Quality Assurance And Manufacturing Preparations April.
GLAST LAT Project Engineering Meeting – ISOC Peer Review 1 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope ISOC Peer Review ISOC Detail.
GLAST LAT ProjectEngineering Meeting, December 3, GLAST Large Area Telescope: Engineering Meeting December 10, 2002 Lowell A. Klaisner Stanford.
GLAST LAT ProjectSubsystem Managers Face to Face, November 17, GLAST Large Area Telescope: Darren Marsh Stanford Linear Accelerator Center Performance.
GLAST LAT Readout Electronics Marcus ZieglerIEEE SCIPP The Silicon Tracker Readout Electronics of the Gamma-ray Large Area Space Telescope Marcus.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 15 Manufacturing & Processes 1 GLAST Large Area Telescope Manufacturing.
GLAST LAT ProjectF2F, June 15, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety Assurance Manager.
GLAST LAT Silicon Tracker Marcus ZieglerIEEE The Silicon Tracker Readout Electronics of the Gamma-ray Large Area Space Telescope Marcus Ziegler.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
System Safety & Mission Assurance (SS&MA) for Sub-Class D Missions Steve Jara NASA Ames System Safety & Mission Assurance Division.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
GLAST LAT Offline SoftwareWorkshop - SLAC, Jan , 2001 R.Dubois Lehman Review Feb Joint NASA/DoE review My understanding: –“The purpose of the.
GLAST LAT ProjectF-to-F, June 15, TrackerR.P. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face June Meeting Robert Johnson.
PMSS Final SOW May 22 nd, Statement of Work 2 GLENN RESEARCH CENTER PROJECT MANAGEMENT SUPPORT SERVICES (PMSS) The Contractor shall provide expert.
Particle Physics and Astrophysics (PPA) Mechanical Engineering Ken Fouts.
Slide 1V&V 10/2002 Software Quality Assurance Dr. Linda H. Rosenberg Assistant Director For Information Sciences Goddard Space Flight Center, NASA
C osmic R Ay T elescope for the E ffects of R adiation PERFORMANCE ASSURANCE BRIAN KLATT MISSION ASSURANCE MANAGER.
GLAST LAT ProjectMarch 24, D Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS D: Composite Panel Fabrication.
GLAST LAT ProjectMonthly Review, November 3, 2004 Tracker SubsystemP. S. Drell 1 GLAST Large Area Telescope: Tracker Subsystem WBS Persis S. Drell.
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Engineering Model Tower.
National Aeronautics and Space Administration November 23, Gamma-ray Large Area Space Telescope (GLAST) Kevin Grady, Project Manager Steven Ritz,
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
GLAST LAT Project DOE/NASA Review, March 31, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
1 Stepping in everyone’s toes ( but for a good cause….) Eduardo do Couto e Silva Software Meeting – January 2001.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: EM Mini-Tower Robert Johnson.
SPACE SHUTTLE PROGRAM Space Shuttle Business Office NASA Johnson Space Center, Houston, Texas Presenter Date Page 1 Space Shuttle Program Flight and Ground.
GLAST LAT ProjectMarch 24, C Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS C: Electronics Module Testing.
GLAST LAT ProjectMonthly Status Review – Nov 3, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review Project Overview 1 Presentation 1 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review W.
GLAST Large Area Telescope:
Procedure for MCM rework on tray MID 070
GLAST Large Area Telescope Instrument Science Operations Center
GLAST Large Area Telescope:
Tower 8 – X6 anomaly MRB Meeting – 24 August 2005.
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Mechanical Integration
Mini-Tower test results
GLAST Large Area Telescope:
Enterprise Content Management Owners Representative Contract Approval
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Large Area Telescope Project
Management Breakout: MREFC Budget Summary Victor L
BRIAN KLATT MISSION ASSURANCE MANAGER
Thermal Vacuum Test: Plans and Procedures
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Integration and Test Organization Chart
March ’05 Face to Face Meeting Introduction
Introduction and Overview
Project Management Issues John N. Galayda, SLAC April 24, 2002
GLAST Large Area Telescope:
Overview Cost to Complete
GLAST Large Area Telescope:
GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4
Presentation transcript:

Lessons Learned and Earned Value Management System Assessment Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu 650-926-2726 Lessons Learned and Earned Value Management System Assessment

Background Pathfinder project First flight instrument integrated at SLAC Most of the staff at SLAC were unfamiliar with the effort required to meet space instrumentation requirements Challenging project Largest silicon detector, 800K channels Limited bandwidth to ground Event processing on board Space qualifying state of the art instrumentation Rigorous requirements of space instrumentation Low power Withstand launch loads Vacuum Challenging thermal environment Reliability

EVMS Assessment The EVMS system could not anticipate problems that arose from insufficient engineering in critical areas early in the project and showed up in environmental testing as the project moved into the flight hardware fabrication phase The EVMS system did not track earned value for work being done by foreign partners on independent budgets (eg the work in Italy supported by INFN and ASI) The GLAST mission office exercised rigorous control of the requirements while the Office of Science exercised rigorous control of the funding which limited ability to respond to cost growth and schedule stretch out

Tracker example of anomaly response Technical Issue Tracker (Past Year) Root Cause Incurred Delay (months) Bias circuit design error and coupon plating problems. Design Problem MCM and cable termination resistors. MCM-sidewall clearance issues. 1 Pitch-adapter flex circuit trace cracking. Process Problem Cable-closeout short circuit. Encapsulation of wire bonds on heavy trays. Bonding of Kapton bias circuits to tungsten. 3 Tracker-Grid interface fastener failure and alignment issues. Design and Process Problem 9 MCM encapsulation delamination. PWB short circuits. ASI funding problems. Funding Problem Conformal coating workmanship. Flex-circuit cable via problems. Flex-circuit cable workmanship problems.

Lessons Learned The Joint Oversight Group is too removed to resolve schedule and funding issues for the project When a DOE laboratory takes on a project in a new discipline such as GLAST, extra effort is required at the beginning to assure that the scope of the project is well understood. Also, the new infrastructure that is required needs to be identified and adequately planned Facilities Staffing – particularly special expertise required Management staffing, systems and procedures The DOE does not have the technical staff, QA support, management support, and funding flexibility that are available from the GLAST Mission Office In particular, lack of funding flexibility limited the DOE’s ability to assist in identifying the issues and provide adequate response The DOE TEC was defined before the project was adequately engineered GLAST predates PED funds

Path Forward SLAC now has the facilities in place to integrate a space instrument Key staff are in place to execute future space-based instrumentation projects In particular, a strong data acquisition system staff is in place with experience with space hardware and software The Kavli institute is attracting renown astro-physicists Executing key science with GLAST Planning and executing future astro-physics projects.