Presentation is loading. Please wait.

Presentation is loading. Please wait.

Large Area Telescope Project

Similar presentations


Presentation on theme: "Large Area Telescope Project"— Presentation transcript:

1 Large Area Telescope Project
Gamma-ray Large Area Space Telescope GLAST Mission Large Area Telescope Project Lowell A. Klaisner, Project Manager Stanford Linear Accelerator Center Project Status March 31, 2004

2 Introduction The transition to the first flight units has had the expected challenges and impacts The LAT team is effectively stepping up to solve problems Producing flight hardware First tower integrated with the grid this fiscal year Tight, success-oriented schedule We will see risk to the instrument delivery date until we have established a production rate history Plan has 9 weeks float to delivery for observatory integration Overall project contingency is OK Project is 65% complete Contingency is 29% of cost to go Funding in the current fiscal year is an issue All funding for FY04 is allocated

3 GLAST MISSION SUMMARY Objective: Larger field of view (FOV), higher sensitivity, and broader energy detection range than any previously flown gamma-ray mission. Mission Duration: 5 yrs (10 yr Goal) Orbit: km Circular, 28.5° Inclination Launch Date: February 2007 Launch Vehicle: Delta 2920H-10 Launch Site: Kennedy Space Center

4 GLAST Observatory LAT GBM NaI Sensors LAT Radiators Solar Array
GBM BGO Sensors +Z Spacecraft +Y +X

5 Instrument Structure Anti Coincidence Detector 16 Tracker Modules Grid
16 Calorimeter Modules Electronics Modules Radiators Mass 3000 Kg Power 650 Watts

6 LAT Organization Chart
Collaboration Science Team Principal Investigator P. Michelson Instrument Scientist S. Ritz EPO L. Cominsky Senior Science Advisory Committee N. Gehrels Project Manager L. Klaisner D. Horn J. Martin D. Nicholson, Admin Instrument Science Performance S. Ritz Instrument Advisory Committee S. Kahn Deputy for Systems D. Horn Project Controls T. Boysen Design Integration & Analysis M. Nordby Mission Assurance D. Marsh Electrical Integration G. Haller Manufacturing Eng. J. Clinton System Engineering P. Hascall Integration &Test E. Bloom TKR R. Johnson CAL N. Johnson ACD D. Thompson Mechanical M. Campell DAQ & FSW G. Haller ISOC W. Craig (acting) D. Lung, Deputy SAS R. Dubois

7 Partner Contributions to LAT
Calorimeter Tracker ACD Grid Tracker (TKR) - Italy (ASI/INFN): provide Si-strip detectors & assemble & test TKR modules - Japan: provide Si-strip detectors & oversee detector production - SU-SLAC & UCSC (USA): provide Si-strip detectors, front-end electronics, cable plant, components Calorimeter (CAL) - IN2P3 (France): mechanical structure - Sweden: CsI xtals & acceptance testing - NRL (USA): Fabricate, assemble and test CAL modules Anticoincidence Detector (ACD) - GSFC (USA) Fabricate, assemble and test the ACD including micrometeoriod shield / thermal blanket Data Acquisition System (DAQ) - SU-SLAC & NRL (USA): Data acquisition hardware & flight software Mechanical/Thermal System - SU-SLAC (USA): provide LAT Grid, thermal radiators, heat pipes & ancillaries LAT Integration & Test - SU-SLAC (USA): assembly & test of LAT - NRL (USA): instrument-level environmental tests All partners contributing to science analysis preparations: software, science simulations

8 International agreements
MoAs between Stanford Univ-SLAC and: INFN, ASI, Italy pending signature IN2P3, France; NRL  revised & signed CEA/DSM/DAPNIA, France; NRL  revised & signed Royal Inst. of Technology & Stockholm Univ., Sweden; NRL  signed Hiroshima Univ., ISAS & RIKEN, Japan; UCSC/SCIPP  signed NASA – Department Of Energy  signed Agency level agreements NASA – CNRS/IN2P3 Agreement pending; draft exchanged NASA – CEA Agreement  signed NASA – ASI Agreement pending; draft exchanged NASA – Japan draft sent to JAXA NASA – Sweden draft in process

9 Budget, Cost, Funding, Performance

10 Cost and Schedule Variance
1 month MAR03 APR03 MAY03 JUN03 JUL03 AUG03 SEP03 OCT03 NOV03 DEC03 JAN04 FEB04 BCWS 49,452 52,780 55,210 57,854 60,114 62,777 66,081 69,052 69,801 73,433 77,394 81,916 BCWP 46,114 49,627 51,835 54,564 56,229 58,348 60,548 62,648 69,724 73,353 76,574 80,742 ACWP 45,435 48,344 51,125 54,402 57,264 59,429 61,990 63,894 67,721 71,081 74,989 78,460 CV 679 1,283 710 162 -1,035 -1,081 -1,443 -1,246 2,003 2,271 1,585 2,281 SV -3,338 -3,152 -3,375 -3,290 -3,885 -4,428 -5,533 -6,404 -76 -80 -820 -1,175

11 Contingency Analysis (K$)

12 GLAST Mission Office Support in FY04
The GLAST mission management and the LAT project management identified areas were additional manpower would help assure that the project meet its goals. The mission office added funds to the project for this additional staff. Integration and Test Staff $ 523K Tracker Staff $ 738K Performance and Safety Assurance $ 973K Flight Software Staff $ 747K Total $2,981K In addition, the mission office added funds to support the costs associated with the following CCB actions: ACD Mechanical Materials and Support $ 195K ACD Photomultiplier Anomaly Resolution $ 299K ACD Base Electronics Assembly $ 222K ISIS Scope Change $ K Total $ 810K Total funds added $3,791K Also, the Mission Office has provided technical support Thermal Engineering EMI/EMC Engineering Tracker and ACD Management Mechanical Analysis

13 History of the Budget at Complete Since Rebaseline

14 BAC projections to end of project
Contingency available $12,447K 29% of cost to go Allocation of project contingency since rebaselining Between the end of July 03 and the end of February 04 Earned value $24,513K Allocation of cont. $ 4,879K Percentage % Rate of Allocation over the last 7 months $697K per month Projection at this rate for the remaining 16 months $11,152K Cost risk will decline as project matures Rebaseline

15 FY04 Cash Flow Planned costs March through September $29,108K
* Mission office moved $500K of LAT funding from FY 05 to FY04 Planned costs March through September $29,108K Project additional funds needed on FY04 At $697K per month $ 4,182K At 20 % of costs (recent experience) $ 5,821K At 29% of costs (rate for the remainder) $ 8,441K Mitigation Move activities into FY05 $5,000 Bridge available from Stanford University Mission office move NASA funding forward, if available

16 Potential Liens

17 LAT Schedule

18 Completion Dates (baseline variance)
LAT Critical Path Tracker Bottom Tray Parts 4/9/04 (0) Assemble Tracker Towers A-12 11/26/04 (0) Integrate Tkr/Cal Towers 12-14 2/3/05 (0) Integrate LAT-Wide Electronics 2/25/05 (0) Integrate ACD 3/15/05 (0) Integrate Cross-LAT Plate 3/18/05 (0) System Test 6/6/05 (0) Ready for CD-4 and Pre-Environmental Test Review 6/7/05 (0) Completion Dates (baseline variance)

19 Threats to Schedule Path to Integration and Test of Tower A
Completing detailed documentation Getting fabrication contracts in place Anomaly in qualification testing Path to Integration and Test of the complete instrument Achieving planned production rates Execution of I&T plans Rapid response to anomalies Path to Environmental Test (CD-4) Anomalies requiring de-integration Rapid analysis of and response to anomalies

20 Level 1 and Level 2 Milestones

21 Technical Status

22 Closed Issues CDR/CD-3 Loss of CNES funding
Successfully transferred work to the US Funded at the rebaseline ASICs All flight ASICs are delivered No unresolved problems CAL-GRID joint Added “Menning Plates” Issue closed Cross LAT plate thermal connection Chose direct connection between DAQ boxes and plate Rebaseline Review Tracker bottom tray design Design complete and parts in fabrication

23 Subsystem Status 1 Data Acquisition (SLAC)
Out for bid for the flight Tower Electronics Modules Designs of all cards exist and prototypes in test Flight Software peer review 2/26/04, monthly software demonstrations Tracker (UCSC, SLAC, INFN) Production planning readiness workshop held in Italy Thermal-Vacuum test of the engineering model complete Flight production underway Silicon ladders (30% complete), Multi Chip Modules, mid-trays, and bottom tray components Need to complete the flight documentation and testing Mechanical (SLAC) Flight GRID being machined Thermal (SLAC) Flight heat pipes in fabrication (Lockheed Martin)

24 Subsystem Status 2 Calorimeter (NRL, IN2P3)
Flight production well underway 80% of CsI crystals in hand 25% of CDEs have been manufactured Flight ASICs (~12,000) have been tested All machined parts and 3 flight structures are complete Anti-Coincidence Detector (GSFC) Flight scintillator detectors, phototube and electronic assemblies and the structure are in production Integration and Test (SLAC) Facilities are ready to begin flight integration in August Plan in place for support equipment and procurement started I&T Kickoff held in March Instrument Science Operating Center (SLAC, SU, KIPEC, Collaboration) Planning underway Manager in place by end of Summer (Bill Craig, Acting) Science Analysis Software (SLAC, Collaboration) Initial suite of software tools in place Highly successful Data Challenge 1

25 Summary No major outstanding technical issues
Analysis and testing continues Producing flight hardware One tower integrated in the grid this fiscal year Tight, success-oriented schedule Overall project contingency is OK Project is 65% complete Contingency is 29% of cost to go Funding in the current fiscal year is an issue All funding for FY04 is allocated Continued strong support from NASA, DOE, and the Collaboration A strong, talented and committed staff

26 Backup Slides

27 Cost Performance Report

28 Contingency Analysis

29 History of Cost Estimate

30 Planned Staffing


Download ppt "Large Area Telescope Project"

Similar presentations


Ads by Google