VELO-installation meeting CERN, January 17, 2006

Slides:



Advertisements
Similar presentations
& Géraldine Conti May 21, 2007Monday Seminar 1 Detector Boxes Fiducialisation IT Frame Survey.
Advertisements

14 June 2007VELOEddy Jans 0 Recent VELO-installation++ activities June 14, 2007 Potmeter calibration Bake-out Cabling & Commissioning.
7 September 2006VELOEddy Jans 0 VELO-installation September 7, 2006 installation of exit window + part I of the beam pipe logging of vacuum data what’s.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
Walls crates cables gas chambers electronics CERN adb.
Setup of laser tracker on DX side NOTE: X axis along M1s centers, towards SX Z axis along M1-M2 centers, towards M2.
EA meeting, Wednesday 6 Dec 2006 TT installation, Jeroen van Tilburg 1 TT installation Installation of the TT station.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
18 June 20031Integration Review B. Schmidt Outline: Filter design and basic concept to ensure seismic stability Filter Installation and the required tooling.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
TGC Big wheel Sector assembly plan Tatsuo Kawamoto ATLAS workshop 2005.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
Preparation of wall position Alignment of A and C side in closed position Creation of reference system Translation of reference system to open position.
Notes After TIG 17/7/08 HF+ Move out of garage: Aug 15* Platform+table+collars+racks+BP support (jack up for platform) = 3 days Controls for motors = 1.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Alignment (results by Jo van den Brand) Preparing IP 8 Velo arrived at IP 8 Preparing UXA C3 Installation transfer lines for the cooling system Next steps.
Undulator Orientation & Electron Beam Spacing Should the undulator frames be toward the central aisle or the tunnel walls? What is the optimum spacing.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
1 Fulvio TESSAROTTO the new RICH beam pipe the new RICH beam pipe - pipe production, gluing and tests - measurement and removal of the old pipe - fixation.
Forum March 2003H.Taureg1 Magnetic Fields in ALICE Mapping and Monitoring.
BPM support and beam pipe length FD support status A.Jeremie.
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
LHCb Experimental Area Meeting V. Bobillier1 Earth network in UX85 experimental cavern.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
Integration with LDC & Push-pull impact on LumiCal Wojciech Wierba Institute of Nuclear Physics PAN Cracow, Poland FCAL Workshop, LAL Orsay,
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
18 June 20031Integration Review B. Schmidt Outline: Overview of the support structures Requirements –Some details on electronics, cabling and piping Constraints.
Services in GIF++ A pictorial record of the work HV Cables LV cables DCS cables Signal Cables Ian Crotty 17 Dec 2014.
Vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand LHCb Vertex Detector System: Status Report J.F.J. van den Brand.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
25 January 2007VELO sub-projectsEddy Jans 0 VELO-meeting January 25, 2007 Sub-projects: SX & SX connectorize cooling cables alignment procedure.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
LHCb MUON - ADDITIONNAL SHIELD BEHIND M5 – UNIT AREA Dimensions of 1 iron brick  100 x 100 x 200 mm3 1 ROW of 1200 mm length  12 iron blocks.
Status VELO alignment 1.Alignment at IP8 Jo van den Brand Frans Mul June 2, 2006.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
TB Peter Glässel, Heidelberg1 Preparing TPC Installation.
VELO Integr - Jan06Jean-Christophe GAYDE TS/SU EDMS n° SURVEY FOR VELO INSTALLATION 1.SURVEY AT GROUND FLOOR - FIDUCIALISATION 2.SURVEY FOR INSTALLATION.
1) News on the long scale length calibration 2) Results of the two surveys performed on plane 7 Set 1: morning of 12/11/2004 Set 2: morning of 19/11/2004.
Status VELO alignment 1.NIKHEF 3D measurements 2.Photogrammetry 3.Calliper checks in x-direction 4.Photogrammetry again Jo van den Brand May 23, 2006.
Baby Mind C OIL DESIGN AND ASSEMBLY SCENARIOS Helder Silva Phillipe Benoit Alexey Dudarev Gabriela Rolando Herman ten Kate Etam Messomo Laurent Nicola.
1 Chamber Interfaces Adalberto Readout-, I2C-, HV-, LV-, Gas- and chamber support interface. Space issues.
Plans for the UT Installation LHCb infrastructure workshop February Burkhard Schmidt for the UT group.
Ferrara MECHANICAL SUPPORT for forward tracking detectors Federico Evangelisti INFN - Ferrara GSI – 2-6 march 2009.
STRAW TRACKER SYSTEM CAD STATUS :
Update of MVD services and requests
Beam
E. Noah, A. Blondel, P. Benoit, F. Cadoux, A. Dudarev, L. Nicola, H
LS1 planning meeting
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
$150K Chicago/ANL seed funding for Braidwood site investigation
Ongoing and to do work M.Lenti.
VELO Metrology CERN Metrology Lab (EST/MF)
EHN1 Neutrino Installation Plans
A very first look at siting issues
Far Detector Activities Late 2017 – Early 2018
ACS news Circulator TCU: control tests in progress All cavity racks
Sebastian Bachmann University of Heidelberg Henk Schuiljenburg NIKHEF
OT Survey & Adjustment Outline: Survey technique
VELO-meeting January 25, 2007 Sub-projects: SX & SX
Cryomodule Assembly Plan
VELO RICH 1 INSTALLATION PLATFORM BALCONY BALCONY
Polarized 3He target installation
Presentation transcript:

VELO-installation meeting CERN, January 17, 2006 preparation IP8-area photogrammetry @ SX8 moving SX8 -> IP8 alignment @ IP8 UXA-C3 platform cables planning 19 January 2006 installation

preparation IP8-area 4 bolts for skates will only be bolted not bolted & glued. height needed for hook of crane ?? install crane. we drill holes for consoles for service platform and for LV- and HV-boxes. differential circuit breakers -> interaction with magnet ON, i.e., problems with regular 220 V. ≤1 cm of surface of concrete console can be used for egalisation. Correct ?? cleaned and painted. beam lines on floor and wall. What length + more lines needed ?? TL-illumination 19 January 2006 installation

photogrammetry @ SX8 shaft 2.5 m free space needed on each side Centre Frame Fiducial Marks 2.5 m free space needed on each side of VELO-tank NIKHEF levels setup on floor photogrammetry uses 5 fiducial points on each side of center frame NIKHEF makes extensions for spheres from 3 -> 20 mm 19 January 2006 installation

photogrammetry @ SX8 Next determine detector positions via 8 reference points on the “shell gauge”. SHELL GAUGE 19 January 2006 installation

moving VELO SX8 -> IP8 VELO corner 19 January 2006 installation

magnet moving VELO SX8 -> IP8 RICH1 Send actual VELO-dimensions (without hoods) to Olivier Jamet. 19 January 2006 installation

moving VELO SX8 -> IP8 Correct dimensions of skates assumed ?? 19 January 2006 installation

alignment @ IP8 first RICH1 needs to be put back rough positioning by NIKHEF by means of beam line projections on floor and walls precise alignment by CERN with theodolites: Dx = Dy = Dz = 0.5 mm (1s) Df = 0.1 mrad in polar angle nominal position of detectors inside is based on reference marks on the outside of the tank. This procedure requires rapid conversion and feedback, i.e. preparation beforehand. 19 January 2006 installation

UXA-C3 platform layout in EDMS 679336 cable trays arrive at the top do the cables enter PLC racks from top/bottom ?? how about Adriana’s rack ?? dimensions chiller racks ?? lekbak needed under chillers. 19 January 2006 installation

cables front view extra duct in existing trays top view by middle of March cable order needs to be checked pull cables a.s.a.p. top view 19 January 2006 installation

planning all IP-8 preparations done or almost done before we decide to move arrival of VELO-setup @ CERN defines t=0 dismantling @ NIKHEF starts at t=-3 weeks positioning and photogrammetry @ SX8 takes 1 week going 100 m down + pass behind magnet to IP8 takes 1 week put back RICH1 + rough positioning takes 1 week install dust covers iterative alignment procedure with theodolites takes 1 week installation of pumps, pipes, power, etc. can then start installation of service platform foreseen around mid April when the mounting of connectors can start depends on pulling of cables. final schedule will be made in the course of next week by Rolf Lindner after news from exit foil + beam pipe. in present preliminary schedule t=0 is on Wednesday March 15 -> start packing at NIKHEF on Wednesday February 22 -> 4.5 weeks left for testing at NIKHEF 19 January 2006 installation