EHN1 Neutrino Installation Plans

Similar presentations


Presentation on theme: "EHN1 Neutrino Installation Plans"— Presentation transcript:

1 EHN1 Neutrino Installation Plans
M.Ne

2 Table of Content Scenario until end April
Schedule for the next 3 weeks General schedule until end April Work organization

3 Scenario until end April

4 From Aug-16 to Apr-17 Area 164 Clean room + SAS Clean room area 164
PPE Area 164 PPX NP02 NP04 Lar pump Clean room + SAS Stair 1 Stair 2 Lar pump SAS SAS MAT Clean room

5

6 NP04 and NP04 cryostats 12/06/16

7 Cold Membrane Vessel (LNG industry technology)
SS 1.2 mm primary membrane in contact with the liquid (primary containment) secondary membrane : composite laminated material (secondary containment) Insulation : reinforced polyurethane foam (5-6 W/m2) 12/06/16

8 Warm vessels External : Steel structure
Internal : 1cm thick Stainless Steel Modular structure Modules bolted together All structural analysis done and OK by HSE SS plates welded in between modules SS vessel must gas tight (10-16 mbar/sec) CERN contracts active 8x2 walls/roofs/floors 8x2x3 ~ 45 trucks First 2 trucks 16-17th Aug., second 2-3 trucks 5-6th Sep. Assembly at CERN done by a Collaboration team: eng CERN + 1 tec CERN + 5 tec JINR + 1 welder JINR + EN/HE transport + EN/SU surveyors NP04 vessel must finish by mid November 2016. Project engineer. : D.Mladenov/EP/DI

9 First the floor ! second trucks already on the road !

10

11 First assemble the floor on concrete blocks !!

12 First prepare the floor NP04 (1/3)
Week 33 : for details  Unload the 2 trucks outside EHN1-NE Prepare the lab in pitB (cabinets, tools, shims, …) Bring the concrete blocks in pitB + blocks positioning tool Position and survey the concrete blocks in position Pre-position the floor modules on the concrete blocks Fix the concrete floor non conformity (SMB) Prepare elastomers and G10 isolation sheets Prepare grounding safety line needed needed during assembly Prepare hydraulic to be used for bolting Prepare for vacuum test and dye penetrant test on SS Test all tools

13

14

15 First prepare the floor NP04 (2/3)
Week 34 : for details  Assemble and bolt the floor on the concrete blocks Prepare welding procedure Survey shape and dimensions Not done!!! If possible pre-position cryostat floor in its final location Weld in between modules the SS plates Dye penetrant tests and vacuum tests Glue G10 as isolator below the beams Pre-position elastomers and rubber

16 First prepare the floor NP04 (3/3)
Week 35 : for details  If not already done position the floor in its final position Connect safety ground Survey position If necessary correct position by shimming Receive next 3 trucks (29th) Start the same type of activities for the first wall as described for the floor week 33-34 Week : Repeat the schedule of the floor for each wall and roof Weld SS vessel corners Where necessary machine SS plates holes and weld local flange (on the roof) Check overall gas tightness Make a laser scan of the inside to define the final geometry when assembly is finished

17 Membrane cryostats SS 1.2 mm primary membrane in contact with the liquid (primary containment) secondary membrane : composite laminated material (secondary containment) Insulation : reinforced polyurethane foam (5-6 W/m2) Full engineering study contracted to the firm GTT in Paris (CERN contract) All the material necessary contracted to Korean licensed firms (CERN contracts) Material will arrive in ~16 sea containers 40’ between the 15th October and 10th November Installation contracted to a GTT licensed firm (CERN contract) which will start beginning of November. Both vessels will be operated at the same time. 15 person will be on side 3 persons of GTT will overview and control the process, including the QA We will do the final He leak checks with the mass spectrometer We have to provide all transport and cranes operation and garbage disposal One CERN Neutrino person will be the link between CERN and the firm for all what has to do with CERN services, daily planning and safety

18 LAr pump and valves Special valves engineered with GTT and a specialized firm 2 valves contracted by CERN LAr pumps on FNAL responsibity, already ordered Installation of pumps and valves part of the contracts Scheduled for January-February 2017

19 Clean rooms

20 Clean rooms

21 NP04 clean room In the final design phase
We have some preliminary offers These are class 100’000 grey rooms To be better defined are the rails and cranes inside for the detector QA and installation We should start a DO in September Installation in early 2017 NP02 room not yet designed

22 Schedule for the next 3 weeks

23 for details  https://edms.cern.ch/document/1712076
W33 W34 W35 week activity Mo Tu We Th Fr Sa So 33 in pitB RO-trucks unloading EN/HE move blocks in pitB (SMB) SMB move small mat. In pitB Prepare working lab Position blocks Survey activities EN/SU Test tools Move floor mod. to pitB Position modules on blocks Fix floor (SMB) Install compress air (EN/CV) EN/CV 34 Assemble floor on blocks Welds SS plates Welding QA Survey floor install G10 + shims install safety ground 36 Position floor in final position Move wall 1 mod. to pitB Assemble wall 1 on blocks

24 for details  https://edms.cern.ch/document/1712076
week activity Mo Tu We Th Fr Sa So 35 in pitB Assemble floor on blocks Survey floor install G10 + shims install safety ground Fix floor (SMB) Install compress air (EN/CV) EN/CV 36-37 floor Move floor mod. to pitB Welds SS plates Welding QA first wall Receive 2 trucks wall 1 RO-trucks unloading Position modules on blocks Assemble wall 1 on blocks Survey wall 1

25 General schedule until end April

26 EHN1-NE activities until April 2017
Activity W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W46 W47 W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W8 W10 W11 W12 W13 NP04 warm structure NP02 warm structure Korean material, arriving 30 containers NP04 cold structure installation NP02 cold structure installation Final QA on cold vessels NP04 Final QA on cold vessels NP02 NP04 main valve installation NP02 main valve installation clean rooms NP04 clean room assembly NP02 clean room assembly

27 What is urgent from our side
To get all yellow barriers in place To get a decent temporary light To have all building doors installed with the access system operational To have a decent WIFI coverage To define space in the hall where we can store for a few months (2-3) material To define parking space and access for workers to the building

28 A provocation!!! We need restrooms inside the hall
No way in winter to have people to go out to baracks in the fields The RP requirements should be put in discussion. If it is really true then all the beverage, coffee, water dispensers should go out too. I think there is room for a rational discussion!

29 Work organization https://edms.cern.ch/document/1716049