Project Management MGT 30725

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
CP Chapter 4 Schedule Planning.
Developing the Project Plan
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
A simple set of tasks in “timeline-schedule” form Req. Gathering Req. Analysis High Level Design Detail Design & Code Test Case DevelopmentTest Execution.
Developing a Project Plan
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Eleanor Roosevelt High School
PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH PROJECT NETWORK DIAGRAM.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 © 2007 Pearson Education.
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Project Scheduling. SEEM Project Scheduling (PS) To determine the schedules to perform the various activities (tasks) required to complete the project,
Project Management. What is a Project? One Time Effort Identifiable Start/End Points Specific Objectives Multiple Tasks Resources from Across the Organization.
Importance of Project Schedules
Project Management Dr. Everette S. Gardner, Jr.. Project Management2 PERT / CPM advantages 1. Disciplined planning 2. Realistic objectives 3. Unambiguous.
Project Time Management
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
© Construction Management Association of America. Do Not Duplicate or Reproduce. Standards of Practice Course CPM Scheduling Lab.
PMP, CAPM, PgMP, PMI-SP, PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services.
ENGM 631 Optimization Ch. 10: PERT/CPM. Great Pyriamid of Cheops (2,500 B.C.) 42,300,000 Stone Blocks 440 Stories 4Accuracy of 0.04 inch 413 acres level.
Software Project Scheduling By: Sohaib Ejaz Introduction A Gantt chart is a graphical representation of the duration of tasks against the progression.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management: PERT/CPM
Project Scheduling KULIAH 10 Magister Sistem Informasi
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Project Scheduling KULIAH 10 Magister Manajemen
Project Management for Business
Project Planning and Scheduling
Project scheduling Precedence diagram method & Resource scheduling
Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.
Project Scheduling Chapter 14.
Chapter 6: Project Time Management
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Project Management Planning Models
Developing a Project Plan
Project Scheduling: networks, duration estimation, and critical path
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Time Planning and Control Precedence Diagram
ENM448-Project Planning and Management
Project Management CPM Method Tutorial-p1
Project Time Management
Project Scheduling: Lagging, Crashing and Activity Networks
Project Time Management
Lecture 5: Project Time Planning (Precedence Diagramming Technique)
Slides Prepared by JOHN LOUCKS
LECTURE 3.
Project Time Management
Project Time Management
Exercise – A small building.
Project Time Management
Scheduling.
Presentation transcript:

Project Management MGT 30725 Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@gmail.com

Lesson 6 – The Project Schedule Agenda PERT and Critical Path Analysis

PERT (Program Evaluation Review Technique) Precedence Diagramming Method (PDM) Activity-on-Node (AON) Diagramming Method Method used in Critical Path Methodology (CPM) No dummy activities Activities are represented by boxes Arrows show relationships between activities Very popular and used by project management software Better at showing different types of dependencies

Sequence activities Leads and Lags Use leads and lags to support realistic and achievable project schedule. Each activity is connected at least to one predecessor and one successor except the start and the end. A B C predecessor Successor Lags Inserted waiting time between activities Leads May be added to start an activity before the predecessor activity is complete. A A B B

Sequence activities Leads and Lags FS – 2 days FS + 2 days A100 FOUNDATIONS A400 PLUMBING A400 - LEAD (Acceleration) by 2 days FS + 2 days A100 WALL PAINTING COAT1 A200 WALL PAINTING COAT2 A200 - LAG (Delayed) by 2 days (need to allow Coat1 painting to dry first before applying Coat2)

Sequence activities Project Schedule Network Diagrams Graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities Network diagram is produced manually or by using project management software.

Network Diagrams – Activity on Node (AON) Exercise: Draw an AON Network for the following precedence table

Network Diagrams – Activity on Node (AON) F C A Finish Start D B E

Network Diagrams – Exercise 1 Preceding Activity Succeeding Activity Start A100 A200 A300 A400 A500 A600 Finish Draw a network diagram based on the above table

Network Diagrams – Exercise 2

Network Diagrams – Exercise 2

Network Diagrams Task ID LS Float LF ES DUR EF ES – Early Start EF – Early Finish LS – Late Start LF – Late Finish DUR - Duration

Network Diagrams – Forward Pass One Predecessor Early Start (ES) = EFp ES = 3 Early Finish (EF) = Early Start (ES) + Duration EF = 3 + 4 = 7 A100 (Task 1) FOUNDATIONS ES EF A200 (Task 2) WALLS LS Float LF ES DUR EF Task ID ES EF May 1 May 2 May 3 May 4 May 5 May 6 May 7 May 8

Network Diagrams – Forward Pass Multiple Predecessor Early Start (ES) = Max(EFp) ES = 3 last completion date of all predecessors A100 ES EF A200 ES EF A300 ES EF A400 LS Float LF ES DUR EF Task ID ES EF May 1 May 2 May 3 May 4 May 5 May 6 May 7 May 8

Network Diagrams – Forward Pass LS Float LF 3 A100 LS Float LF 3 4 7 A200 FS Finish-to-Start A100 (Task 1) FOUNDATIONS LS Float LF ES DUR EF Task ID ES EF A200 (Task 2) WALLS ES EF May 1 May 2 May 3 May 4 May 5 May 6 May 7 May 8

Network Diagrams – Backward Pass One Successor Late Finish(LF) = LSs LF = 3 Late Start(LS) = Late Finish(LF) – Duration LS = 3 - 3 = 0 A100 (Task 1) FOUNDATIONS LS LF LS Float LF ES DUR EF Task ID A200 (Task 2) WALLS LS LF May 1 May 2 May 3 May 4 May 5 May 6 May 7 May 8

Network Diagrams – Backward Pass Multiple Successor Late Finish (LF) = Min(LSs) LF = 4 earliest completion all successors A200 (Task 2) WALLS LS LF A100 LS LF A200 LS Float LF ES DUR EF Task ID LS LF A300 LS LF May 1 May 2 May 3 May 4 May 5 May 6 May 7 May 8

Network Diagrams – Backward Pass Float 3 A100 3 Float 7 4 A200 FS Finish-to-Start A100 (Task 1) FOUNDATIONS LS Float LF ES DUR EF Task ID LS LF A200 (Task 2) WALLS LS LF May 1 May 2 May 3 May 4 May 5 May 6 May 7 May 8

Network Diagrams – Float/Slack Float = Late Start – Early Start 3 A100 3 7 4 A200 FS Finish-to-Start LS Float LF ES DUR EF Task ID

Critical Path Method (CPM) Critical Path is the longest duration path in a Network Diagram. IT identifies the shortest time needed to complete a project. There can be more than one critical path in a Network Diagram. Near-critical path is the path that has close in duration to critical path. Any delay to an activity in a Critical Path will delay the entire project. All activities in a Critical Path contains zero (0) slack/float.

Case Study - 1 Following activities were identified as main tasks for the computerization project. Draw the Activity on Node (AON) network diagram and mark the critical path for the project. TaskID Activity Time (weeks) Immediate predecessor A Analyse Requirements 6 ---- B System Design 8 C Finalyse the Architecture 4 D Database Design E System Implementation F Testing G UAT 12 H Parallel Run I Rollout 1 C,H

Schedule Compression Used to shorten the schedule duration without reducing the project scope. Crashing - used to shorten the schedule duration for the least incremental cost by adding resources. Examples of crashing include approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing works only for activities on the critical path where additional resources will shorten the activity’s duration. Fast Tracking - activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. An example is constructing the foundation for a building before completing all of the architectural drawings.

Group Work - Case Study - 2 Expected Duration - Exercise Refer ABC superMKT case study and answer questions

Lesson 7 – The Project Schedule Agenda Estimate Costs and income Creating a Preliminary Budget Budget and Schedule Balancing