1 Project Management for Business
Week 4 LSBM , Sept 2015 Project Management for Business

2 Outline Project Scheduling PERT/CPM

3 University of Nottingham
8/6/2018 Project Scheduling It is part of project management within the Planning phase of the Project Development Life Cycle. Project Scheduling: Allocate resources to execute all activities in the project. Maria Petridou

4 University of Nottingham
8/6/2018 Project Scheduling Objectives: Establish beginning, ending and duration of each activity in the project. Calculate overall completion time of the project given the amount of usually limited resources. Determine the critical path and its duration. Determine the slack time for all non-critical activities and the whole project. Maria Petridou

5 University of Nottingham
8/6/2018 Project Scheduling Phases: Define activities or tasks according to the project objectives. Identify precedence relationships or dependencies Estimate time required to complete each task. Draw an activity-on-arrow / activity-on-node PERT diagram. Apply CPM to calculate earliest and latest starting times, earliest and latest completion times, slack times, critical path etc. Construct a GANTT chart. Reallocate resources and resolve if necessary. Continuously monitor/revise the time estimates along the project duration. Maria Petridou

6 University of Nottingham
8/6/2018 PERT Diagrams Program Evaluation and Review Technique It is a network model that shows activity completion times and their precedence. Tool used to control the length of projects. PERT was developed in the late 1950’s for the US Navy. It has the potential to reduce both the time and cost required to complete a project. Maria Petridou

7 University of Nottingham
8/6/2018 PERT Diagrams 3 B D A F 1 2 5 6 C E 4 Single start node Single finish node Maria Petridou

8 University of Nottingham
8/6/2018 PERT Diagrams Activity-on-node Activity-on-arrow Maria Petridou

9 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method ET – Earliest node time for given activity duration and precedence relationships LT – Latest node time assuming no delays ES – Activity earliest start time LS – Activity latest start time EF – Activity earliest finishing time LF – Activity latest finishing time Slack Time – Maximum activity delay time Maria Petridou

10 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 A ( 3 ) D ( 5 ) 1 5 B ( 4 ) E ( 2 ) 3 4 C ( 7 ) Maria Petridou

11 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method Step 1. Calculate ET for each node. For each node i for which predecessors j are labelled with ET(j), ET(i) is given by: ET(i)= maxj [ET(j)+ t(j,i)] where t(j,i) is the duration of task between nodes (j,i). Step 2. Calculate LT for each node. For each node i for which successors j are labelled with LT(j), LT(i) is given by: LT(i)= minj [LT(j) – t(i,j)] where t(j,i) is the duration of task between nodes (i,j). Maria Petridou

12 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 A ( 3 ) D ( 5 ) 1 5 B ( 4 ) E ( 2 ) 3 4 C ( 7 ) Maria Petridou

13 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 A ( 3 ) D ( 5 ) 1 5 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) Maria Petridou

14 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 A ( 3 ) D ( 5 ) 1 5 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) 11 Maria Petridou

15 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 13 A ( 3 ) D ( 5 ) 1 5 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) 11 15 Maria Petridou 15

16 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 13 A ( 3 ) D ( 5 ) 8 1 5 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) 11 16 Maria Petridou 16

17 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 13 max A ( 3 ) 8 D ( 5 ) 1 5 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) 11 17 Maria Petridou 17

18 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 A ( 3 ) D ( 5 ) 1 5 13 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) 11 Maria Petridou

19 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) 11 Maria Petridou

20 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) 11 11 Maria Petridou

21 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 8 A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 C ( 7 ) 11 11 Maria Petridou

22 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 8 A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 4 C ( 7 ) 11 11 Maria Petridou

23 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 8 5 A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 4 C ( 7 ) 11 11 23 Maria Petridou 23

24 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 8 5 A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 4 C ( 7 ) 11 11 24 Maria Petridou 24

25 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 8 5 min A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 4 C ( 7 ) 11 11 25 Maria Petridou 25

26 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 8 A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 4 C ( 7 ) 11 11 Maria Petridou

27 CPM – Critical Path Method
University of Nottingham 8/6/2018 Step 3. Calculate processing times for each activity. CPM – Critical Path Method Task Duration ES EF LS LF Slack Critical Task A 3 5 8 No B 4 Yes C 7 11 D 13 E 2 Maria Petridou

28 CPM – Critical Path Method
University of Nottingham 8/6/2018 CPM – Critical Path Method 2 3 8 A ( 3 ) D ( 5 ) 1 5 13 13 B ( 4 ) E ( 2 ) 3 4 4 4 C ( 7 ) 11 11 Maria Petridou

29 Project Management Example: General Foundry Inc.
Have 16 weeks to install a complex air filter system on its smokestack May be forced to close if not completed w/in 16 weeks due to environmental regulations Have identified 8 activities

30

31 AON Network for General Foundry

32 Activity Time Estimates

33 Determining the Project Schedule
Some activities can be done simultaneously so project duration should be less than 25 weeks Critical path analysis is used to determine project duration The critical path is the longest path through the network

34 Critical Path Analysis
Need to find the following for each activity: Earliest Start Time (EST) Earliest Finish Time (EFT) Latest start time (LST) Latest Finish Time (LFT)

35 Forward Pass If only 1 immediate predecessor, then
Identifies earliest times (EST and EFT) EST Rule: All immediate predecessors must be done before an activity can begin If only 1 immediate predecessor, then EST = EFT of predecessor If >1 immediate predecessors, then EST = Max {all predecessor EFT’s}

36 EFT Rule: EFT = EST + activity time Node Notation:

37 Forward Pass: Earliest Start and Finish Times

38 Backward Pass Identifies latest times (LST and LFT) LFT Rule: If activity is the immediate predecessor to only 1 activity, then LFT = LST of immediate follower If activity is the immediate predeccor to multiple activities, then LFT = Min {LST of all imm. followers}

39 LST Rule: LST = LFT – activity time

40 Backward Pass: Latest Start and Finish Times

41 Slack Time and Critical Path(s)
Slack is the length of time an activity can be delayed without delaying the project Slack = LST – EST Activities with 0 slack are Critical Activities The Critical Path is a continuous path through the network from start to finish that include only critical activities

42 Project Schedule and Slack Times

43 Critical Path and Slack Times

44 Project Scheduling Questions?

45 Reference List 1. Project Management: Achieving competitive advantage, chapter 9 2. Project Management: A managerial Approach, chapter 13, Project Termination