Projects: Critical Paths

Similar presentations


Presentation on theme: "Projects: Critical Paths"— Presentation transcript:

1 Projects: Critical Paths
Dr. Ron Lembke Operations Management

2 PERT & CPM Network techniques Developed in 1950’s
CPM by DuPont for chemical plants PERT by U.S. Navy for Polaris missile Consider precedence relationships & interdependencies Each uses a different estimate of activity times

3 Questions Answered by PERT & CPM
Completion date? On schedule? Within budget? Probability of completing by ...? Critical activities? Enough resources available? How can the project be finished early at the least cost?

4 PERT & CPM Steps Identify activities Determine sequence Create network
Determine activity times Find critical path Earliest & latest start times Earliest & latest finish times Slack

5 3 1 2 Activity on Node (AoN) Project: Obtain a college degree (B.S.)
Attend class, study etc. Receive diploma Enroll 3 1 2 1 month 4? Years 1 day

6 1 2 3 4 Activity on Arc (AoA) Project: Obtain a college degree (B.S.)
Attend class, study, etc. Receive diploma Enroll 1 2 3 4 1 month 4,5 ? Years 1 day

7 1 2 3 4 AoA Nodes have meaning Project: Obtain a college degree (B.S.)
GraduatingSenior Applicant Student Alum

8 Liberal Arts Sidebar Alum = ? Alumnus Alumna Alumni Alumnae Alumni

9 Network Example You’re a project manager for Bechtel. Construct the network. Activity Predecessors A -- B A C A D B E B F C G D H E, F

10 Network Example - AON D G B A E Z C H F

11 Network Example - AON F H C A E Z B G D

12 Network Example - AON E H C G A Z F B D

13 Network Example - AOA D G 3 6 8 B E A 1 2 5 H 7 9 C F 4

14 AOA Diagrams A precedes B and C, B and C precede D B A 1 2 3 D 4 C 3 B A 1 2 C 4 D 5 Add a phantom arc for clarity.

15 Critical Path Analysis
Provides activity information Earliest (ES) & latest (LS) start Earliest (EF) & latest (LF) finish Slack (S): Allowable delay Identifies critical path Longest path in network Shortest time project can be completed Any delay on activities delays project Activities have 0 slack

16 Critical Path Analysis Example

17 Network Solution B D E A G 2 6 3 1 1 C F 3 4

18 Earliest Start & Finish Steps
Begin at starting event & work forward ES = 0 for starting activities ES is earliest start EF = ES + Activity time EF is earliest finish ES = Maximum EF of all predecessors for non-starting activities

19 Activity A Earliest Start Solution
D B C F G 1 6 2 3 4 For starting activities, ES = 0.

20 Earliest Start Solution
D B C F G 1 6 2 3 4

21 Latest Start & Finish Steps
Begin at ending event & work backward LF = Maximum EF for ending activities LF is latest finish; EF is earliest finish LS = LF - Activity time LS is latest start LF = Minimum LS of all successors for non-ending activities

22 Earliest Start Solution
D B C F G 1 6 2 3 4

23 Latest Finish Solution
D B C F G 1 6 2 3 4

24 Compute Slack

25 Critical Path A E D B C F G 1 6 2 3 4

26 New notation C 7 Compute ES, EF for each activity, Left to Right
LS LF Compute ES, EF for each activity, Left to Right Compute, LF, LS, Right to Left

27 Exhibit 6 C 7 F 8 A 21 G 2 B 5 D 2 E 5

28 Exhibit 6 21 28 28 36 C 7 F 8 0 21 36 38 A 21 G 2 28 33 21 26 26 28 B 5 D 2 E 5 F cannot start until C and D are done. G cannot start until both E and F are done.

29 Exhibit 6 21 28 28 36 C 7 F 8 21 28 28 36 0 21 36 38 A 21 G 2 0 21 36 38 28 33 21 26 26 28 B 5 D 2 E 5 21 26 26 28 31 36 E just has to be done in time for G to start at 36, so it has slack. D has to be done in time for F to go at 28, so it has no slack.

30 Gantt Chart - ES A C F B D E G

31 Solved Problem 2 B 4 E 6 G 7 A 1 C 3 I 4 F 2 D 7 H 9

32 Solved Problem 2 B 4 E 6 G 7 C 3 A 1 I 4 F 2 D 7 H 9 1 5 5 11 11 18
1 5 5 11 B 4 E 6 11 18 1 5 5 11 G 7 11 18 0 1 1 4 18 22 A 1 C 3 I 4 0 1 6 9 8 10 18 22 F 2 1 8 9 11 8 17 D 7 H 9 2 9 9 18

33 Summary Activity on Node representation Calculated
ES, EF for all activities LS, LF for all activities (working backwards) Slack for each activity Identified critical path(s)