Third LHC Splices Review SMACC Organisation Scope of work (What’s new since Nov 2011) Organization chart update Human resources Budget Unforeseen? Unexpected?

Slides:



Advertisements
Similar presentations
Alfa-Omega Team General information General information (Anna) W Bellows (Alain) DN200 (Andrea) A.A.A. - TE-MSC-CMI Section meeting Feb 19th, 2013.
Advertisements

O. Pirotte, A.Perin, TE/CRG, 4 th LHC Splice Review, Page 2 4 th LHC Splice Review, July 22-24, 2013 O. Pirotte (TE-CRG), A. Perin (TE-CRG)
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
Aw Team - summary of LS1 activities CMI Section Meeting, 16th September 2014 Anna Chrul (HNINP/CERN)
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
Overview of SMACC-QA 1.Recall of SMACC-QA organization 2.Tuning the procedures 3.Main results from the QC teams 4.Auditors findings Ranko Ostojic 23 July.
Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Alfa-Omega Team Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Long Shutdown 1 (LS 1) Plan Frédérick BORDRY. F. Bordry, 16 th August 2012 W HAT IS LS1? Not a project, but a time-frame (Nov-2012 to August-2014)
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Technology Department 1 Visit to Hall 180: Presentation of the consolidation process Third LHC Splice Review, November 12, 2012.
Fourth LHC Splices Review Quality Assurance Review Review of actions from 3 last reviews NB : 8 non-closed ones from 1 st review 5 non-closed ones from.
Third LHC Splices Review Review of actions from 2 last reviews Double shunt on quadrupole bus Insulation system Spiders and lyras electrical insulation.
K. Foraz, S. Prodon TS-IC TS workshop – May 2005 Underground logistics K. Foraz, S. Prodon TS-IC.
LS2 Safety Thomas Otto, LS2 Safety Coordinator.
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Fourth LHC Splices Review Quality Assurance Review Introduction Why this 4 th review ? Committee, mandate Questions to the reviewers Overall Quality Assurance.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project … Courtesy ….
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
Third LHC Splices Review Production Readiness Review Introduction Why this 3 rd review ? Planning, committee, mandate Evolutions since last review: SMACC.
The integration of 420 m detectors into the LHC
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
A. Perin, TE/CRG, DFBA LSC Page 2 LHC Long Shutdown 1 Committee June 14 th, 2013 A. Perin (TE-CRG) On behalf of the DFBA splices consolidation.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
MSC Technical Meeting 29 August 2013 Overheated QBBI.A21L6 F. Savary with contributions from N. Dalexandro, H. Prin, C. Scheuerlein, P. Voisin.
1 st of April st LS2C LS2 Committee Mandate and Organization 2 Chairman:Jose Miguel JIMENEZ Deputy:Jean-Philippe.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC Risk Review Installation Progress Francesco Bertinelli – TE/MSC 5 March, 2009 (20 minutes) On behalf of - and with several contributions from – the.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
Overall planning, consolidation, stops, time line K. Foraz MAC – April 27th 2010 April 27th 20101K. Foraz - Machine Advisory Committee.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
LHC experience with installation Katy Foraz March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop ***********************************
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
SMACC Eighteenth report [20 min] 07/02/2014
CERN Construction Planning and Scheduling (LHC installation)
SMACC Tenth report [15 min] 13/09/2013
ELQA Electrical Quality Assurance
Giorgio on behalf of ELQA team
Safety in Construction and Upgrade Phases
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
HSE rules & regulations
LS1 Committee January 24th, 2014
LHC Dipole Diode Insulation Consolidation Review (I) INTRODUCTION
Consequences of warming-up a sector above 80 K
Reinforcement of the LHC Dipole Diodes Insulation during LS2
MPE main activities planned for LS2
Overview & baseline of LS2 and roadmap for CRG
LS2 session J.M Jimenez, J.-P. Tock, K. Foraz 24/11/2017
K. Foraz on behalf of OSS members
Review of hardware commissioning
Shortening the long RQF/RQD busbar segments in points 1 and 5
Presentation transcript:

Third LHC Splices Review SMACC Organisation Scope of work (What’s new since Nov 2011) Organization chart update Human resources Budget Unforeseen? Unexpected?  Contingencies Worksite organisation concerns Conclusions 13th of November 2012 Third LHC Splice Review 1/25 J.Ph. Tock

SMACC Organisation: Scope of work  Consolidation of the 13 kA superconducting splices  In the continuous cryostat (From Q7 to Q7)  In the DFBAs  In the quadrupole diodes (one type) Including operations to give access and to reclose after  Consolidation of the superconducting circuits  Replacement of non-conform cryomagnets  Consolidation of the connection cryostats  Correction of the known and new NCs (best effort)  Consolidation of the cryomagnets & interconnections  Installation of the remaining pressure relief devices  Repair leaking Y-lines  Consolidate SAM Helium level gauges  Correct triplet cryogenics configuration  Consolidate PIM (Preventive and corrective)  Investigate and fix known and new leaks 13th of November 2012 Third LHC Splice Review NEW ? ? ? ? 2/25 J.Ph. Tock

SMACC Organisation: Scope of work 13th of November 2012 Third LHC Splice Review Working day starts at the top of the lift; Infrastruc ture will be provided High inner splice SSS Highest leak Electrical integrity issue Beam optics Spread all around : work on leaks, PIMs, SAM (He, DN160) Y-lines repair CC Consolidation / Inspection DN 200 installation Triplet braid (End of LS1 for rad prot) Cryo-dipole Circuit and splices issues Critical reversed beam screen Canteen, cloakroom, meeting rooms, toilets, showers,… 3/25 J.Ph. Tock

SMACC Organization Chart 13th of November 2012 Third LHC Splice Review SMACC J.Ph. Tock (# 255) Superconducting Magnets And Circuits Consolidation Open/Close IC [DN200] A Musso (A Chrul) #36 Main arc splices cons. F Savary (H Prin) #75 -Sleeves cutting -BB surfacing -Shunt installation -Insulation -Splice de- & resoldering [15%] -Quadrupole diodes connection -Experts Special interventions “SIT” N Bourcey (G Maury) #18 -Cryomagnets exchange -Connect. Cryostat cons. -PIMs -Specific issues -Heavy NCs -Opening/ Closure of IC Partial and complete W bellows & ther. shields -Installation of DN200 Quality Assurance R Ostojic #39 -Electrical QC: #16: C.Scheuerlein (P.Thonet) -Welding QC: # 6 : JM Dalin -Beam vacuum QC: #6 : C Garion -Open/close IC QC: #7 [Shared]: D Bodart -QA manager support: #2 -Audits: #3 ELQA [TE-MPE] K Dahlerup (G D’Angelo) #28 -Continuity -HV test Leak Test [TE-VSC] P Cruikshank (C Garion) #19 -Beam lines -Cryogenics lines -Insulation vacuum Project Office M Pojer (R Giachino) #11 -Radiation protection -Safety, Access -General logistics -Pressure test -Link to visits, media -Coordination with Survey, BLM, Instrumentation, Transport, planning, QPS, cryogenics, VSC, MPE, CRG, … Test teams on a chain of IC -Reporting tools -Administrative support (Budget, human resources, scientific secretary) DFBA [TE-CRG] A Perin (O Pirotte) [#10] -Splices and BB TIG welding [EN-MME] S Atieh (D Rey) #18 (+5) - Orbital & manual Long Shutdown 1 F. Bordry 4/25 J.Ph. Tock

SMACC: News in the Organization Chart Increase from 206 to 255 persons ! (+49 / 24 %)  Experience of test on mock-ups (SM18 and MT1) : + 16  Integration of DFBA consolidation including AK&P : + 10  Consolidation of the quadrupole diodes :+ 9  ELQA team :+ 5  Reinforcement of SIT : + 3  New IC thermal shields : + 3  Reinforcement of logistics : + 2  Spiders and lyras inspection : + 1 Alternates have been defined for all activities Interfaces are (being) defined within the SMACC meetings 13th of November 2012 Third LHC Splice Review 5/25 J.Ph. Tock

SMACC Human resources 13th of November 2012 Third LHC Splice Review Since Nov 2011:+ 31 FSU + 11 coll + 7 staff (TBC) [Some were not counted] Main increase amongst FSUs * The most flexible solution  Ratio of staff/collaborators decreased 6/25 J.Ph. Tock

SMACC Human resources availability Collaborations 13th of November 2012 Third LHC Splice Review  74 Collaborators  5 are at CERN presently and will stay up to the start  6 agreements out of 9 are signed and finalised  3 to be finalised accounting for 19 persons / Planned for end of November 2012  For tasks with long training period and wherever possible (ELQA, ICIT, DN200), revival of previous teams  2/3 are experienced  Arrival 4 to 8 weeks prior to intervention in the tunnel (depending on task and CERN rules)  Individual duration of stay : from 6 months to 2 years / Most frequent: 9 months  Overlap of 1 to 3 months depending on function  Training to be ensured in parallel with work in the tunnel 7/25 J.Ph. Tock

SMACC Human resources availability Collaborations 13th of November 2012 Third LHC Splice Review 1: NTUA 2: WUT 3: DUBNA 4a: PAEC 4b: PAEC 5a: HNINP 5b: HNINP(#3) 6: FNAL 8/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review  94 Persons  52 are at CERN  41 are trained and (very) experienced  9 are under training, 2 are at CERN but not available yet  42 have to be hired (on-going)  Arrival between 6 weeks (goal) and 4 months prior to start of intervention Budget is foreseen For training, integration, qualification  Normally for the entire duration of the project (Rotation exists)  Training to be ensured in parallel with the work in the tunnel  Is “local” recruitment being saturated ? [About 100 for the whole CERN]  69 Persons  45 are experienced (and are training newcomers)  6 are under training  18 are foreseen but are working on other activities (LHC operation for example)  Part time availability from January 2013 on For training, integration, qualification  FTE equivalent: in fact more persons available but partially  Part time availability (Typically 40-50%)  Training and know-how transfer have to be ensured in parallel with the work in the tunnel CERN staff SMACC Human resources availability FSU / Industrial Support + 18 persons as contractors (Leak test, weld inspection) 9/25 J.Ph. Tock

SMACC Human resources Training status 13th of November 2012 Third LHC Splice Review  Persons are not at CERN  69 Collaborators Amongst them, 26 are experienced  43 remains  42 FSUs  Persons are not available  2 FSUs  19 CERN staff (FTE eq)  Typically 35 persons Why not more training ?  “New” resources towards task with a short training period (Ex: Open/Close IC)  Error proof “automatic” procedures (Ex ELQC)  Tooling sent to collaborators (Ex cutting machine) so pre training  Revival of previous teams (ELQA, ICIT)  Low ratio for splices, due to new activities and recent resizing of the teams following mock-up tests (Insulation, shunt soldering, cu machining, QDiodes)  Detailed procedures  Good ratio easier to ensure for small teams 10/25 J.Ph. Tock

SMACC Human resources 13th of November 2012 Third LHC Splice Review Safety Motivation Coordination Team work Competent and equipped The only way to success 11/25 J.Ph. Tock

SMACC Budget 34.5 MCHF 13th of November 2012 Third LHC Splice Review Human resources oriented project (71%) (Almost) no contingency  45 % for splices consolidation proper From sleeve machining to rewelding (excl QA)  23 % for QA/QC outside production teams  Rest for:  Giving access and reclosure (11%)  Specific consolidation (13%)  Logistics, management, others  Budget structure put in place (12 budget codes) 12/25 J.Ph. Tock

SMACC Budget Time evolution 13th of November 2012 Third LHC Splice Review  Material budget spent before start of the work Remains maintenance, logistics, consumables  Means oriented expenditures  What matters:  Quality  Deviations  Progress rate 13/25 J.Ph. Tock

 Contingencies 13th of November 2012 Third LHC Splice Review How to cope with :  Unforeseen developments ?  > 15 % of splices to redo  New non-conformities  …  Unforeseen scenarios ?  Contingencies in available man power  Sizing the team for 60 IC/week eq and planning assumes 53 [13 %]  6 efficient working hours are assumed (2 hours for displacement) [Realistic – 0%]  No work planned on weekends : Limited impact because of legal limitations Limited experienced and trained staff available  Some experienced staffs are presently not in SMACC. In case of need and priority given by management, they could be redirected to SMACC. [5%]  Staff collaboration profile [A few %]  In manpower  In the SIT  In the schedule  In the budget (Almost none) Training Overlap and know-how transfer “Realistic”? workload profile Start-up issues Contingency ? (schedule delays ) 14/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review  Increase of Special Intervention Team capacity  Outsource standard interventions (Opening, closure, main BB soldering, ….) to the train team [Gain of expertise]  Increase its size : + 3 persons (20% increase)  This ensures a theoretical (optimistic) availability of minimum 30 % to handle NCs and full (theoretical) availability for the last 6 months Courtesy N Bourcey / M Bernardini  Contingencies  In manpower  In the SIT  In the schedule  In the budget (Almost none) 15/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review  Contingencies  In manpower  In the SIT  In the schedule  In the budget (Almost none)  Contingencies in the LS1 schedule ?  Sizing the team for 60 IC/week eq and planning assumes 53 [13 %]  SMACC is on the critical path (See K Foraz’s presentation)  Looking by sectors, there are some margins (Are they real ?) beware of coactivity, access constraints and limitations of other resources 16/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review  Contingencies after CD are not usable if < 3 months (Warm-up & Cool-down durations)  These periods are used by other teams so there will be access constraints (Powering test, pressure tests,….) and coactivity  Shifting some sectors would increase parallelism of subsequent activities with obviously also limited resources so would impact on the overall schedule  3 last sectors without usable time slot  If issue detected after CD, interventions can be envisaged in only 2 sectors (67/78) with a limited but non negligible impact  For 56 (the first one), there is a possibility to correct if the issue is/can be identified before cool-down  Using these contingencies would greatly impact the whole LS1 (ALMOST) NO CONTINGENCY IN THE LS1 SCHEDULE  Contingencies  In manpower  In the SIT  In the schedule  In the budget (Almost none) 17/25 J.Ph. Tock [months]

13th of November 2012 Third LHC Splice Review  Time windows are foreseen in the detailed schedule for unsoldering and resoldering all splices [Baseline is 15 %]  Corresponding teams are slightly oversized wrt 15%  Tooling is available  Contingencies  In manpower  In the SIT  In the schedule  In the budget (Almost none) 18/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review SMACC Organisation concerns:  Schedule  Manpower  Technical  Logistics First sector validated 15 months after start, Too late for feedback -Thorough beforehand testing and reviews -Training -Qualification -Intermediate QA/QC SMACC Train will extend on 3 sectors SMACC will extend on the 8 sectors  Supervision will be an issue -Reduces coactivity -Worksite coordinator -Logistics foreseen +Cars and equipped trucks, +Canteen, storage, meeting rooms on the points 19/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review SMACC Organisation concerns  Schedule  Manpower  Technical  Logistics  Availability  Collaboration agreements to finalise  Potential difficulty in FSU recruitments  Staff turnover  Planned for collaboration  Short notice with FSU  Ratio of experienced staff -Training is planned -But will have to be simultaneous to work in the tunnel -Detailed procedures -Overlaps ? Can we do more ? 20/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review SMACC Organisation concerns  Schedule  Manpower  Technical  Logistics  DFBA consolidation  Technical solutions still under development  Could impact the overall schedule and divert critical resources  Newly discovered NC Beam operation so far has only identified a few new issues  Experience shows that there will be many ? How Critical is it? ? Are available contingencies sufficient ? ? Can we do more ? 21/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review SMACC Organisation concerns  Schedule  Manpower  Technical  Logistics  Access modalities Relaxation of access constraints (No biometry)  What will be the next bottleneck ? Lifts ? Solution for bikes under study  General logistics  Efficient logistics for RP vacuum cleaners handling  Parking places shortage Shuttle services ? How Critical is it? ? Can we do more ? 22/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review SMACC Organisation concerns  Schedule  Manpower  Technical  Other From my “little” experience, most things happen... And many more… 23/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review SMACC Organisation Conclusions  Schedule  Optimised baseline is available for LS1 and SMACC in particular  No global contingency / Some little local ones included  Manpower  Ratio of experienced staff is about 50 % thanks to  Advanced hiring of FSU and training  Reintegration of experienced collaborators  Turnover to be minimised  To be finalised (FSU, collaboration agreements)  Technical  DFBA consolidation is late wrt other activities  Logistics  Actions are taken to avoid bottlenecks  We are not ready YET but we are confident that we will be ready for the start of the interventions in April 2013  Continuous efforts, commitments and works are required 24/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review Third LHC Splices Review Thanks to everybody 25/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review Third LHC Splices Review 26/25 J.Ph. Tock

13th of November 2012 Third LHC Splice Review 27/25 J.Ph. Tock