Presentation is loading. Please wait.

Presentation is loading. Please wait.

CERN Construction Planning and Scheduling (LHC installation)

Similar presentations


Presentation on theme: "CERN Construction Planning and Scheduling (LHC installation)"— Presentation transcript:

1 CERN Construction Planning and Scheduling (LHC installation)
K. Foraz

2 Content Introduction Multi-level planning Follow-up Conclusions
Deviation management Communication Conclusions ITER - K. Foraz EN-ACE

3 Challenge to carry out a Mega-Project
Time Horizon Multi-years Multi-phases Chain of Command Multi-layers organization Matrix Structure High‐degree of Specialization Subject Matter Expertise Cutting-Edge Technology Dispersed Teams Virtual teams in multiple locations Outsourcing to other countries Risks had to be properly analyzed Responsibilities had to be clear Coordination was crucial As well as clear and transparent communication Mega-Project factors Impact on the Project ITER - K. Foraz EN-ACE

4 Scheduling requirements
To coordinate a large project requires an overall view, which can only be achieved by collecting and summarizing detailed information Have a coherent information up-to-date Be able to identify the over/under-estimation from experience Multi level planning From planning to scheduling ITER - K. Foraz EN-ACE

5 The Master Schedule Review of the strategic goals and major milestones
ITER - K. Foraz EN-ACE

6 LHC construction and installation schedule
From strategy to tactic Aim: implement and control the flow of installation Respect the main milestones of the Master Schedule Based on the WBS Linear schedule ITER - K. Foraz EN-ACE

7 From tactic to operation
Detailed schedules From tactic to operation The LHC main ring: 8 sectors treated as 8 identical machines Arcs Long Straight Sections Services areas 3 main MSProject files Weekly review of the 3 schedules, and their dependences ITER - K. Foraz EN-ACE

8 Tools used MSProject Excel Gant chart Level resources Progress curves
Automated excel -> Linear schedule Time sheets Main options for general schedule ITER - K. Foraz EN-ACE

9 Baseline schedule The delay of the QRL imposed the reshuffling of some activities. Additional resources were added for the following phases +3 months Major non-conformities during installation: +2 months because of the QRL, +4 months because of the interconnections Interconnection non conformities + Inner Triplet Crisis +7 months Hardware commissioning was included ITER - K. Foraz EN-ACE

10 Baseline evolution 2002 2003 2004 2005 2006 2007 Civil engineering
LHC civil engineering work Water cooled cables Cryogenic line 1st LHC cryo-magnets lowering LHC Interconnection work 2002 2003 2004 2005 2006 2007 Civil engineering General Services Cryogenic line installation Machine installation 2002 2003 2004 2005 2006 2007 2002 2003 2004 2005 2006 2007 ITER - K. Foraz EN-ACE

11 Follow-up Aim: to depict actual status and compare it to baseline
Adaptation through continuous feedback Minor changes Major changes Schedule Change Requests circulated through the groups and approved by the project leader – Schedule Change Order ITER - K. Foraz EN-ACE

12 Follow-up Information sources ITER - K. Foraz EN-ACE

13 Follow-up Bi-monthly short term planning review
Who: Schedule officers, Project engineers or representatives, Work coordinators, Safety coordinators What: Work within the next 3 months, logistic issues ITER - K. Foraz EN-ACE

14 Follow-up Worksite meetings
Who: Work coordinators, Safety coordinators, worksite supervisors, contractors, (schedule officers) What: Work within the week, worksite issues, daily logistics… ITER - K. Foraz EN-ACE

15 Follow-up Other meetings: MARIC, ICC… 2017.01.16
ITER - K. Foraz EN-ACE

16 Schedule deviation management
Purpose Determine whether the schedule has changed Determine which factors create schedule changes Manage actual changes as and when they occur Minimize overall impact of delays to the main milestones Sources of deviation 1st worksite Material readiness Lack of resources «Force majeure», Accident/Incident Unexpected technical difficulties ITER - K. Foraz EN-ACE

17 Schedule deviation management
Understanding the cause – to prevent gap widening the consequence – to find the best answer Solutions Additional resources ($$) Shift works Schedule reshuffling Accepted delay ! “We will either find a way, or make one.” – Hannibal ITER - K. Foraz EN-ACE

18 Getting your message across to your audience
Communication «Government» Getting your message across to your audience Shared Vision Project community The world Contractors & collaborations Regular reports ITER - K. Foraz EN-ACE

19 Highlight issues & risks (solutions & alternative plans)
Communication «Government» Synthetic Highlight issues & risks (solutions & alternative plans) ITER - K. Foraz EN-ACE

20 Communication Project community & Contractors & collaborations
General Project status & Details on deadlines, co-activites and constraints (the closest you get to the worksite, the more you simplify the information) ITER - K. Foraz EN-ACE

21 it's kind of fun to do the impossible !
Conclusions it's kind of fun to do the impossible ! Walt Disney Planning & scheduling a Mega-Project requires Clear structure and clear responsibilities Flexibility (schedule pressures are coming from all avenues) Close contact with the top & the bottom Transparency ITER - K. Foraz EN-ACE

22 Thank you for your attention
ITER - K. Foraz EN-ACE

23 ITER - K. Foraz EN-ACE


Download ppt "CERN Construction Planning and Scheduling (LHC installation)"

Similar presentations


Ads by Google