Northern Tier Transmission Group Report to Columbia Grid Planning Committee February 9, 2012 “To ensure efficient, effective, coordinated use & expansion.

Slides:



Advertisements
Similar presentations
1 Report of the Planning Coordination Committee Report to the WECC Annual Meeting April 20, 2006 Robert Jenkins, PCC Chair.
Advertisements

NTTG Report to TEPPC BiennialTransmission Plan.
Order 2004 Sensitive 1 WECC Phase 1 Rating Process Coordinated Planning and Technical Studies: PCC Presentation on the Avista Interconnection to the PG&E.
Northern Tier Transmission Group SPG Report to TEPPC June 17, 2010 Denver To ensure efficient, effective, coordinated use & expansion of the members transmission.
Study Results PC8-PC16 System Stress Tests This slide deck contains results from the 2012 TEPPC Study Program related to the various stress tests performed.
Transmission Planning in the West pocket guide This reference guide is intended to assist individuals new to transmission planning in the Western Interconnection.
TransWest Express and Gateway South WECC Planning Coordination Committee David Smith, National Grid October 25-26, 2007 Vancouver, B.C.
Rocky Mountain Area Transmission Study RMATS Economics Economic Comparisons Preliminary: Distribution of Gains and Losses RMATS Steering Committee July.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
Public Service Company of New Mexico
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
Montana Energy Summit Transmission Planning Process April 22, 2008.
SPP’s 2013 Energy Consumption and Capacity 2 12% annual capacity margin requirement CapacityConsumption Total Capacity 66 GW Total Peak Demand 49 GW.
WECC PCC Meeting Salt Lake City, UT March 26, 2014.
1 Dale Osborn Midwest ISO February 27, Wisconsin Renewable Energy Summit Transmission Expansion Opportunities with Wind Energy.
WECC PCC Meeting Salt Lake City, UT July 16, 2014.
North American Strategic Infrastructure Leadership Forum October 12, 2011.
Montana Ambassadors Helena, Montana February 25, 2011.
ISO Grid Planning Presentation to CREPC October 1, 2002
Past Studies and Resource Diversity Western Renewable Energy Zones, a joint initiative of the Western Governor’s Association and the U.S. Department.
Successful Transmission Planning & Development in the West Kelly Barr Manager, Regulatory Affairs & Contracts Salt River Project Phoenix, Arizona June.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
WestConnect Activities Charles Reinhold WestConnect Project Manager 2008 ACC BTA Workshop Phoenix, AZ May 22, 2008.
Energy Gateway Update for Wyoming Infrastructure Authority January 27, 2009 Darrell Gerrard Vice President Transmission System Planning.
OSC Meeting April 27, Transmission Cost Allocation Overview.
COMMON USE SYSTEM March 5, 2008 Black Hills Power Service Center Rapid City, SD TRANSMISSION COORDINATION AND PLANNING COMMITTEE.
Transmission Planning at the California ISO September 10, 2015.
CWAG ENERGY CONFERENCE BIG SKY, MT Collaborative Efforts to Find Solutions: A Case Study – The Mountain States Transmission Intertie (MSTI) Presented by.
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
Study Results High EE/DG/DR Study This slide deck contains results from the 2011 TEPPC Study Program. This study shows the results of an increase of EE/DG/DR.
“DRAFT” RMATS 2008 Base Case (To be presented at the RMATS Stakeholders Meeting) March 17, 2004.
Rocky Mountain Area Transmission Study Steering Committee Meeting 2013 Case Alt 1 & 2 - Iteration 2 – Test Transmission Solutions Alt 3 & 4 – Iteration.
© 2000 PACIFICORP kV LINE WALLA WALLA – WALLULA – Mc NARY 500 kV LINE HEMINGWAY – CAPTAIN JACK – REGIONAL PLANNING MEETING REGIONAL PLANNING PROJECT.
Jan Strack San Diego Gas and Electric TEPPC Overview TEPPC Review Task Force January 11, 2016 Salt Lake City, UT.
TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects — The Center for the New West “ The Sun Valley Energy Roundtables 2006” November 30 – December.
FERC Order 1000 Drafting team activated April Filing Interregional Coordination Transmission Planning Regions CAISO, Columbia Grid, NTTG, WestConnect Interregional.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
WECC Reliability Study Requests Byron Woertz, Manager—System Adequacy Planning W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Chelsea Loomis, Regional Electric Transmission Planning.
Long Term Transmission Integration Planning at the California ISO Intermittency Analysis Project (IAP) Energy Commission Staff Workshop February 13, 2007.
Renewable Energy Transmission Initiative 2.0 Plenary Group Meeting April 18, 2016 Sacramento, CA Thomas Carr Western Interstate Energy Board TEPPC’s Resource.
LS Power LS Power is a power generation and transmission group
CREPC/WIRAB Meeting April 27, 2016 Salt Lake City, UT Thomas Carr Western Interstate Energy Board Evolution of Grid Planning in the West.
Biennial Transmission Plan Studies Update - DRAFT April 6, 2011.
Slide 1 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N BPA Network Open Season 2013 Cluster Study ColumbiaGrid Planning Meeting May 2, 2013.
Study Plan Development & Approach May 5, 2010 Conference Call & Webinar “To ensure efficient, effective, coordinated use & expansion of the members’
PC05 Low Hydro Study Results
PC04 High Hydro Study Results
1 NTTG Transmission Planning Process Columbia Grid Open Season Meeting August
Topics Corporate Overview – Transmission Expansion Planning - Members
4/23/2018 Steering Committee Meeting 2013 Case Alt 1 & 2 - Iteration 2 – Test Transmission Solutions Alt 3 & 4 – Iteration 1 - Define Congestion.
Barrilla Junction Area Transmission Improvements Project
TAS Quarterly Meeting November 2-3, 2016 Michael Bailey, P.E. WECC
Transmission Planning Update October 20, 2010
Study Results Common Case Study
Keegan Moyer Interim Manager, Transmission Expansion Planning
SunZia Project Description
ColumbiaGrid Planning Meeting FERC Order 1000 Activities June 7, 2018
TAS Quarterly Meeting November 2-3, 2016 Michael Bailey, P.E. WECC
Western Electricity Coordinating Council
Planning Committee- Map
Study Results Common Case Study
Study Results PC8-PC16 System Stress Tests
Study Results California In-State Net-Short California Out-State Net-Short California Out-State Net-Short w SWIP N This slide deck contains results from.
TONBRIDGE POWER GREEN LINE
Palo Verde-COI RAS Retirement
Study Results Drought Scenario Study
Palo Verde-COI RAS Retirement
Common Case Transmission Assumptions
Presentation transcript:

Northern Tier Transmission Group Report to Columbia Grid Planning Committee February 9, 2012 “To ensure efficient, effective, coordinated use & expansion of the members’ transmission systems in the Western Interconnection to best meet the needs of customers & stakeholders.”

NTTG Biennial Planning Cycle We are here Q1 Q2 Q3 Q4 Q5 Q1 Q6 Q2 Q7 Q3 Q8 Q4 Gather Information Develop Study Plan, Assumptions Perform Draft Plan Analysis Prepare & Review Draft Report Process Econ. Studies, CostAlloc. Prepare & Review Final Report Obtain Final Plan Approval Economic Study Requests Perform Economic Studies Report and Review Economic Study Requests Perform Economic Studies Report and Review NTTG Economic Study Cycle NTTG Biennial Planning Cycle

NTTG Biennial Planning Report & Summary

Just finished Quarter 8 of Cycle –Finalized and Approved Report and Exec Summary –Available at Quarter 1 of Biennial Planning Process –Stakeholder Requests: Planning needs and data –Request window open for Economic Study Requests No WECC Wide requests received this year Expecting several “Regional” ESRs before NTTG window closes March 31, 2012 –Data and Modeling Improving Round Trip base case process Working on TEPPC 2010 and 2022 Cases Other Activities –FERC Order 1000 Regional compliance NTTG Planning Committee

Final Planning Report for Cycle Core Case Reliability Study: –Five hours of stress test cases for NTTG’s footprint were exported from production cost studies for power flow reliability analysis –Cases were solved and passed high level N-1 contingency analysis within study criteria Existing System will not be able to reliably serve network load growth requirements in 2020 and transmission additions are required The NTTG projects on the Foundation list (either under construction and/or meeting other SCG Criteria) are sufficient to meet reliability requirements for 2020 network loads

System Scenarios Additional renewable generation scenario cases were performed in response to stakeholder requests - generation but no specific receiving customers. Delivery points calculated from Production Cost Model –Since no agreements in receiving area –Scenario resource additions were offset by generation reductions in California & Arizona Reliability studies for the same five hours as for Core Case (so 20 cases performed) –All required additional transmission above the Foundation List Looked for limited transmission additions that would allow all five stress test hours to pass an N-1 contingency study –HVAC and HVDC additions considered –Generic additions so as not to pick specific sponsor 6

Scenario 1 Results Scenario 1 – 6,000 Megawatts in Wyoming –Adding 3,000 MW transfer capability Clover-Crystal line was inadequate 2,100 MW over limit on COI, 433 criteria violations –Also adding 3,000 MW transfer capability Aeolus-Crystal still left problems COI was 760 MW over its limit 147 criteria violations –Further addition of 1,500 MW transfer capability Midpoint-Robinson left fewer problems COI still 200 MW over limit 119 remaining criteria violations –Addition of phase shifting transformers or substituting two kV DC lines would likely further reduce problems 7 Midpoint Aeolus Clover Crystal Robinson

Scenario 2 Results Scenario 2 – 3,000 MW in Montana, 3,000 in Wyoming –Adding Townsend-Midpoint and Clover-Crystal was inadequate 1,700 MW over limit on COI, 1,600 MW over Montana-Northwest limit –Tested combined Scenario 3 and Scenario 4 transmission additions 3,000 MW capability from Townsend via Midpoint and Robinson to Harry Allen plus 1,500 MW from Aeolus to Crystal plus 1,500 MW from Clover to Crystal 29% over limit on Victorville-Lugo 350 MW over COI limit of 4,800 MW 98 criteria violations –Appears adequate, violations can be resolved with local controls –Other hours have not been tested, given previous dominance of March hour 8 Townsend Midpoint Aeolus Clover Crystal Robinson

Results of Scenario 3 Analysis Scenario 3 – 3,000 MW in Montana –Significant problems again occurred on the high export hours –Problems with Montana to Northwest, COI paths Generic Solution: Add Transfer Capability 1)Added 1,500 MW from Townsend (Central MT) to Midpoint (Central ID) Montana-Northwest over by 400 MW Still 1,700 MW over on COI 2)Tested 3,000 MW transfer capability from Townsend via Midpoint and Robinson to Harry Allen Fixed problems on Montana-Northwest COI just 325 MW over limit 77 violations 2) appears adequate, violations can be resolved with local controls –Other hours studied again have fewer issues 9 Townsend Midpoint Harry Allen Robinson

Midpoint Aeolus Clover Crystal Robinson Results of Scenario 4 Analysis 10 Scenario 4 – 3,000 MW in Wyoming –Significant problems occurred on the high export hours (March noted here) –Problems with paths TOT2A, COI Generic Solution: Add Transfer Capability 1)1,500 MW capacity from Clover (Central UT) to Crystal (Southern NV) Still 900 MW over COI limit 2)1) + 1,500 MW capacity Midpoint-Robinson COI less than 100 MW over, 200 violations 3)1) + 1,500 MW capacity Aeolus-Crystal COI 104 MW over limit, 132 violations 3) appears adequate, violations can can be resolved by local controls Other hours studied have fewer issues

Scenario Conclusions  Adding 3,000 MW of generation in either Montana or Wyoming appears to require 3,000 MW of additional transfer capability through a partial double-circuit 500 kV AC or DC circuit to deliver via Southern Nevada to Arizona and California  Delivery via Northwest would require upgrades MT-NW and to COI  Adding 3,000 MW in both Montana and Wyoming works relatively well with double-circuit 500 from Townsend to Harry Allen via Midpoint and Robinson, a 500 kV line from Aeolus to Crystal and another from Clover to Crystal or DC tie lines  With 6,000 MW in Wyoming, double-circuit from Aeolus to Crystal plus double-circuit from Clover to Crystal still needs Midpoint- Robinson to get reasonable results or DC tie lines 11

Annual Economic Studies 2010 Economic Study Requests – 25 Received –21 Interregional sent up to TEPPC –3 NTTG Sub-Regional Amps 230 kV upgrade to 401 MW MSTI Colstrip 500 kV system upgrade –1 NWE Local 1500 MW 230 kV radial collector lines into Townsend 500 kV & MSTI 2011 Economic Study Requests – 24 Received –None Sub-Regional –All Interregional and directed up to TEPPC 2012 NTTG ESR Window will Open Jan 1 – Mar 31 –Note WECC window closes Jan 20 next year (instead of 1-31)

Economic Studies NTTG Cluster Study - Added 1500 MW wind at Townsend. Performed economic studies with expansion : 1. Increase capacity of the AMPS line (Path 18) from 337 to 401 MW 2. Increase rating of Montana-Northwest path (Path 8) by 600 MW 3. Add Mountain States Transmission Intertie (MSTI) project Results –Large congestion and coal cycling without additions Some wind spill –Moderate congestions and cycling with Path 8 and 18 –Acceptable performance with all 3 upgrades