Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #32 PLENARY DCL Trials Update 4/16/2014 Matt Maki DCL Trials Lead
Federal Aviation Administration DTAP Build 7.1 Schedule Update Build 7.1 Limited Climb Via SID Compliance: -Interim Build with KEWR focus -UM169 CVS UL when MAINT ALT Set to NONE -AJV-8 ATP issued KMEM/KEWR CVS DTAP Trials waivers (April 2, 2014) -Fixes PTR 179 (Revised Dispatch Message EXPALT Header/Data) and PTR 180 (Dual Index Rollover Crash/DTAP Restarts) Build 7.1 Estimated Schedule: April 14-15:FAT at Thales April 16:Install/SAT at FAATC -April 16-25:Testing at FAATC -April 28 - May1:Install and SAT at MEM and EWR (Parallel installs)
Federal Aviation Administration B7.1 Climb Via Sid – CAF, Dispatch Message
Federal Aviation Administration B7.1 Climb Via Sid – Revised ALT (NONE), Dispatch Message Note: Revised DP listed in DM header due to B7.1 configuration to utilize CLIMBOUT field. B7.2 corrects this and just Revised ALT will be listed in the header
Federal Aviation Administration DTAP Build 7.2 Schedule Update Build 7.2 Full Climb Via SID Compliance: -Compliance with full CVS Changes -CVS, CVS Except Maintain, Maintain ALT Selections -Arrival/Departure Loadability, FD DL Response to AOC -Longer WJHTC lab testing period granted Build 7.2 Estimated Schedule: -June 11-12:B7.2 FAT at Thales -June 13:Install/SAT at FAATC -June 16 - July 3:Testing at FAATC -July 7-10:Install and SAT at MEM and EWR (Parallel installs)
Federal Aviation Administration KEWR DCL Trials Status Update UAL, FDX, UPS Daily Ops Ongoing: -UPS MD11/B767 daily operations commenced March 15 -Open OPR reports continue to be stable/diminish -Working with UAL to schedule remaining 9 B767 Fleet qualifying operations (May dates under consideration) -Legacy COA B757/B767 fleet Sabre/FANS upgrades start this summer – expanded KEWR participation expected International Participation Update: -BAW UK CAA approval letter received by FAA -DLH, SAS CAA approval letters pending -AFS-50 scheduling final approval briefing meeting with NY International POI reps to cover BAW, SAS, DLH ops -Airline AOCs standing by to resume DCL ops
Federal Aviation Administration KEWR DCL Trials Status Update March 26 EJA Global 5000 CPDCL Testing Complete: -Rockwell Collins Pro Line Integrated Avionics -CAF, Initial/Revised UM80 successful UL/loads -Initial/Revised UM79 not loadable – Rockwell reseaching KEWR HADDS, FDIO Test NCP Extensions Approved: -Via the 4/16 NAS CCB -Space NCP Extension not required until equipment removal April 7 Briefing with ZNY Automation, TMU: -Seeking ATOP DB ingest into DTAP for expanded SWAP Route processing -TMU briefed on Field 6A ‘EWR’ vs ‘KEWR’ DTAP processing effects
Federal Aviation Administration KMEM DCL Trials Update DCL Operations Running Well -DTAP Processing FDX DCL ops per push -Route Revisions remain minimal/none in #s -Server 1, 2 Re-starts On-going (Tues/Fri) until B7.1 installed on April 28 Boeing DCL KMEM/KEWR Stats Reporting