MUSE NSF Review March 24, 2014 1 MUSE Project Management Ronald Ransome Rutgers The State University of New Jersey For the MUSE Collaboration.

Slides:



Advertisements
Similar presentations
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Advertisements

TIME AND COST These slides have been added to the standard MRU PM Cert materials and are made available to students who have attended my class. Robin Hornby.
Fermilab E906 Schedule Paul E. Reimer 20 June 2008.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MINER A NuMI MINER A DAQ Review 12 September 2005 D. Casper UC Irvine WBS 7.2 & 7.3: Data Acquisition D. Casper (UC Irvine)
NuMI Offaxis Costs and Whither Next Stanley Wojcicki Stanford University Cambridge Offaxis workshop January 12, 2004.
Part II Project Planning © 2012 John Wiley & Sons Inc.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
HPS Budget and Schedule Marco Oriunno, June 4-6, 2013 HPS Collaboration Meeting, JLAB.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
HFT project Overview and Status October 14, 2010 F.Videbaek BNL.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 10 Project Cost Management.
Project UF Practical management of projects Randy Graff, PhD.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
John LeRose March 12, A Program of three “projects” to assemble the Super BigBite Spectrometer for a series of experiments in Hall A There is a.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Alexei Fedotov Project Management.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
LIGO-G M Planning and Implementation Strategy for Advanced LIGO Gary Sanders LSC Meeting Hanford, August 14, 2001.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
M. Bonesini - MICE Inst Meeting M. Bonesini INFN Milano TOF installation plans.
Conventional Construction Working Group Meeting Tom Lackowski L2 Conventional Facilities Mu2e Working Group.
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
P. Shanahan Nov 15, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since May review Near Detector Electronics production.
XLIX Engineering Design Firm © 2010 ENGR/ETGR Definition of Project 1 A project is “…a combination of human and non-human resources pulled together.
MINERvA Status Report Deborah Harris, Gabe Perdue, Kevin McFarland, Jorge Morfin October 15, 2009.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
1 Installation Logistics Itzhak Tserruya HBD meeting BNL, July 6, 2006.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 16-Nov-2009.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
ATLAS Pixel Detector July 2003 SC Pixel Meeting N. Hartman LBNL 1 Pixel Support Tube WBS Santa Cruz Cost Workshop July 9, 2003.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
LHCf Detectors Sampling Calorimeter W 44 r.l, 1.6λ I Scintilator x 16 Layers Position Detector Scifi x 4 (Arm#1) Scilicon Tracker x 4(Arm#2) Detector size.
26-Feb-16S.Movchan Straw manufacturing and QC1 Dubna NA62 straw tracker assembly area (milestone) halls plans conclusion Presented by S.Movchan.
EDM Fast Start Presentation WBS 11 – Assembly and Commissioning Vince Cianciolo, Paul Huffman May 23, 2006.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
Gas system for NA62 Straw detector Roberto Guida On behalf of Gas Service Team NA62 Straw working meeting, March 26, 2012 Outline: P&I Drawing Schedule.
1 HBD: Responsibilities, Cost and Schedule Itzhak Tserruya EC/DC Meeting, BNL, March 9, 2005.
NUMI MINOS MINOS Far Detector Installation & Commissioning Jeff Nelson MNHEP DoE Visit September, 2002.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Jim Fast Pacific Northwest National Laboratory
Executive Steering Committee Meeting September 23, 2009
The SABRE Crystals Frank Calaprice.
10/month is the present production rate 2 FTE + sporadic contributions
Overall Project RAG Status:
East Hall under construction
Presentation transcript:

MUSE NSF Review March 24, MUSE Project Management Ronald Ransome Rutgers The State University of New Jersey For the MUSE Collaboration

Outline  Project WBS Organization  Overall Schedule  Assessment of each WBS  Contingency management MUSE NSF Review March 24,

WBS  There are 8 construction elements  We’ve included a catch-all “Installation” element tThis will contain miscellaneous work to be done before and after installation, as well as installation milestones  The Gantt chart also has a WBS 10 (Funding) which is simply for convenience of linking tasks to the funding schedule MUSE NSF Review March 24,

4

WBS Dictionary MUSE NSF Review March 24, WBSInstitutionScope 1RutgersBuild support table and frames for detectors 2Tel AvivScintillating Fiber Detector 3RutgersCerenkov Detector 4HebrewStraw Chambers 5GWULH2 Target 6GWUElectronics and DAQ 7S.CarolinaScintillators 8HamptonGEM detectors Each WBS is independent of the others until final assembly, except some electronics needed for testing

Schedule  Two major milestones: tTest run in fall 2015 tFull run in fall 2016  Items needed for 2015 Run tSupport Table (WBS1) – by June (anticipated by March 2015) tGEMs (already there) tHalf of Cerenkov (WBS3) – by July (by January 2015) tHalf of Scintillator (WBS7), Veto – by August (by August 2015) tSci-Fi detector (WBS2) – by September (by August 2015) tStraw tube – 1 chamber (WBS4) – by October (by June 2015) tHalf of electronics (WBS6) – with associated detector (by July 2015) tDoes not need LH2 MUSE NSF Review March 24,

Budget & Contingency  Each WBS has a combination of labor and equipment.  Equipment is mainly standard, from well known designs, or off-the-shelf. tLargest uncertainties come from currency exchange risks  Labor is mainly in salaried employees (i.e. grad students, post-docs, full time tech), not hourly. This gives some less uncertainty in costs. MUSE NSF Review March 24,

8

Travel  Travel is a major expense tMeetings (~$40K/year) tInstallation/testing 2015 (~$250K) tRunning 2016 onward (~$350K/year) MUSE NSF Review March 24,

WBS  I will discuss major cost components, schedule, and risks for the WBS 2,3,4,7.  WBS 1 consists of low cost construction with very low construction, technical, or schedule risk  WBS 8 consists of minor backup to working system  WBS 5,6 discussed earlier today  WBS 9 currently has a primary cost of an on-site post-doc MUSE NSF Review March 24,

WBS 4 – Straw Tubes  Major Cost Items tStraws  Straws & wire BOE – quote $24K  Hardware (pins, caps) BOE – PANDA experience - $327K  Contingency $146K tLabor  Salaried – 2 GS (one from HU, one from Temple)  $175K (includes travel for Temple student)  Contingency $35K tTotal Cost $637K +$202K contingency MUSE NSF Review March 24,

WBS 4 - Schedule  Set up tRequires mounting table, clean room tEstimated Completion date – August 2014  Straw Construction tEstimated at least 25/week tFirst chamber completed – May, 2015 tChamber 2-4 completed – January 2016 MUSE NSF Review March 24,

WBS4 MUSE NSF Review March 24,

WBS 4 – QA and Risk  QA tStraws will be tested with source, planes with cosmics tPressure testing as straws are built  Major Risks tHigher than anticipated failure rate  Close consultation with PANDA to conform to proven procedures  Buy enough extra parts to mitigate small batch costs/time delay  We will buy 4000 straws at outset, and parts for 3500, with contingency for 500 more sets of parts MUSE NSF Review March 24,

WBS 7 - Scintillator  Major Costs tPMTs – BOE quote - $187K tScintillator – BOE quote - $78K tBacking structure – BOE quote $44K tLabor – BOE past experience - $110K  Total Cost $442K + $72K contingency MUSE NSF Review March 24,

WBS 7 - Schedule  Pre-construction – order PMT’s and scintillator (2-3 months)  Scintillators are made in batches of 6, with one set completed before moving on.  Need to place orders by July 2014 to be ready for fall 2015 run.  Full set completed by early 2016, no risk on full run MUSE NSF Review March 24,

WBS7 MUSE NSF Review March 24,

WBS 7 – QA & Risk  QA – scintillators checked with source and cosmics before shipping  Risks t low technical risk, this is a proven technology tSome schedule risk for 2015 test run if material is delayed in arriving. Would require using smaller number for test, additional shipping costs. tSome design risk, may increase size slightly if decision is made to move farther back (<10% cost) MUSE NSF Review March 24,

WBS 2 SciFi  Major costs tFiber – BOE quotes - $12K tPMT – BOE quotes - $23 K tPMT bases, supplies – BOE past experience - $32K tLabor – GS $70 K tTotal - $152K plus $29K contingency MUSE NSF Review March 24,

WBS2 MUSE NSF Review March 24,

WBS 2 Schedule, QA, Risk  Easily completed in 6 months after materials arrive  Will be tested with source and cosmics  No schedule risk  Low technical risk, proven technology MUSE NSF Review March 24,

WBS 3 - Cerenkov  Major Cost tPMTs – BOE quote - $195K tTotal cost $212 K plus $27 contingency  Schedule – easily assembled in 2 months after materials arrive  QA – cosmic and beam tests  No schedule risk  Low technical risk, proven technology MUSE NSF Review March 24,

WBS3 MUSE NSF Review March 24,

Handling Contingency  Plans for handling contingency tM&S/Labor Contingency  <$5K up to WBS manager  $5-25 K up to Project Manager  >$25 K must be reviewed by managers for impact on scope and schedule, approval by Project Manager tTravel Contingency  Any anticipated change over $2 K must be approved by Project Manager  Must take into account importance to set-up, construction, maintaining experiment (e.g. move to set-up travel out of collaboration meeting travel) MUSE NSF Review March 24,

Schedule & Reporting  Schedule will be reviewed once date is know for funding tSet milestones  Determine funding distribution based needs to prioritize test run 2015  Each WBS manager will report project progress to Project Manager on a bi-monthly basis. MUSE NSF Review March 24,

WBS 1 MUSE NSF Review March 24,

WBS5 MUSE NSF Review March 24,

WBS6 MUSE NSF Review March 24,