21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.

Slides:



Advertisements
Similar presentations
VELO Module PRR preparation meeting28-feb-2006 LiverpoolMassimiliano Ferro-Luzzi 1 Introduction VELO overview Overall planning A bit of (recent) history.
Advertisements

US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Line Efficiency     Percentage Month Today’s Date
LHCC referee meeting – 03/07/2007 LHCC referee meeting – 03/07/2007 Status of the TRD at CERN as of July 2007 TRD Group Physikalisches Institut Universität.
HLT Collaboration (23-Jun-15) 1 High Level Trigger HLT PRR Planning Volker Lindenstruth Kirchhoff Institute for Physics Chair of Computer Science University.
1 Timescales Construction LCR MICE Beam Monitoring counters + DAQ My understanding Jan 07 Feb 07 Mar 07 Apr 07 May 07 Jun 07 Jul 07 Aug 07 Sep 07 ISIS.
Hans-Åke GustafssonLHCC review January 31, ALICE meets LHCC referees 31/01/ :00  Milestones report H-A Gustafsson  FMD questions H. Boggild.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
TGC Big wheel Sector assembly plan Tatsuo Kawamoto ATLAS workshop 2005.
WP1.2 – Photon Detectors Stephan Eisenhardt University of Edinburgh  Budget  Milestones  Progress Report  Partners: International Collaborating Groups.
MICE Collaboration Meeting Frascati 26 – 29 June 2005 Work Group report On Design & Safety Review.
Gek 16/6/041 ITRP Comments on Question 19 GEK 9/06/04 19) For the X-band (warm) technology, detail the status of the tests of the full rf delivery system.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
DT1 Gas Section Debrief of 2005 activities.. The Purpose of the Debrief  Compare plan and achievements.  Analyze how the work is done ? Do we meet the.
23 Apr 2008Paul Dauncey1 Future proposal possibilities Paul Dauncey.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
STATUS OF HO Sudhakar Katta TIFR, Mumbai India-CMS meeting, Delhi 27 th Sept 2007.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
Introducing Project Management Update December 2011.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
On behalf of joint ITEP / IHEP team: A. Arefiev, N. Filimonov, T. Kvaratskheliya, I. Machikhiliyan, P. Shatalov, T. Zakoryuchkina, A. Zhokhov, S. Zvyagintsev.
ALICE Pixel Operational Experience R. Santoro On behalf of the ITS collaboration in the ALICE experiment at LHC.
1 October 2003Paul Dauncey1 Mechanics components will be complete by end of year To assemble ECAL, they need the VFE boards VFE boards require VFE chips.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
25 January 2007VELO sub-projectsEddy Jans 0 VELO-meeting January 25, 2007 Sub-projects: SX & SX connectorize cooling cables alignment procedure.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
OLAV3 Engineering Integration and installation of experimental beam pipes: the case of LHC 7/8/20111P.Lepeule for VSC group.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
Detector Summary Tracker. Well, as far as the tracker hardware is concerned, we are done. – Need to do the system test to make sure nothing has degraded.
DCal Insertion Tooling 24/02/ DCal Insertion Tooling DCal Insertion System feature following main components 1. One rotator : cylindric welded structure.
Summary of User Requirements for Calibration and Alignment Database Magali Gruwé CERN PH/AIP ALICE Offline Week Alignment and Calibration Workshop February.
10 May 2006Paul Dauncey1 ALICE EMCAL Technical Proposal: First Discussion Paul Dauncey, Michel Gonin, Junji Haba.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
AEM, Sept Frank Chlebana (Fermilab) Status of the LHC and CMS Frank Chlebana (Fermilab) All Experimenter’s Meeting Sept
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
1 Update on Power Supplies TB L.Jirden u LV u Concerns u Orders & deliveries u Maintenance u HV u Overview u purchasing.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
Detector Gas Systems Status Update Ferdi Hahn PH-DT1-GS 3 rd Detector Steering Meeting on Gas Systems June 2005.
(Alice COsmic Ray Detector) Status Report
Calibration: preparation for pa
Jan 2016 Solar Lunar Data.
HFT Overview Flemming Videbæk BNL 3/14/12 F2F LBNL.
Technical Coordination Parallel Session November 2011, FNAL
Update on the SVD construction
Project Major Activities Over Next Days (as of xx/xx/xx)
LHC Experimental Vacuum Systems Status October ‘07
ITI Portfolio Plan Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Current Date Visibility of ITI Projects ITI Projects.
Renovation of the 45-year old PS magnets
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
Experience between AMORE/Offline and sub-systems
<Location> – <Project Name>, Sponsor: <name>
2016 FIT FOR PERFORMANCE Weight Control Program
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Gantt Chart Enter Year Here Activities Jan Feb Mar Apr May Jun Jul Aug
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE

Step 3 Step 2 Step 1 Put your text here Put your text here
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec ITEM 1 ITEM 2 ITEM 3
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE
Trillo Apparel Company Revised Delivery Plan
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE
CSC Electronics Installation and Commissioning CSCE I&C
Presentation transcript:

21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning and Installation” K. Safarik: “Strategy for Data-Taking, Alignment and Calibration”

21 Mar 2007ALICE - Paul Dauncey2 Installation: Recent Progress Major milestones recently achieved SSD and SDD mounted on ITS frame ITS frame lowered into pit and inserted into TPC Be beam pipe passed through and connected to absorber Current status Beampipe now in bake-out Bake-out period shortened From 26 to 17 days Assumes no leaks will be found

21 Mar 2007ALICE - Paul Dauncey3 Integration: Constraints W. Riegler NOW

21 Mar 2007ALICE - Paul Dauncey4 Installation in series means every detector is on the critical path Every delay counts against the overall ready date Delays have built up over the last year TPC was taken into pit in Mar 2006 Ready for ITS on 1 Feb; at CR06 this was 1 Oct ITS was actually installed on 15 Mar ITS delay due to SDD tests; cannot be fixed once installed Roughly 5 months delay since CR06, 1 month since Jan LHCC “Luckily”, LHC schedule delayed by 4 months since CR06 Rest of delay compensated by breaking strict ordering for A-side forward detectors Very little contingency left for planned detector Would need to move to nights and/or weekends Or not install some components Installation: Comments

21 Mar 2007ALICE - Paul Dauncey5 V0, T0: Apr FMD3: Apr Installation: C-side Forward Detectors All thee detectors are ready for installation Procedure tested in full in 2005; confident of this step

21 Mar 2007ALICE - Paul Dauncey6 SPD: 27 Apr – 2 May Connections: 3-9 May Installation: SPD, connection to ITS Most difficult part; pixel detector needs to be on time

21 Mar 2007ALICE - Paul Dauncey7 FMD2: 8-11 May Services: 14 May – 7 Jun TPC movement: 8-13 Jun Beampipe: Jun Installation: Services, FMD, beampipe

21 Mar 2007ALICE - Paul Dauncey8 PHOS, one module: Jun EMCAL support: 26 Jun – 2 Jul Installation: PHOS, EMCAL

21 Mar 2007ALICE - Paul Dauncey9 TOF, TRD modules 3-30 Jul Installation: TOF, TRD Adds extra modules to existing installation Realistically is contingency End date won’t change even if start date is later

21 Mar 2007ALICE - Paul Dauncey10 Miniframe: 31 Jul - 5 Sep Installation: Miniframe Schedule Review in Sep recommended bringing this forward At the expense of installation of other detectors This recommendation was not taken up Critical milestone: carries services for almost all A-sides No installed detectors can read out on A-side until miniframe is in place LHC vacuum closes after installation; no time to fix anything

21 Mar 2007ALICE - Paul Dauncey11 V0, T0, FMD, PMD: 6-25 Sep Shielding: 26 Sep – 9 Oct Installation: A-side Forward Det, Shielding A-side forward detectors pushed after beampipe closure to make schedule; no apparent downside

21 Mar 2007ALICE - Paul Dauncey12 Critical: A-sides won’t connect until Sep Not all services in place yet… …although scheduled to be by the time the relevant detectors arrive

21 Mar 2007ALICE - Paul Dauncey13 L. Leistam

21 Mar 2007ALICE - Paul Dauncey14 L. Leistam

21 Mar 2007ALICE - Paul Dauncey15 Services and power supplies Services are not complete CAEN power supplies are a “real concern”; still no real progress Space in the pit Space is extremely tight for people working on the installation of detectors and services Miniframe Effectively a huge patch panel Planned by subdetectors semi-independently; no overall plan shown Commissioning: Issues

21 Mar 2007ALICE - Paul Dauncey16 K. Safarik Estimates 20k events for this

21 Mar 2007ALICE - Paul Dauncey17 Cosmics is an essential step before beam data Only way to be sure all timing, event building, etc, is right Otherwise, Nov beam will be used for commissioning, not calibration and alignment Current plan is mainly parasitic running until Oct 10 Installation continuing Installed detectors run as-and-when ready After this, full detector cosmics running can occur 4 weeks scheduled, roughly half without magnet on, half with magnet on Alignment requires ~20k cosmic events in SPD Rate is ~ 1/min; requires ~14 days Completely fills allotted time No spare time for actual commissioning of whole detector readout Commissioning: Cosmics

21 Mar 2007ALICE - Paul Dauncey18 Installation: Very significant progress Whole schedule at risk from delays from all remaining detectors Accurate up-to-date knowledge of the LHC schedule is essential Coordination across subdetectors is good and well managed Commissioning Individual subdetectors have done many tests in the lab Need to increase as centralised activity in the pit Lack of services, particularly on A-side will be a drawback Cosmics are a valuable tool but are at risk of being lost as a contingency buffer for any further schedule delays Recommend appointing a “Cosmics Manager” To plan the cosmics running in detail (like the CMS MTCC) To make sure it happens and the data are analysed Conclusions