Linac4 Project Meeting 1/2010 19/01/2010 1. 1st priority 2  First priority: from the Linac4 project, the best wishes to you and your families for a 2010.

Slides:



Advertisements
Similar presentations
CFS TIME SCHEDULE EDR - CFS Europe – Kick-Off Meetings Kick-Off Meetings, CERN, 3, 4, 5 September ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe.
Advertisements

Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
February 2009 Summary of Chamonix 09 Steve Myers.
SCIENTIFIC ACTIVITIES AND BUDGET ESTIMATES FOR 2007 AND PROVISIONAL PROJECTIONS FOR THE YEARS AND LONG-TERM PERSPECTIVES White Paper Robert Aymar.
Accelerator Schedules LHC and LHC Injectors Schedules MSWG meeting 16 January 2015 SPSC - 13 January 2015 Rende Steerenberg, BE/OP2 Rende Steerenberg,
CERN: important events Restart of the LHC: –First beam on 20 November at 0.45 TeV –First collisions on 23 November, followed by slowly ramping up the beam.
Dr. José Miguel JIMENEZ LS2 Coordinator LHC Performance Workshop (Chamonix 2014) Session 8 - Long Shutdown 2 Strategy and Preparation Chair: José Miguel.
Controls & Monitoring Schedule J. Leaver 02/11/2009.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
LINAC4 STATUS Alessandra M. Lombardi for the LINAC4 team 1.Motivation and goals 2.Status of Linac4 2 years after official start of the project ( )
Impact on Project Planning and Cost. Agenda CERN Project Budget Planning Summary E. Gschwendtner, 9 April
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
TS, Length of YETS EYETS LIU & CONS Project
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Linac2 Review  L2 operated with 99 % uptime in 2010 and 98% in the last 10 years  Systems review: all under control even for L2 till LS2 if ‘nightmare’
1 1. Some recent views ( ) 2 Linac tunnel
IEFC WS March 2011 Middle-Long Term Needs for Ion Beams S. Maury 111 Middle-Long Term Needs for Ion Beams S.Maury Thanks to T. Bohl, C. Carli, D.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
EVM Today & Tomorrow ST Workshop 2003 I. Bejar Alonso.
Technology Department WP2 Progress Report Th. Otto
Workshop Objectives & Highlights from Daresbury Meeting Erk Jensen, CERN.
NA61 11 October 2010Light Ion for NA61/ S. Maury1 Light Ion in SPS Foreseen to have primary Ar beam physics in 2012 Nothing runs in 2012 NA61 duty cycle.
Linac4 Status 1 M. Vretenar sLHC public event
Session 7: I-LHC Organization: Chamonix Summary Session7; Oliver Brüning 1 -session organized in collaboration with D. Manglunki and all speakers.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
PHIN Fabrication of a photo-injector for the CTF3 accelerator and for the NEPAL test stand WP 4 of the JRA2 PHIN 1.Status of the construction of RF guns.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Resources, Schedule and Risk Management Pierre Bonnal CERN DG-DI Projects Support Office 1 st HiLumi LHC Collaboration Meeting 16 th to 18 th November.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
Ian Bird LCG Project Leader Updating the Resource Planning for 2009/2010.
LHC Injectors Upgrade Project 1/12/2010 R. Garoby.
Update on the M1 schedule Muon Meeting March 23, 2009 Burkhard Schmidt.
28 th January LHC Performance Workshop Session 8: (E)YETS and Long Shutdown 2 Strategy and Preparation. Long.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
Dr. José Miguel JIMENEZ LS2 Project Leader, CERN 1 LS2 Days 30 th September2015.
1. Linac4 Timescale 2  Technical design report issued December 2006  Project approved by CERN Council June 2007  Official start of project January.
1 st of April st LS2C LS2 Committee Mandate and Organization 2 Chairman:Jose Miguel JIMENEZ Deputy:Jean-Philippe.
CERN GS Department CH-1211 Genève 23 Switzerland cern.ch/gs-dep Internet Services GS AIS General Services Department GS Advanced Information Services EVM.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
LHC Injectors Upgrade Project 11/11/2010 R. Garoby.
SLHC – PP Budget April 3rd, 2008 CERN April 2, 2008 M.C.
Update on the Critical Path of the PS Booster Schedule for the EYETS
Controls & software Andy Butterworth.
Updated with comments 22 may 2017 Updated again 29 June 2017
LHC schedule.
LINAC4 50 MeV phase BIS STATUS
The end of an ERA: the achievement of the LHC
Installations, modifications, consolidation in 2005:
Renovation of the 45-year old PS magnets
Upgrade Strategy for the Experimental Vacuum Systems
Overview & baseline of LS2 and roadmap for CRG
Benoît DAUDIN (GS-AIS-PM – CERN) 22-March-2012
RNE Technical meeting February 2018, PCS UG.
ABP/RTL Main RTL Activities for 2007/8:-
Linac Coherent Light Source (LCLS)
Update on Linac4 Status, Reliability Run and Modelling
LHC Machine Advisory Committee, CERN 12th June 2008
ATS Consolidation Day 22nd May 2019 Beam Instrumentation
Presentation transcript:

Linac4 Project Meeting 1/ /01/2010 1

1st priority 2  First priority: from the Linac4 project, the best wishes to you and your families for a 2010 full of health and happiness.

2nd priority : Linac4 schedule 3  At Chamonix, will be presented (and approved) a new schedule for all the activities in the A&T Sector.  Following the request from the physicists and the situation with the Inner Triplet project, it is very likely that the connection of Linac4 to the PSB will take place in the 2014/15 Shutdown.  In the future, the CERN schedule will alternate long and short shutdowns (2-year run periodicity) with long shutdowns in 2010/11, 2012/13 and 2014/15.  But: the 2014/15 shutdown cannot be missed (next long one in 2016/17…).

New schedule – main lines 4  Conclusion: wisdom suggests to keep the present linac installation and commissioning schedule, and foresee the additional year (2014) for extended commissioning time, in order to: a) absorb delays, b) sort out potential reliability issues, c) improve performance.  Only consequence: the linac dump should stand 1 year of testing beams (precise conditions to be defined). End 2013: Linac4 completed Fall 2014: start connection to PSB

Linac4 schedule – what will change 5 Present Master Plan, approved in April 2009 Only this part will be moved by 1 year ! 1. Construction 2. Linac installation, commissioning 3. Connection and PSB commissio ning

Linac4 Resources – what’s new? 6  This year, the management wants to give consistency to MTP (resources) and MPP (manpower) plans, arbitrating between conflicting projects and coming out with a schedule compatible with the available resources.  There will be “baseline” projects and “add-on” projects. Linac4 will clearly be a baseline project (together with LHC, injectors, consolidation, Inner Triplet…).  In case of conflict for manpower between baseline projects, the management will rearrange the schedule accordingly to the priorities.

Linac Budget 7 In MCHF spent / 18.2MCHF = 80%. We need to define soon the 2010 allocations (26.5MCHF were foreseen for 2010 in the MTP). The WP Holders will have to update the budget table.

EVM needs you… 8  After Chamonix, the schedule will be clear and we have to redo the EVM Baseline.  In February, you will all have a chance to update your EVM Workunits with the new schedule and any other change that you foresee is necessary.  Deadline end of February for updating the workunits, March 15 th for completing the new EVM baseline (all WUs loaded).  And then, hopefully, we can go with the same baseline till the end of the project…

Changes in the Project  Pierre Bourquin retires at end of March.  Remo Maccaferri retires at end of July.  (+ Lyn Evans retires at end of May). The enthusiasm and experience of these colleagues have been essential for setting up the project (in a sense the most difficult phase…), and we have now have to start preparing the transition!