COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.

Slides:



Advertisements
Similar presentations
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Advertisements

November 17, 2008 ILC08 HVAC and VE Update November 17, 2008 ILC CFS Workshop 2008 Chicago Lee Hammond, Fermilab Global Design Effort.
44 th Annual Conference & Technical Exhibition By Thomas Hartman, P.E. The Hartman Company Georgetown, Texas Sustainable Chilled Water.
UTSW Thermal Energy Plants, Power Generation and Electrical System What do we do to meet the Emission Reduction, Energy usage Reduction and Electrical.
SAFETY FOLLOW-UP HL-LHC PROJECT WP17 – Infrastructures meeting S. La Mendola, Jose Gascon DGS/SEE 09 July 2015.
HSE Preliminary General Requirements for FCC layout and air management A. Henriques & M. Widorski on behalf of the HSE Unit 17/12/2014 FCC I&O Meeting.
Value Engineering Session Air Treatment / HVAC November 27, 2007 Lee Hammond, FNAL CFS.
First Considerations on CLIC Cooling System Ch. Martel, J. Inigo-Golfin TS/CV.
Conventional Facilities and Siting Global Design Effort Safety Requirements for IR Conventional Facilities and Siting Group Safety Requirements for IR.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
Chilled water Meyrin consolidation Study 1 st Part Many thanks for their contribution to: Pasquale Alemanno, Fortunato Candito, Alexander Putzu.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
1 11/11/2003 NBI Decay Tube and Windows Presentation by Ans Pardons 1 Decay Tube & Windows Introduction (Location, Planning) Decay Tube Entrance.
Urban Water Department of Hydro Sciences, Institute for Urban Water Management Peter Krebs Dresden, Global water aspects 1 Introduction to urban.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
September 19/20, 2007 SIS 100 Magnet cooling and cryogenic distribution.
EN-CV during LS1: Upgrade, Consolidation, Maintenance, Operation M Nonis EN/CV Chamonix 2012 – LHC performance Workshop On behalf of EN/CV Group.
HOW THE DUMP RESISTOR’S TANK LOOKS LIKE COOLING OF THE LHC ENERGY EXTRACTION RESISTORS G. Peón (ST/CV), K. Dahlerup-Petersen, G. Coelingh (AT/MEL) Air.
VENTILATION PRINCIPLE FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 28/7/2009 Already presented by C. Martel/ J Inigo Golfin on15 th October 2008 CLIC WORKSHOP.
John Osborne : GS-SEM Civil Engineering 19 May 2009 Report on behalf of CLIC Civil Engineering and Services (CES) WG CTC 19 May 2009 Tunnel Cross Section.
How to reduce cooling duties in CLIC M. Nonis EN/CV CLIC Workshop th February 2014.
Civil Engineering and Services - drawings for CDR - CDR chapter J.Osborne and M.Gastal for CES WG 1.
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
COOLING & VENTILATION FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 16/9/2009 CLIC TWO BEAM MODULES REVIEW
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
MDI Meeting 13 th MDI: Latest news on civil engineering and services First draft concept for the ventilation system in the CLIC experimental area 11/06/2010.
C.KotnigFCC Design Meeting FCC Beam Screen cooling Claudio Kotnig.
VENTILATION PRINCIPLE FOR THE DRIVE BEAM TUNNEL CERN TS/CV Wednesday 9 th July 2008 CLIC.
Europe / CERN studies for SB2009 ILC Re-Baseling J.Osborne CERN (CFS & CES) 2009 Linear Collider Workshop of the Americas 28 September - 4 October 2009.
The integration of 420 m detectors into the LHC
Risto Nousiainen, CLIC workshop ” Technical Issues, Integration & Cost ” working group Progress on Study of Module Cooling Risto Nousiainen.
MDI Meeting 13 th MDI: Latest news on civil engineering and services First draft concept for the ventilation system in the CLIC experimental area 11/06/2010.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
Design considerations for the FCC electrical network architecture FCC week 2016, Rome, April 2016 Davide Bozzini - CERN/EN/EL With the contribution.
N-TOF review HVAC and cooling systems Proposal to be validated by the project CERN TS/CV 13th February 2008.
Rosanna Cocimano Amsterdam, 5-6 July 2010KM3NeT WPF/L General Meeting Rosanna Cocimano INFN LNS Power plan for detector layout Presented in TDR.
Technical Review EHN1 Extension Cooling Systems and Pipework Jérôme Rodary / EN-CV.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Ullrich, DESY Dubna GDE XFEL The European X-Ray Laser Project X-Ray Free-Electron Laser 1 Water cooling XFEL Desingn of the XFEL water cooling.
HIE-ISOLDE Workshop: The Technical Aspects Target Area Infrastructure Ventilation 29 November 2013 Andrea Polato* - CERN EN-CV-PJ * The research project.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
FCC Refrigeration cost vs magnet temperature Laurent Tavian CERN, ATS-DO 15 February 2016.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
E- source kick-off meeting e- Source RDR- Conventional Facility & Siting Overview Fred Asiri/SLAC.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
ILC Utility Design Study for Kitakami-site
Update on the PSB Cooling and Ventilation Systems
Review of the International Linear Collider (ILC) Electrical and Mechanical System Design to be held at CERN on 21 March, 2012 The purpose of the Review.
ARAC/H/F Air-cooled water chillers, free-cooling chillers and heat pumps Range: kW.
CLIC Civil Engineering Update
Conventional Facility & Siting (CF&S) Overview for the Positron Source
CLIC Civil Engineering & Infrastructure Working Group Meeting
CLIC Civil Engineering & Infrastructure
Innovative He cycle Francois Millet.
Americas KlyCluster Cost Analysis Overview
News from Integration WG
Tunnel Cross Section Studies
FCC Tunnel and Shaft Cross Sections
Cooling systems for HL-LHC (WP17.3)
COOLING & VENTILATION INFRASTRUCTURE
CLIC Civil Engineering Update
EN-CV: P8 systems and Detector Cooling
Cryogenic cavern in Asian site
Workshop on fire protection for physics research facilities
LINAC 3 Meeting ICL machines Injectors
Presentation transcript:

COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016

Content Main input data Civil engineering layout Heat loads Cooling plants Requirements General architecture & specific issues Ventilation plants Requirements General architecture Services in the tunnel cross section Conclusions & next steps Acknowledgements: G. Peon, A. Rakai, Members of I&O WG FCC Study Annual Meeting - 14 April M. Nonis2

Double Tunnel Option Single Tunnel Option FCC Layout FCC Study Annual Meeting - 14 April M. Nonis Safe Tunnel  6 m  4.5 m 3

Impact on CV systems FCC Study Annual Meeting - 14 April M. Nonis Present studies focus on how we will comply with the requirements, not on detail design of each system. The two options (one - two tunnels) do not have a major impact on the choice of the technical solution to adopt. In addition, similar technical solutions can be proposed for the FCC-hh and for the FCC-ee. Differencies on the size of the plant are based on the geometry and on specific heat loads. Where needed, specific systems will be implemented in case of high demanding requirements. 4 In the following slides the FCC-hh option with one single tunnel is taken into account as baseline for this talk.

Technical heat loads FCC-hh FCC Study Annual Meeting - 14 April M. Nonis WATERAIR Surface [MW] Underground [MW] Surface [MW] Underground [MW] TOTAL [MW] Magnets Cryogenics RF Power converters HV Cables Experiments Others TOTAL TOTAL TECHNICAL HEAT LOAD: MW

Main input data Cooling plants Ventilation plants Services in tunnel cross section Conclusions & next steps

Requirements to cooling plants FCC Study Annual Meeting - 14 April M. Nonis Reliability of systems Operability although long distances & altitude variations: Leaks, pressure losses, static pressure Minimize environmental impact: Noise Visual impact Water consumption Cost 7

FCC-hh: heat loads cooling circuits [MW] FCC Study Annual Meeting - 14 April M. Nonis MWL-AAsAuA-BBsBuB-CCsCuC-DDsDuE-DEsEuE-F Cryo RF Exper Gen services Magnets Pow converters Chilled water Total Total point MWFsFuF-GGsGuG-HHsHuH-IIsIuI-JJsJuJ-KKsKuK-LLsLu Cryo RF 4.5 Exper Gen services Magnets Pow converters Chilled water Total Total point POINT A Power kW ∆T K Q m3/h ND mm H bar Primary43,000152, Primary (shaft)3, Cryogenics S20,000151, Experiments S10, Gen services2, Chilled water5, Power converters Cryogenics U1, Tunnel circuit L-A Tunnel circuit A-B Experiments U2, make up water (5%)

Cooling plants for FCC-hh FCC Study Annual Meeting - 14 April M. Nonis One cooling plant in each Point : Surface buildings Underground equipment in cavern Alternate Points: one station in cavern cooling two adjacent sectors N+1 redundancy for main equipment 53 MW 11 MW 43 MW 5 MW 53 MW 52 MW 43 MW 11 MW 16 MW 9 Pow Converters Chilled water Cryogenics Sector left Circuit n Sector right

Main user: make up water for cooling towers Around half of the Points should be directly fed by water from local network. Other Points supplied by underground pipeline cast in the concrete slab of the tunnel. Fire fighting in underground: make up water pipe (where existing) dedicated pipe in other sectors. Fire fighting in surface: preferably from local network. Water supply in FCC Points FCC Study Annual Meeting - 14 April M. Nonis A L K J I H G F E D B C 10

Constraints - specificities FCC Study Annual Meeting - 14 April M. Nonis Underground depth (400 m): static pressure 40 bars separate circuits between surface & underground. Sector length (10 km): increase diameter to reduce pressure losses  avoid use of booster pumps, sectorization valves and connection to drain along the sector, balancing of circuits more complicated, inlet temperature fine tuning at equipment level (if needed). 11 Altitude variation in sector: max ~100 m  10 bar reduce pressure in tunnel at manifold level, differential pressure reducer on each manifold.

Main input data Cooling plants Ventilation plants Services in tunnel cross section Conclusions & next steps

Requirements to Ventilation Plants FCC Study Annual Meeting - 14 April M. Nonis Reliability of systems: Heat loads Safety related: Tunnels: air speed between 0.7 and 1.4 m/s Pressure cascades: Fire safety: safe area  technical area: 20 Pa Higher radiation area  lower radiation area: 20 Pa Smoke and He extraction Cost 13

Air speed - operating conditions FCC Study Annual Meeting - 14 April M. Nonis 123 Volume change/hr Flow rate [m3/h] Air speed [m/s]11.53 Distributed pressure loss [Pa] Localised pressure loss [Pa] Total pressure loss [Pa] Accelerator tunnel Safe tunnel 123 Volume change/hr Flow rate [m3/h] Air speed [m/s] Total pressure loss [Pa] Standard equipment – industrial fans 14

Pressure cascade: main features One ventilation system per zone to manage pressure difference wrt adjacent areas. Use of air locks for connecting galleries. Overpressure for safe tunnel ensured by dedicated devices at each passage among the two areas (air curtains – air locks): Independent from number of doors opened Failure of one equipment does not affect safety in other passages. FCC Study Annual Meeting - 14 April M. Nonis Accelerator tunnel Safe tunnel 15

FCC Study Annual Meeting - 14 April M. Nonis16 Ventilation of the FCC underground -20 Pa-40 Pa -20 Pa +20 Pa Dump zone Collimation region P

FCC Study Annual Meeting - 14 April M. Nonis17 Ventilation of the FCC underground -20 Pa-40 Pa -20 Pa +20 Pa Dump zone Collimation region P

Ventilation Scheme Accelerator & safe tunnel FCC Study Annual Meeting - 14 April M. Nonis Tunnel wall temperature: 20 °C Air temperature increase in tunnel: 8 °C Temperature: 17 °C - 25 °C Air recycling (values for accelerator tunnel): Use of free cooling 21% of time on full fresh air configuration  Need for (minimum) 12 additional extraction AHUs Reduce energy consumption of 11.5 MWh/ yr. ROI < 3 years (Statistics 2000 – 2014) T [°C]< 5°C 5  1010  1717  2222  25 >25 Hr/year2’1971’8232’5441’ %25%21%29%15%6%4% RecyclingPartialNoFull 18

Main input data Cooling plants Ventilation plants Services in tunnel cross section Conclusions & next steps

Cooling and ventilation services in tunnel FCC Study Annual Meeting - 14 April M. Nonis Cooling pipes Make up water pipe Tunnel air ventilation 20 Fixed & rolled curtain ref. A. Henriques talk «Conventional Safety» Smoke and He extraction duct

Main input data Cooling plants Ventilation plants Services in tunnel cross section Conclusions & next steps

FCC Study Annual Meeting - 14 April M. Nonis The general architecture has been defined. Mainly industrial existing solutions foreseen. Detailed studies for different options will follow. Custom made solutions to be applied wherever necessary. Further studies will focus on: Environmental impact, Improve overall efficiency of the systems, Valorisation of waste heat. Conclusions & next steps 22

THANK YOU FOR YOUR ATTENTION