Presentation is loading. Please wait.

Presentation is loading. Please wait.

ILC Utility Design Study for Kitakami-site

Similar presentations


Presentation on theme: "ILC Utility Design Study for Kitakami-site"— Presentation transcript:

1 ILC Utility Design Study for Kitakami-site
CFS WG AWLC-SLAC ILC Utility Design Study for Kitakami-site H. Hayano (KEK) for M. Yoshioka, T. Sanuki, T. Onuki, S. Narita, T. Okamura Y. Murakami, H. Aoki, I. Kumagai, Y. Kamezawa (Tohoku-ILC-preparation-office and KEK) Acknowledgement to Tohoku Electric, Toshiba, Yurtec, Takasago Thermal Eng, Atox, Maekawa, Tobishima, QST, Iwate Pref., Oshu City, Ichinoseki City, Ichinoseki Fire Station, AAA, LCC/ILC, KEK

2 Utility Design Targets, Conditions and Proposals
Make the overall utility design specific to Kitakami Candidate Site Estimate Cost for All Utilities with easy decomposition for the staging case Estimate Installation Schedule of All Utilities Use TDR ECM=500GeV Accelerator (high-lumi upgrade) as a basement Two Vertical Shafts and One slope access in the collision point site One slope access in Damping Ring Far End streight section (proposal) Design change for under-ground access halls and passway (proposal) Six Slope Access for Linac, such as PM+/-8, PM+/-10, PM+/-12 No PM+/-13(escape access, water-drain) but One water-drain tunnel from the collision point (proposal)

3 Name Convention Interaction Region PM-12 AH-12 AS-0 AS-0a AS-12 PM-10
electron linac AS-0a AS-12 AH-10 PM-10 AS-0b AH-0a AS-10 PM-8 AH-8 AH-0 Interaction Region AS-8 damping ring PM+8 AH+8 AS+8 PM+10 AH+10 positron linac AS: Access Station (surface) AH: Access Hall (in tunnel) PM: Point of Merging with access tunnel AS+10 PM+12 AH+12 AS+12

4 Electric Power Distribution Design

5 Electricity Access Redundant power supply from (1) Local electric company and (2) LNG-CGS Mizusawa Station J-PARC 154 kV, 15 km Aerial wire Riken Main substation co-generation J-PARC Main substation

6 Electric Power from Tohoku Electric Co, Mizusawa Station
ILC Trans Yard (reserved!) Reserved Trans Yards Two 154kV Trans Yards

7 Electric Power Load Table

8 Design of Electric Power Line System (1)
Main subsation 66 kV Co-generation Substation 66 kV Lines 154 kV receive at AS-0 surface 66 kV receive at every AH in the tunnel 6.6 kV Lines Local Station 66 kV Lines Distribution in tunnel 6.6 kV receive at Main Linac Klystron Tunnel (400V, 200V, 100V distributed) Main subsation

9 Design of Electric Power Line System (2)
Main subsation 66 kV Co-generation Substation at Access Hall 66 kV Lines 6.6 kV Lines 154 kV receive LNG space Local Station AH tunnel AS surface Number of local substation 54 in total splittable racks, distribute in-between Klystrons Linac RF tunnel

10 Air, Cooling Water Distribution Design

11 Cooling Water Supply from Oshu-city
Water supply system from the Isawa dam facility to the access stations through pipe in the linac tunnel (250 A) Banshouji point ~13km Isawa Dam ILC From Oshu-city Banshouji Point, water supply availble. IP

12 Design of Cooling Water System
Chiller and pumps Main Linac Cooling Water Schematics Access Station Access Hall Main Linac He compressor cooling Design conditions; 35 degree supply, DT = 30 degree (15 degree for racks and WG, 5 degree for He compressor), T control = +/- 1degree ordinary device, Pressure-forward,backward = determined from flow rate and pipe diameter, required flow-rate = from sum-up of RF unit power, assumed values for BDS and DR Water reservoir & supply

13 Design of He Compressor Cooling Water System
Circulation pump 32℃ 8 compressor for one cryo plant DT =5C 37℃ Ground surface Access station Outdoor yard Closed water cooling type cooling tower Machine room Compressor room Circulation pump 32℃ 37℃

14 Design of Water Drainage System
Access Station (surface) Access Hall (tunnel) Design conditions; drainage spring water from tunnel surface to the surface, use spring water as cooling water, or just dump

15 Design of Ventilation System
RF tunnel accelerator tunnel Design conditions; 1/3 of circulation air is exhausted out with HEPA filter, 1/3 fresh air is taken in. put air into RF tunnel, exhaust air from accelerator tunnel, through holes of shield wall.

16 Temperature Settings Matters to consider
Water temperature measurement by ground water observation hole as a function of elevation (by Iwate Prefecture/Tohoku Univ./Yachiyo Engineering) Matters to consider Cooling water temperature setting with emphasis on economical operation RF: 35℃⇒65℃ Cryo: 32℃⇒37℃ ・・・・・ Air conditioning temperature setting with emphasis on economical operation Temperature of the under-ground (13.4℃) + α = 18℃ depth (m) ILC

17 Design of Air Conditioning System
Air handling Unit at the Surafce Cooling water system for air conditioning in the ML tunnel (1) Distributed Fan Coil Unit. (2) 7degree chilled water is supplied for FC (piping with 200A). (3) Chilled water is produced with Chiller unit located at the AS. Air handling Unit in Tunnel Distributed Fan-Coil Unit in RF Tunnel, no FC in accelerator tunnel.

18 Design of Main Dump Water Cooling System
Pump and Chiller Unit in Surface Pump Unit in Tunnel

19 Design of RI Water Drainage System
undergorund surface

20 Cryogenics Arrangement Design

21 Design of Helium Cryogenics System (1)
Surface Access Tunnel Access Hall Accelerator Tunnel

22 Design of Helium Cryogenics System (2)
Surface Facility Cold Box in Access Hall Accelerator Tunnel side Access Tunnel side

23 Proposals of surface facility Design

24 Collision Point Surface
AS-0 surface Collision Point Surface Total Area ha each zone is splittable, Area shape can be modified

25 Damping Ring Access Surface
AS-0a surface Damping Ring Access Surface Total Area ha each zone is splittable, Area shape can be modified

26 Main Linac Access Surface
AS-12 surface Main Linac Access Surface Total Area 1.66 ha each zone is splittable, Area shape can be modified

27 Change proposals of underground facility Design

28 Proposal of Utility Cavern Movement at Interaction Point
Considering power flow, water flow and air flow between the surface through utility shaft and the accelerator devices, location of Utility Cavern is reconsidered. Surface Facility to DR to DR Energy Flow Vertical shaft Utility Cavern to DR to DR Energy Flow tunnel to RTML to RTML Underground accelerator to ML, BDS, BD to ML, BDS, BD to DH

29 Proposal of Utility Cavern Movement at Interaction Point
Considering power flow, water flow and air flow between utility shaft and the devices, TDR modified (two vertical shafts) Proposed design of Utility cavern Floor Area 50m x 20m = 1000 m2 Tunnel 8m x 200m =1600 m2 Floor Area 25m x 25m = 625 m2 Bypass tunnel 3m x 200m =600 m2 connection tunnel between Utility and DR Bypass tunnels between Utility and ML, DH, BDS, dumps

30 Proposal of Functions of Utility Cavern extension at Detector Hall
25m Extension of Detector Hall 5th Floor 3rd Floor 4th Floor 1st Floor 2nd Floor Concerns accelerator/detector effect from mechanical vibration, AC power lines effect on utility device from detector magnetic field leakage

31 Proposal of New Access Hall shape for Main Linac
TDR Access Hall Proposal of New Access Hall shape for Main Linac direct access of Electric, Water/Air, Helium to Main Linac Tunnel. separate halls for electric, water, helium Keep enough room for cables, pipes, ducts and helium trasfer lines Hall:2998 m2 tunnel: 2010 m2 total area=5008 m2 total volume=38395m3 Proposed Access Hall go to surface 135m After cryogenics change request Hall:135m x 20m = 2700 m2 hight=13m, tunnel:2284 m2 hight=7.5m total area=4984 m2 , volume=52230m3

32 Proposal of pipes(He, Water and air), power cables arrangement
in the access tunnel This figure shows only the required space in access tunnel for cable and rack It is not the actual installation plan Access tunnel: Required space for Piping Cable rack

33 Summary of Kitakami-site Utility Design and Proposals
Design studies for ILC Utility specific to Kitakami-site have been done for AC power line, Water, Air-conditioning, surface area, and so on. Several new proposals are proposed, we will continue to discuss them for new change request. Cost estimation is on-going for comparison to TDR Further Design change is in consideration for more cost-down.

34 End of Slide


Download ppt "ILC Utility Design Study for Kitakami-site"

Similar presentations


Ads by Google