MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE RF workshop 16t h February 2012 Daresbury Laboratory Response to RF review for the MICE RF system.
Advertisements

Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
RF systems for MICE Andrew Moss The MICE RF Group and the TIARA WP7 Team Contributions include Daresbury, RAL, CERN, LBNL, LANL, FNAL, Strathclyde & Sheffield.
Andrew Moss Daresbury Laboratory Collaboration Meeting th 19 th October 2012 RAL MICE RF System review.
Andrew Moss Daresbury Laboratory August 2013 Latest results of MICE amplifier testing.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
RF Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration Meeting.
Andrew Moss Daresbury Laboratory Collaboration Meeting th -16 th February 2013 Coseners House MICE RF HP System rprogress.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Andrew Moss ASTeC Collaboration meeting CM29 15 th - 18 th February 2011 MICE RF System.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Electrical & Control Power Supplies Trevor Hartnett.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
MICE VC 10-Oct-2013 Alain Blondel 1 MICE NEWS VC 162 LOTS OF THINGS HAPPENED! have arrived at RAL: -- EMR (see report today) -- AFC2 see pictures -- SS2.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
Progress on the MICE RF High Power Drive Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE CM38 RF Parallel Session.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 Collaboration Meeting 33 - Glasgow 26 th June 2012 Design Layout Andrew Moss for Alan Grant, STFC.
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
RF Review CM37 Andrew Moss. Amplifier results at Daresbury 2MW at 35kV, good efficiency and gain.
MICE RF Power Status Paul Drumm ~ Sunday August 1 st 2004.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
MICE RF – Installation at RAL Tim Stanley, MICE RF Engineer, RAL 2 June 2014.
Development of CAD concept model of package transformer substation (PTS) Aleksandra Seledkova Perm National Research Polytechnic University.
Standalone Commissioning Plan in MICE Hall K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review 9th Sept 2016.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
MICE HPRF Up-date Tim Stanley RAL – Testing 212 kW achieved from driver stage 4616 #1 at DL, ready for endstage 116 #2. Good experience, in tuning.
ELENA installation progress F. Butin / ELENA collaboration.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Chris Booth Sheffield 29th March 2006
MICE CM28 Engineering Session Summary (On behalf of Wing)
MICE RF System Power Supplies, Control and Monitoring Status report
MICE Target Report Video Conference 29/11/07
MICE CM31 Schedule summary
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Presentation transcript:

MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013

RF Amplifiers - Performance

2 MW RF output was achieved at Daresbury, in July, on the TIARA amplifier chain. PSU trips were mitigated to allow high enough HT supply voltage (35 kV) to achieve the 2 MW RF Amplifiers and PSU racks were dismantled and arrived at RAL MICE Hall mid-August.

TIARA System – Plan A

End-stage, ground floorDriver stage and PSU racks

Preparations for Installation CAD drawings are complete (DL); electrical drawings are complete (DL); detailed installation drawings generated by RAL.. Alternative layout, of o/p co-ax, will be implemented; avoids significant lead-time for floor mods. Safety Document generated by RF group and being ratified at RAL. TS appointed EMF Protection Advisor.

Procurement of Co-ax RF TX lines MEGA, in the USA, have fulfilled full order of parts for entire MICE RF system. Importation, under MoU, via Univeristy of Mississippi, achieved late September. Many thanks to Don Summers, and UMISS, for supply of co-ax and other components of RF system

Arrival of a batch of TX lines at RAL

6” co-ax

6” co-ax – assembly practice

Mechanical Installation PSU and Control racks (5) craned into position during August. End-stage amplifier craned-in during September

Mechanical Installation – End-stage

Mechanical Inst: HT PSU and SSPA

Mechanical Inst – HT PSU Rack 2

Mechanical Installation Co-ax feed from Driver stage to Endstage fitted; co-ax is rigid piping.

Mechanical Installation – 3” co-ax

Mechanical installation Driver stage accurately fixed in position

Electrical Installation Wiring of PSU and Control racks has progressed. Some re-work required owing to config of End-stage HT port.

Services - Water De-mineralised cooling water supply plumbed to MICE RF area. Dedicated closed-loop, but shares cooling with chilling system for magnets. Aiming for 21 to 24 degrees C at flow input.

Services - Water Water distribution panel manufactured; delivered and fitted at RAL last week. (Design review required post-TIARA)

Services - Water

Services - Air Supply, of dry and clean compressed air, has been provided to RF area in MICE Hall; local distribution tubes and valves being fitted.

Programme Concern that, owing to protracted test- programme at DL to mid-2013, to resolve technical issues, installation programme is very compressed. Avoiding the proposed mods., to mezzanine floor, won some time. EMR Runs during October reduced hall-time by ~50%

Programme Target dates to completion of TIARA milestone: Nov 16: Mechanical installation complete, including both amplifiers, co-ax transmission lines and loads, and all services. Nov 29: Electrical commissioning of 4616 (driver) stage complete and RF tested into load

Programme Dec 9: Electrical commissioning of 116 (End-stage) complete, ready for RF testing Dec 20: Amplifier chain functional; RF power delivered to load; TIARA milestone achieved

Early 2014 Installation of under-floor co-ax lines; needs to be completed by end of February(?) to avoid clashes with supports for return yoke and perhaps other components. All these co- ax lines are fixed-length and rigid! TS to familiarise with first RF cavity? New financial year: Build of RF amplifier system 2 commences at DL?