LHC CRYOGENICS – new experience of run with increased beam energy and intensity Krzysztof Brodzinski CERN, Geneva, Switzerland With contribution from:

Slides:



Advertisements
Similar presentations
Status of Cryogenics at point 4 following the power cut L. Tavian 20 August 2011.
Advertisements

Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
Going towards LHC Run2 CRYOGENICS 5 th Evian Workshop 2-4 June 2014 SESSION 4 - Systems 2 - Status and commissioning plans (HW perspective) Krzysztof Brodzinski.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
E-CLOUD VACUUM OBSERVATIONS AND FORECAST IN THE LHC Vacuum Surfaces Coatings Group 03/07/2011 G. Bregliozzi On behalf of VSC Group with the contributions.
SC - 04Feb'13Cryo Heaters Review Cryogenic Heaters Review Operation use and wishes S. Claudet - A. Suraci LHC Cryogenic Operation.
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
H. Herzog, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN LARGE SCALE CRYOGENIC.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
The cryogenic systems of the ATLAS and CMS detectors Johan Bremer on behalf of TE/CRG 06/06/2013AFF.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
HC review - 12 May 2005Luigi SERIO - AT/ACR/OP1 SECTOR COOL DOWN AND CRYOGENIC COMMISSIONING L. Serio.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
OLAV III Experience with the LHC Insulation Vacuum System S. Blanchard, P. Cruikshank, B. Jenninger, N. Kos, W. Maan, L. Mourier, N. Provot, J. Wallner.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Experience from large helium inventory management at CERN ILC Cryogenics and Helium inventory meeting CERN, Wed. 18 th of June 2014 D. Delikaris Technology.
C.KotnigFCC Design Meeting FCC Beam Screen cooling Claudio Kotnig.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
FCC Week 2015, Washington Cooling the FCC beam screens
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
Crab cavities – cryogenics for SPS and LHC LHC-CC13, 6 th LHC Crab Cavity Workshop – CERN, Geneva, Switzerland 9-11 December 2013 K. Brodzinski on behalf.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Vacuum Cleaning / Scrubbing measurements in the LHC J.M. Jimenez on behalf of G. Arduini, V. Baglin, G. Bregliozzi, P. Chiggiato, G. Lanza, OP.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Industrial contributions to the maintenance of CERN.
LHC Performance Workshop LS1 Session Cryogenic system: strategy to achieve nominal performance and reliable operation J. Bremer, K. Brodzinski, J. Casas,
ILC Cryogenics: Study of Emergency Action and Recovery - in progress -
Cryogenics storage and distribution
CONSOLIDATION day in view of HL-LHC Cryogenic aspects
M Chorowski, H Correia Rodrigues, D Delikaris, P Duda, C Haberstroh,
Innovative He cycle Francois Millet.
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
FCC Week 2017, Berlin Towards a conceptual design for FCC cryogenics
Update of cryogenic activities
SPS cryogenic proximity equipment and SM18 validation
S. Claudet, Daniel Berkowitz & A. Perin (TE-CRG)
LHC Performance Workshop (Chamonix 2016)
The LHC - Status Is COLD Is almost fully commissioned
CRYOGENICS – strategy, unavailability root causes and limitations
Long Shutdown for the LHC: Vacuum Beam Pipes
Dynamic simulations: a useful tool for cryogenic installations
Preparation of the activities for the LHC Long Shutdown 2
Hollow e- lens, Cryogenic aspects
Daniel Berkowitz (TE-CRG)
Activities of the ME section during LS2 ( )
How does a cryogenic system cope with e-cloud induced heat load
Cryogenic cavern in Asian site
Summary post TCC#54_02Aug’18
Cryogenic management of the LHC Run 2 dynamic heat loads
Laurent Delprat CERN, Geneva, Switzerland
HL-LHC New MS optimisation WP9, Preliminary cost estimates
Presentation transcript:

LHC CRYOGENICS – new experience of run with increased beam energy and intensity Krzysztof Brodzinski CERN, Geneva, Switzerland With contribution from: S. Claudet, D. Delikaris, L. Delprat, G. Ferlin, E. Rogez and L. Tavian

K.Brodzinski_ICEC26_ Outlook Introduction to LHC cryogenics Cryogenic operation overlook Long shut down 1 activities Preparation and operation with increased beam parameters 1.9 K circuit and heat load K beam screen circuits (cryogenics vs photon-electron cloud) Limitations and operational optimization scenarios Main failures during Run Availability and helium consumption Conclusions 2

K.Brodzinski_ICEC26_ Introduction  circumference  ~ 27 km,  constructed at ~ 100 m underground,  the accelerator ring inclination is 1.4 % Compressor station 4.5 K refrigerator 1.8 K pumping unit (cold compressor) Interconnection box LHC cryogenics: 8 x K 1800 sc magnets 24 km & K K 135 tons of helium inventory 3

K.Brodzinski_ICEC26_ Operation outlook 4

K.Brodzinski_ICEC26_ Feedback from LS1 Feedback from LS1 basing on Run2 (2015): Major overhaul and maintenance (mainly on warm compressor stations) – done and operational R2E (Radiation to Electronics): SEU (Single Event Upset) – eliminated (0 cases declared in 2015) ! Cold boxes, QRL bellows, DFBA SM – all repairs with success no leak left 71 QRL cryo valves replaced (38 on the BS circuit) - operational M M M M M M M M R R R R M – maintenance of 64 compressors R – Repairs of 4 refrigerators - QRL compensators replacement 3TU – 3 turbines replacement - DFBAs SM repairs - R2E campaign 3 TU P1 P2 P3 P4 P6 P7 P8 P5 P18 B B A B A B A A LL HL 5

K.Brodzinski_ICEC26_ Copper Stabilizer Continuity Measurement 6 Copper stabilizer  current conductor during resistive transition (quench). Consolidation + successful tests done during first LHC long shutdown. Example of non-conformity Cryogenic conditions adjustment for the test: -20 K and 4.5 bar in the cold mass (out from superconducting condition) -Supercritical helium in main supply line with J-T valve + bayonet magnets HX in use

K.Brodzinski_ICEC26_ Magnets training for 6.5 TeV Statistics for 1232 dipoles: 1064 did not quench, 168 did quench (9 - twice, times) 179 quenches in total Contribution G. Willering Courtesy of CERN TE-MPP team ~ 6 hours 7

K.Brodzinski_ICEC26_ K circuit IFJ-PAN_K.Brodzinski_ PK visit_K.Brodzinski_ K. Brodzinski, CryoOps, KEK - Japan 2012 ~ 214 m subsector F D Return (4.5 K, 0.3 Mpa) Screen (70 K, 1.6 Mpa)

1.9 K circuit heat load 9 K.Brodzinski_ICEC26_ Dynamic heat load on 1.9 K comes from resistive heating in the magnets interconnection splices and as beam induced heating Recalculation of the heat load for reference fills for sector 1-2 from equation (1) gives the following results where: Δh is the enthalpy difference upstream J-T valve and downstream the cold mass heat exchanger, m 1.8KPU is the flow measured by cold pumping unit and Q EH is electrical power applied on 1.9 K circuit 4 TeV operation (fill 3134): Q 1.9K = 717 W 6.5 TeV opearation (fill 4569): Q 1.9K = 878 W For one high load sector: Nominal 1.9 K = 1460 W, Installed K = 2400 W Conclusion: 1.9 K heat load for Run2 was considerably lower than nominal design and installed capacity  optimization in operation scenarios could be done

K.Brodzinski_ICEC26_ Beam screen at K and capacity Heat loads: Qs – static heat load, Q EH – electrical heater, Q BS – from beam operation (ARCs: EH is used now out of beam operation periods to avoid low velocity helium stream oscillations in BS circuit, LSS: in permanent use for stability ~50 W/sector) LHC Design Report vol. I, 2004, p.328 and p.316 Exercise for s1-2: Input: Qs=400 W, EH=49 W, Q qrl =630 W, P ref =7700 W, L totBS =6033 m Calculation: ( )/6033=1.1 W/m/a -> 2*53*1.1=116 W/half cell Exercise for 2-3: Input: Qs=400 W, EH=49 W, Q qrl =570 W, P ref =7600 W, L totBS =5971 m Calculation: ( )/5971=1.1 W/m/a -> 2*53*1.1=116 W/half cell 85 W/half cell 10

K.Brodzinski_ICEC26_ Beam screen circuit and HL at 6.5 TeV 11 During operation at 6.5 TeV with 25 ns of the inter-bunches spacing the contribution from photo-electron cloud was much higher than expected. Dedicated scrubbing did not treat the problem -> LHC was cleaned during the run. Courtesy of G. Iadarola Load per half cell: [W/hc = W/m *53*2]

K.Brodzinski_ICEC26_ BS – cleaning effect 12 In addition, the cloud was not homogeneously distributed between the sectors and in some cases pushed cryo-plants to the capacity limits. The cleaning effect is unexpectedly slower in more clouded sectors than in low clouded. The upgraded from LEP machine at P2 appeared as with the lowest capacity limit.

K.Brodzinski_ICEC26_ How to deal with the cloud The e-cloud thermal effect requires from cryogenics: 1.Fast dynamic increase of cooling capacity during injection and rump AND fast dynamic decrease of the capacity during de-dump 2.Large continues demand for cooling capacity during related fill How to deal with “1” (*) Fast dynamic control logic applied on local BS cooling loops (acting by anticipation to thermal load, triggered with information about number of injected bunches) Thermal capacity buffer of ~ K prepared before each beam injection Modification of Cryo Maintain interlock (before T=30 K during 30 s, now T=40 K, 30 min) * see more in B. Bradu et al contribution to ICEC26 Beam screen cryogenic control improvements for the LHC run 2 How to deal with “2” Process optimization – already well done, not a lot of margin left (limitations on main refrigerators – see slide 12) Apply modifications in operation scenario for equal split of return flow (3 valves to be changed – see slide 15) 13

K.Brodzinski_ICEC26_ Operation scenarios 14 Thanks to in-built interplant piping and reduced demand for capacity Run1 was operated with two cryo-plants off. Run2 (2015) required high capacity for BS cooling so all 4.5K cold boxes were in operation but as 1.9 K load was relatively low and 3 cold pumping units were off (higher global availability proven) Run2 (2016) is foreseen to be operated with 4 cold pumping units off – tests underway

K.Brodzinski_ICEC26_ Cryo plants Run2 configuration 1.9 K circuit 4.5 K circuit Magnets supply 1.9 K circuit 4.5 K circuit Magnets supply He storage Compression Refrigerator (economizer) Refrigerator (liquefier) AB Currently 1.9 K return flow is unbalanced affecting operational stability and performance of the refrigerators. To resolve the issue 3 valves design must be more precise to control the flow –> replacement to be studied and approved (long term solution … ~2019) 15

K.Brodzinski_ICEC26_ Main failures 1/2 Major failure – an internal helium leak (order of a mbarl/s) in LHCB 4.5 K refrigerator at P8 declared on 18 June 2015 (TS1). Consequences: vacuum diffusion pump stopped, lowered capacity on P8 cryo plant, frequent cold condition losses because of poor quality of supercritical helium in the supply collector. Repairs done on “helicoflex” sealing on TU filter cap in January Second (smaller, 10^-3 mbarl/s) leak detected on DN400 AL/SS transition repaired with “vac-seal” varnish. Compensatory measures: -Cold compressor connected to plant B (for economizer mode) -Vac. roots pumping unit connected -2 nd spare roots in situ -Process adaptation to minimize the leak Vacuum signal Start up of cold turbines 16

K.Brodzinski_ICEC26_ Main failures 2/2 Main components or rotating machines which required replacement: 3 turbine failures on 4. 5 K refrigerators: P18: TU2 – replaced with LN2 pre-cooler during repair time P18: TU3 – replaced with spare P2: TU2 – replaced with LN2 pre-cooler during repairs 1 warm compressor failure: P4: HP compressor CP6 Systematic vibration measurements (1/month) allow for in advance detection of the problem to avoid serious damage and high repairs cost of affected machine From June 2009 until now: 8 warm compressors had to be repaired (7 of firm “A”, and 1 from firm “B”) 16 turbine accessory valve failures (needed for some turbines to control axial profile of the shaft temperature). Replacement study is launched at CERN (offers already received), prototypes to be installed on the cold boxes in PLC failures – progressive replacement was done by a new product with “anti-crash firmware”. 17

K.Brodzinski_ICEC26_ Availability – global cryogenics 18 Statistics for Run2 (2015) period from 5 th April to 14 th December 2015

K.Brodzinski_ICEC26_ Availability – main cooling machines K cold boxes 1.8 K pumping units 4 x PLC

K.Brodzinski_ICEC26_ Cryo Maintain statistics The most time consuming losses: PLC: 4 failures with 26.9 % Cold compressor: 8 failures 19.4 % Human factor 15.1% (mainly late TS1 recovery) Elec. Instrum. Tunnel 13.3 % 4 above contributors  75% of the down time The most frequent losses (main contributors): DFBMI: 39 He level losses with 2% (linked with P8 QSRB leak) DFBAF: 21 He level losses with 1% solution found (to be improved ex. with YETS) No obvious solution for improvement (to be studied) Legend: 20

K.Brodzinski_ICEC26_ Helium consumption and losses 21

K.Brodzinski_ICEC26_ Conclusions 22 LHC cryogenic system operated successfully for Run1 and Run2 (2015) with global availability between % for 8 independent cryo-plants First Long Shutdown consolidations visibly helped (0 radiation caused failures declared in 2015) Beam energy increase required special tests and preparation (copper continuity test and magnets training) where cryogenic provided requested safe operation Cold box capacity for 1.9 K circuit has relatively large margin and this saving is used to cover heat load from electron cloud on the beam screen circuit Gained operational experience allowed optimization in operation scenarios of the plants, however some of them approached the global capacity limit, continues study on improvements and optimization of the cryogenic process is underway Thank you for your attention! Questions ?

K.Brodzinski_ICEC26_ Back up 1: Electron cloud mechanism 23 G. Rumolo - CERN

K.Brodzinski_ICEC26_ Back up 2: Scaling laws 24 LHC Design Report

K.Brodzinski_ICEC26_ Back up 3: LHC standard cell 25