Emergency Landslide Correction Benefits of a Contract Joey Franzino, P.E. INDOT Geotechnical Operations Engineer September 23, 2015.

Slides:



Advertisements
Similar presentations
St. Anthony Falls Bridge Replacement Jon Chiglo, P.E., Project Manager.
Advertisements

September 28, 2013 Greg Duncan, Assistant Chief Engineer of Operations Anaheim, CA Performance Based Maintenance Contracting in Tennessee (Experience One.
Construction Communications. Communication is an expectation Inform our customers about improvement projects Raise awareness of: Construction zone locations.
Delmar Boulevard bridge replacement over Interstate 170.
Summary of Conceptual Design Site 3 Causeway Landfill Culvert Stabilization Marine Corps Recruit Depot Parris Island (CTO JM38) 19 August 2014.
I-96 Reconstruction/Bridge Repair Project City of Livonia and Redford Township Wayne County May 10, 2013 Association of the Council of Western Wayne Yankee.
Public Works Greg Chock Operations Manager Harlan Hanson Road & Bridge Engineer
COUNTY OF SAN DIEGO DEPARTMENT OF PUBLIC WORKS County of Los Angeles Public works 2015 Sustainable Pavement Round Table February 10, 2015.
Duane Hill, District Engineer
GEOTECHNICAL ENGINEERING Session 07 Subject: S0012 / Introduction to Civil Engineering Year: 2007.
 Narrow roadway, with no shoulders  Poor pavement condition  AADT 405/150 – Low Traffic Volume  Ideal candidate for P.I.P.
August 18, 2011 State Route 99 Auxiliary Lanes Project Route 32 to East 1st Avenue.
75 Express Lanes Segment D Construction From South of Sheridan Street to North of Griffin Road Presentation to Ivanhoe Community August 27, 2014.
Oklahoma’s Experience with Wire Rope Safety Fence.
East Branch Dam Safety Modification Project
Geotechnical Investigation Step 1 - Gather Existing Information Structure Data Bridge, building, road, wall, etc. Type - stories, loads, materials, etc.
S.R. 256 Road Reconstruction Project From City of Austin to S.R. 203 Thursday, February 6, 2014 Austin Elementary School 6:00 p.m.
Lyme Regis No longer Slip-sliding Away September 1, 2006.
Transportation Study for City of Bluffdale Porter Rockwell Boulevard is a planned, designed and partially built major arterial road that connects Mountain.
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
I-65 Added Travel Lanes Project in Tippecanoe County
 Embankment Construction – LOTs  What is the maximum length of a LOT? Mainline pavement lanes, turn lanes, ramps, parking lots, concrete box.
Crane Bridge Design STJ Engineering Matt Albert AJ Chandler Noah Fehrenbacher Jake Gennicks Jake Wilhoit Rose-Hulman Institute of Technology.
LPA – Utility Coordination Natalie Parks StructurePoint November 20, 2013.
Route 109 Bridge Reconstruction at Wood Road The Missouri Department of Transportation.
Florida Department of Transportation District 4 TSM&O Program Advanced Transportation Management System (ATMS) Installation in South Broward County ATMS.
Clinton Street Bridge over the Maumee River ODOT Project DEF May 14, 2015 Public Meeting.
Indiana’s Major Moves Projects Asphalt Pavement Association of Indiana Michael B. Cline, P.E., PTOE Commissioner INDOT December 13, 2012.
GDOT Maintenance Overview Eric C. Pitts, P.E. State Maintenance Engineer June 28, 2013.
Managing Council’s Road Network for Better Outcomes Storm Damage Experience Ian de Bruyne Manager Program Planning & Delivery IPWEA Regional Forum 15 May.
Presenter: Dewayne Johnson, P.E. SE Region Director/Bureau of Traffic Operations Director.
Purpose of Work Shop Share Ohio’s experience with a full closure reconstruction: the rationale, challenges, implementation and benefit.
Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center.
Project Update: Airport Freeway, I-820 and I-35W Townhall Meeting for State Representatives Stephanie Klick and Jonathan Stickland Monday, May 12.
3 Easy Steps STEP 1: SITE SELECTION Select Area with Unsuitable Rock Types.
FD05 STATEWIDE RESURFACING PROGRAM OVERVIEW DIANA RADCLIFFE, TEBM, ROADWAY PRESERVATION, DIV OF MAINTENANCE.
2003 Warranty Presentations Caltrans WARRANTED HMA PAVEMENTS PAVEMENTS.
I-495 NORTHERN SECTION SHOULDER USE PROJECT State Project No , P101, C501 CITIZEN’S INFORMATION MEETING UPC NOVEMBER 19, 2013.
VT 100 over the Mad River Bridge Replacement July 13, 2015.
General Tab Project, Cost Schedule, and Work Limits Roadway Character
Asphalt Pavement Association of Indiana Annual Winter Conference Michael B. Cline Commissioner, INDOT December 14, 2010.
Delmar Boulevard bridge replacement over Interstate 170.
Grand Valley Metropolitan Council March 3, 2016 Erick Kind Region Engineer MDOT-Grand Region.
The Highway Fund – Planning, Measuring, and Reporting Mike Holder, PE, Chief Engineer 2015 CAPA / DOT Workshop February 24, 2015.
IMUTCD–Recent Revision, Panel Sign Standards & OHSSI Lalit Garg, P.E. Traffic Administration, INDOT March 9, 2016.
 HDR, Ott Constructability, Dan Brown  Visit and boat tour of Rouchleau pit ◦ Access better than potrayed ◦ Challenging geotechnically 
I-75 Ramp Widening Project Scope of Project – Safety Project to Widen I-75 NB Exit Ramp (Ramp A) and I-75 SB Exit Ramp (Ramp C) at the I-75/US 25W Interchange.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
August 6, 2013 LAKE FORREST DRIVE UPDATE. sandyspringsga.gov Lake Forrest Drive Update  Actions To-Date Work Orders – 13 since 2009 for clean-up, 8 of.
Part 10-1b Micropiles and self-drilling rods in soil and rock engineering V-2009 (rev. XI-2012) (Part 10-1b, PP 2007, animation+p/r : compr.)
SA Economic Indicators Report updated:April 2016 Next update:May 2016.
District 7 (Los Angeles and Ventura Counties) State Highway System San Gabriel Mountains National Monument Area SAN GABRIEL MOUNTAINS NATIONAL MONUMENT.
Public Information Meeting St. George Road - Oak Hill Road Intersection Reconstruction Project.
GEOTECHNICAL ENGINEERING Session 07
Geotechnical Investigation
Big French Creek Slide Timeline of Events
Geohazard inventory Training • April 19, 2017
City of San Jacinto 7th Street Pavement Repairs
Thank you for bringing us to where we are
Dave Kuhn Assistant Commissioner
General Tab Project, Cost Schedule, and Work Limits Roadway Character
US26: Cornelius Pass Rd -185th Ave
Emphasis on Quality Rochester’s City Owner Contract Process
Guardrail Leaveouts 606 special provision July 6, 2016.
State Highway System San Gabriel Mountains National Monument Area
Highway 169 Bridge Replacement & Pavement Resurfacing
PROJ. 566(17) LOR PID MAJOR WIDENING
Contract 60X10 Informational Meeting Weber I-55
S.R. 261 Intersection Improvement at Fruitwood Lane in Newburgh
ACEC Designer Training
Presentation transcript:

Emergency Landslide Correction Benefits of a Contract Joey Franzino, P.E. INDOT Geotechnical Operations Engineer September 23, 2015

Indiana Road Map

Geotechnical Challenges with Landslides Lengthy investigation generally required o Borings including Rock Cores o Lab Testing o Slope Indicators with up to one year of monitoring o Lots of analyses Constant Maintenance o Asphalt and riprap often get dumped to fill cracks and offsets in pavement o Guardrail gets displaced o Eventually, the road can no longer be maintained and must be closed

Geotechnical Challenges with Landslides Road closures o Some roads closed for years until repair o Detours are often lengthy, could cost motorists over 20 miles of time and fuel Repair Costs o Costs vary from $1,000 to $10,000 per linear foot o Frequent change orders due to unexpected conditions

US 52 Slope Failure

If we had no contract…  US 52 was closed on April 2, 2014  Our next step would be to get borings with rock cores. o I would have to treat it as an emergency and drop everything else to drill it, causing other projects to be delayed o The drilling would likely be complete in two to three weeks  I would then need some lab testing o I would likely limit the lab testing in the interest of time since we have a closed road o At best, this lab testing would take two more weeks

If we had no contract…  Based on my site observations, and what I saw encountered during the soil nail wall construction, I believe our best option without a contract would be a reinforced slope o I would then need to do analysis at multiple locations o I would have to write a report o The total time for this would be one to two weeks

If we had no contract…  I would then turn my Geotechnical Report into INDOT Design o They would need to draw up plans o I would have to review the plans o They have to set them up for a letting o The project would be let o The total time for this process would be three to four months

If we had no contract…  The project would then go to Construction o A pre-construction meeting would be held and the contractor would wait for Notice to Proceed o The Construction would be tedious with the reinforcement and aggregate compaction o From the letting date to the road being opened might take four to six weeks

Correction MethodCostDate Road OpensRoad Closed Days Major Differences

SR 75 Slope Failure in Jamestown

Costs Soil Nail Wall$88,020 Toe Stabilization$59,800 Totals$147,820

If we had no contract…  SR 75 was completely closed to all traffic on June 3,  I anticipate that our best option would have been a Gabion Wall. o The Geotechnical Engineering Process would have been similar to what we would have had to do without a contract on US 52. o The Design Process would have been similar. o The Construction Contract process would have been the same, however, the Construction would have taken less time.

Correction MethodCostDate Road OpensRoad Closed Days Major Differences

SR 111 in Floyd County

Costs Soil Nail Wall$250,740 Toe Stabilization$100,000 Totals$350,740

If we had no contract…  On July 13, 2015, traffic was moved to the southbound lane and southbound shoulder (the northbound lane is closed).  I anticipate that our best option would have been Ground Improvement. o The Geotechnical Engineering Process would have been more intense than what we would have had to do without a contract on US 52 and SR 75. o The Design Process would have taken longer. o The Construction Contract process would have been the same, however, the Construction itself would have been much longer.

Correction MethodCostDate all lanes openRoad Closed Days Major Differences

 Athar Khan  Jonathan Paauwe  Jean Hiadari  Jane Twaddle Special Thanks Today

Questions?