EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

CERN IT Department CH-1211 Genève 23 Switzerland t Mobile services: Sunrise SWAP Rodrigo Sierra IT/CS.
Long shutdown 2013: Electrical distribution activities 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group.
LIU CABLING & OPTICAL FIBRES STRATEGY Georgi Minchev Georgiev EN-EL-CF.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Barriere O, Le Roux P
112/09/2013. Summary  Events on the network  Incidents  Network reconfigurations  Network operation  Update on activities  Tests  Projects and.
Injector De-cabling Project Project Team Meeting #
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
Introduction S. Baird 12 th September Accelerator Consolidation Workshop  Why are we here?  Boundary conditions  What is (not) included?  Outcome.
Status of handling studies for PSB-LIU Caterina Bertone EN-HE LIU-PSB 17/09/2015 Courtesy: A. Newborough EDMS
Injector De-cabling Project Enlarged meeting # S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Injector De-cabling Project Enlarged meeting # E. HARROUCH, EN-MEF, on behalf of the Injector De-cabling Project Team.
Booster LV Electrical Distribution: Schedule and Quantities Aims: Modernisation of Booster electrical infrastucture To install necessary infrastructure.
15 January 2008 S.Infante TS-EL CONTROLS ACTIVITES.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Injector De-cabling Project Enlarged project meeting # S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
J. Pedersen, ST/EL Consolidation of the CERN technical infrastructure and civil engineering. J. Pedersen ST 6 th ST workshop, Thoiry, 1 – 3 April 2003.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Static Var Compensator Status (SVCs for Booster and SPS) Situation in 2009 Karsten KAHLE, TE-EPC ATOP days March 2009.
ATC/ABOC Days, 22 January 2007 The safety electrical networks at CERN Anne Funken, TS-EL.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
ABOC/ATC days Electrical Network: Selectivity and Protection Plan José Carlos GASCON TS–EL Group 22 January 2007.
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
Injector De-cabling Project Project meeting # 7, S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
Essential Consolidation Items for LIU-PSB Collection from LIU-PSB WP holders.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
Activities related to BE-BI during LHC-YETS 7 th December, 2015 Maria Barberan, Marzia Bernardini.
LIU EL-FC ACTIVITIES Georgi Minchev Georgiev EN-EL-FC EDMS
Proposal for rerouting of buried electrical networks and optical fibres at Point 1 LS2 Committee meeting S. Bertolasi on behalf on EN/EL WP17.2 HL-LHC.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
Electrical Group Inputs for LIU-Ions J. Devine, on behalf of EN/EL.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
YETS & LS2 Works EN-EL / Power distribution
Situation of the Static Var Compensators at CERN.
Update on the Critical Path of the PS Booster Schedule for the EYETS
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
TE-MSC activities in SPS during LS2
Injector De-cabling Project
AD consolidation activities in LS2
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
the high-voltage network of CERN ToMORROW
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
the CERN Electrical network protection system
SPS activities during LS2 TE-EPC (Power Converter Group)
YETS & LS2 Works EN-EL / Power distribution
TE-MSC activities in SPS during YETS
GIS Portal Racks Project
Business opportunities related to CERN electrical network
Experimental Areas – LS2 planning
ILO Industrial Opportunities Days, 6-7 June 2019
Presentation transcript:

EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL

1.Introduction 2.LIU & Consolidation a.Major projects b.Other projects/works c.Activities not yet confirmed 3.Maintenance 4.Operation 5.Planning & Conclusion Agenda N. Bellegarde / EN-EL2

1.Introduction 2.LIU & Consolidation a.Major projects b.Other projects/works c.Activities not yet confirmed 3.Maintenance 4.Operation 5.Planning & Conclusion Agenda N. Bellegarde / EN-EL3

Overview of the electrical network N. Bellegarde / EN-EL LS2 LS1 run2 4

Methodology It is envisaged to work in campaigns as far as practicable  To be implemented for maintenance activities (as it was done during LS1)  To be implemented for projects/works  Already implemented for cabling and optical fibre activities  This is critical to ensure that a maximum number of activities will be carried out. N. Bellegarde / EN-EL5

1.Introduction 2.LIU & Consolidation a.Major projects b.Other projects/works c.Activities not yet confirmed 3.Maintenance 4.Operation 5.Planning & Conclusion Agenda N. Bellegarde / EN-EL6

LIU & Consolidation Major projects – Run2  New diesel generators in Meyrin (ME91)  New 400 kV substation (BE2) N. Bellegarde / EN-EL Study phase ongoing Contribution GS & EN-CV 7

LIU & Consolidation Major projects – Run2 / LS2  Renovation of the 400 kV protection system (not funded yet)  Consolidation and upgrade (LIU) of the SPS electrical infrastructure (overall budget to be confirmed at the end of the study phase)  7 BAs to be done in total (incl. new BAF3 for RF)  User’s requirements being collected N. Bellegarde / EN-EL Study phase ongoing Possible contribution GS & EN-CV for new buildings 8

LIU & Consolidation Major projects – LS2  Renovation of the main Meyrin substation (ME9) Note: 18 kV cables to be hauled before LS2  Consolidation of the 400 kV park in Prévessin (new incoming circuit breaker, firewalls, transformer non-conformities, etc.)  Consolidation and upgrade (LIU) of the LV distribution in the PS complex (resourcing needs being studied with overall budget to be confirmed)  Consolidation and upgrade (LIU) of the LV distribution in the PSB (incl. cable dismantling program) (resourcing needs being studied with overall budget to be confirmed) N. Bellegarde / EN-EL Contribution GS & EN-CV 9

LIU & Consolidation Injector de-cabling project – Run2 / LS2 / …  To identify and remove obsolete cables within the injector complex, until end of LS2  First priority: Identification of obsolete cables in the Booster and SPS BA5  Partial / total removal must be decided by end September 15’  Triggered by LIU needs (room in cable containment)  Second priority: SPS BA3  Third priority: Identification of obsolete cables in the PS, TT2, LINACs N. Bellegarde / EN-EL RUN 2015YETS RUN 2016EYETS RUN 2017YETS RUN 2018LS2 BOOSTER Cable identificationIDENTIFICATION Cable labelling LABELLING Cable disconnection DISCONNECTION Cable removal REMOVAL SPS Cable identificationIDENTIFICATION Cable labelling LABELLING Cable disconnection DISCONNECTION Cable removal BA5 LEFT REMOVAL BA5 RIGHT & BA3 REMOVAL PS, TT2 & Linacs TO BE DEFINED 10

LIU & Consolidation Injector de-cabling project – Status per machine  Booster:  3000 obsolete cables to be removed (consolidation budget) before LS2  2800 used cables to be removed and replaced during LS2 for LIU (LIU budget)  2 big cable campaigns for EN-EL (EYETS16-17, YETS17-18 and LS2)  Strong commitment from all the equipment groups during identification and disconnection stages  Resources to be secured for YETS15-16 N. Bellegarde / EN-EL Machine/areaTotal number of signal and control cables Identified obsolete cables on Sept. 21 st Booster12’0003’000 (25%) SPS – BA5~ 6’5003’250 (50%) SPS – BA3~ 8’0000 PS – CENTRE RING~ 7’ (14%) TT2~ 3’00072 (2.5%) 11

1.Introduction 2.LIU & Consolidation a.Major projects b.Other projects/works c.Activities not yet confirmed 3.Maintenance 4.Operation 5.Planning & Conclusion Agenda N. Bellegarde / EN-EL12

LIU & Consolidation Other projects/works  Modification of the existing 18 kV Autotransfer and new 66 kV Autotransfer (not funded yet)  Consolidation of UPS systems (Chloride and Schneider) (not funded yet)  Consolidation of 48 V DC systems (SPS, LHC substations on surface, Meyrin, new EN-EL projects)  Renovation of the machine network in Meyrin (West Area – ME65/66/74) (partially funded)  Local control infrastructure consolidation (more than 150 remote I/O stations and cross-wiring junctions from LEP to be replaced) N. Bellegarde / EN-EL13

LIU & Consolidation Other projects/works  TE/EPC  New SVC in Meyrin (ME59)  Replacement of the SPS SVC in Prévessin (BE)  LIU-PSB  Renovation substation ME25 + new building 245  Other users’ projects  Experiments  SM18, SF18  East Area  EHN1  Etc.  See users’ presentations for details. N. Bellegarde / EN-EL14

LIU & Consolidation Signal cabling projects  Replacement of irradiated cables (4-5 months during LS2)  TDC2-TCC2 (1st priority: already postponed for LS1)  TS4- or TS6+ (in 2nd priority to evaluate)  Decision to be taken according to the RIACWG recommendations (EDMS )  Services needed: RP, Transport, Coordination, Users  Repair of aged cables connected to the RAL patch panel (3- 4 months during LS2)  SPS P4, P5, P6 and North Area  Services needed: RP, Coordination, Users  Plus more than 30 other large projects generated by users (LIU, PSS, etc...) needing signal cables  see users’ presentations N. Bellegarde / EN-EL15

LIU & Consolidation DC cabling projects  Replacement of DC WCC hoses in LHC-1, LHC-2 and LHC-5 (12-14 months during LS2)  Approx. 200 cables concerned for a total length of 2300 metres of hose to be replaced  Services needed: EN-HE, EN-MEF, EN-CV, TE- EPC, DGS-RP  Removal of unused DC WCC cables in SPS-5L and SPS-5R (4 weeks during YETS )  Required for the integration of the new dump in point SPS-5. Dismantling and disposal of irradiated cables. Retrieval of several lengths as spare cable for future projects or repair.  Services needed: EN-HE, EN-MEF, EN-CV, DGS-RP  Plus more than 10 projects generated by users (LIU, LHC, Test benches, Labs….) needing DC cables  see users’ presentations N. Bellegarde / EN-EL16

LIU & Consolidation Optical fibre projects  Consolidation of fibre backbones and main distribution points (2-3 months during LS2)  Increase the fibre capacity in Meyrin, Prévessin and LHC sites  Services needed: EN-MEF  Deployment of underground SPS fibre infrastructure (part of BI-BPM Upgrade) (6 months during LS2)  Installation of fibre infrastructure in remaining half part of SPS machine  Services needed: EN-HE, EN-MEF, TE-EPC, BE-RF  Fibrothèque database (12 months during LS2)  Survey on the fibre infrastructure on all machine areas for registration  Services needed: EN-MEF N. Bellegarde / EN-EL Plus more than 20 other large projects generated by users (LIU, PSS, etc...) needing signal cables  see users’ presentations 17

1.Introduction 2.LIU & Consolidation a.Major projects b.Other projects/works c.Activities not yet confirmed 3.Maintenance 4.Operation 5.Planning & Conclusion Agenda N. Bellegarde / EN-EL18

LIU & Consolidation Activities not yet confirmed  LHC:  Replacement of diesel generator in LHC4  Replacement of FIR protection relays  Meyrin:  Renovation of ME49/16/76 (PS and Administrative Areas)  Prévessin:  Renovation of substations HM1 & HM2 (Administrative Area)  Renovation of the 3.3 kV network in the North Area and replacement of diesel generator BB81 N. Bellegarde / EN-EL Budget / Resources 19

1.Introduction 2.LIU & Consolidation a.Major projects b.Other projects/works c.Activities not yet confirmed 3.Maintenance 4.Operation 5.Planning & Conclusion Agenda N. Bellegarde / EN-EL20

Maintenance 400 kV and 66 kV preventive maintenance  1 st step: 400 kV preventive maintenance (incl. transformers)  2 nd step: 66 kV preventive maintenance (incl. transformers)  With the new 400 kV substation (BE2), it will be possible to separate the 400 kV and 66 kV preventive maintenance for the first time  The power available at CERN will not be limited during the 400 kV and 66 kV preventive maintenance (instead of a previous limitation to 60 MVA through the Swiss network) Duration of the above maintenance activities: 400 kV preventive maintenance: in parallel with other consolidation activities 66 kV preventive maintenance: approx. 1 month N. Bellegarde / EN-EL To be organized in campaigns 21

Maintenance Other preventive and curative maintenance  400/18 kV transformers  18/3.3 kV, 18/0.4 kV and 3.3/0.4 kV transformers  18 kV and 3.3 kV switchgear  400 V switchboards  48 V DC, UPS and lighting systems  AUG (consolidation) Duration of the above maintenance activities: Meyrin / West Area / PS Complex – Several weeks North Area – 1 week per point (BA80/ BA81/ BA82) SPS – 1 week per point (SPS1/2/3/4/5/6/7) LHC – 1 week per point (LHC1/18/2/3/4/5/6/7/8) N. Bellegarde / EN-EL To be organized in campaigns 22

1.Introduction 2.LIU & Consolidation a.Major projects b.Other projects/works c.Activities not yet confirmed 3.Maintenance 4.Operation 5.Planning & Conclusion Agenda N. Bellegarde / EN-EL23

Operation AUG tests:  Meyrin / West Area – 4 days per year (Admin. Area, PS Complex, ISR, West Area)  Prévessin / North Area – 4 days per year (Prévessin, BA80, BA81, BA82)  SPS – 7 days per year  LHC – 9 days per year Auto transfer test:  1 day for network preparation  1 week-end test  1 day for nominal configuration “Normal/Secours” test:  Approx. 2 hours required in total (the test itself requires approx. 10 min early one morning) N. Bellegarde / EN-EL24

1.Introduction 2.LIU & Consolidation a.Major projects b.Other projects/works c.Activities not yet confirmed 3.Maintenance 4.Operation 5.Planning & Conclusion Agenda N. Bellegarde / EN-EL25

N. Bellegarde / EN-EL PROJECTWHENFINANCED BE2RUN2YES ME91RUN2YES New cables for Meyrin machine network ME59RUN2YES Substations ME65/66/74 (West Zone Meyrin)RUN2PARTIALLY SPS renovation substations HT/BT and auxiliariesRUN2/LS2PARTIALLY Substation ME24/25 (LIU/BOOSTER)RUN2/LS2YES (LIU) Consolidation AUGRUN2/LS2YES Consolidation 48 VdcRUN2/LS2 + …YES Consolidation 400kV park BE (firewalls, HTB transformers…) LS2YES Substations ME16/49/76 (PS Complex)LS2BUDGET REQUESTED Autotransfer: new for 66 kV + consolidation 18 kVLS2NO ME9LS2YES 400kV protection systemLS2BUDGET REQUESTED Planning & Conclusion 26

N. Bellegarde / EN-EL PROJECTWHENFINANCED Replacement UPS Chloride and SchneiderLS2NO Consolidation low voltage network PS complexLS2PARTIALLY Diesel generator LHC4LS2NO Local control infrastructure consolidationLS2BUDGET REQUESTED Consolidation and upgrade (LIU) of the LV distribution in the PS-TT2 LS2PARTIALLY Replacement protection relays LHCLS2 + …BUDGET REQUESTED 3.3 kV network Zone NorthLS2 + …NO Substations HM1/HM2 (Prevessin Admin area)LS2 + …NO Planning & Conclusion Note: Cabling and optical fibre activities not listed 27

Planning & Conclusion N. Bellegarde / EN-EL28

Planning & Conclusion Some activities shall absolutely be completed during Run2 in order to carry out the activities scheduled during LS2 Other activities shall be anticipated as much as possible during Run2 but will be completed during LS2 Necessity to work in campaigns to complete as many activities as possible (projects/works/maintenance) – User’s requests therefore need to arrive timely Work site supervision is likely to be significantly increased during LS2 – Refer to LS1 Debriefing Day Additional installation contracts may have to be put in place before LS2 – Refer to LS1 Debriefing Day N. Bellegarde / EN-EL29