Malcolm Ellis – Brunel University – 8th April 2008 1 The International Muon Ionization Cooling Experiment.

Slides:



Advertisements
Similar presentations
Norman McCubbin1 Report from the Collaboration MICE Project Board (CMPB) Norman McCubbin Director, Particle Physics Department MICE Funding Agencies Committee.
Advertisements

1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Detector Systems Update MICO March 17, MICE Detector Systems  CKOV u Mississippi RAL  TOF0/1 u Hamamatsu PMT assemblies show an increasing.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 MICE phase I - Project Status Richard Apsimon (Project Manager) & Andy Nichols (Technical Coordinator) … with considerable help from Ken Long! MICE Video.
Linda R. Coney – 24th April 2009 Online Reconstruction & a little about Online Monitoring Linda R. Coney 18 August, 2009.
MICE: The International Muon Ionization Cooling Experiment Diagnostic Systems Tracker Cherenkov Detector Time of Flight Counters Calorimeter Terry Hart.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
CMPB Alain Blondel 14 April STATUS OF MICE.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
ICHEP 2012 Melbourne, 7 July 2012 Paul Soler on behalf of the MICE Collaboration The MICE Beam Line Instrumentation (Trackers and PID) for precise Emittance.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
1M. Ellis - MICE VC - 1st November 2007 Cosmic Ray Test Preparations  The cosmic ray test was initially planned to be held in R12, but this proved to.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE CM35 Status and Goals Alain Blondel 1 WELCOME TO MICE CM35! – Status and Goals - Many thanks to Chris Rogers, Debbie Loader and Rose Hayes for taking.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
MICE CMPB Alain Blondel 1 Highlights on MICE.
MICE FAC open session Alain Blondel 1   MICE The International Muon Ionization Cooling Experiment.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
Database David Forrest. What database? DBMS: PostgreSQL. Run on dedicated Database server at RAL Need to store information on conditions of detector as.
MICE CM39 St Catherine’s, Oxford, 26 June 2014 Paul Soler Instrumentation Global Commissioning Plan.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
ch/~bdl/lepc/lepc.ppt 1 MICE Status and Plans Rikard Sandström Université de Geneve International Scoping Study CERN,
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Monte Carlo simulation of the particle identification (PID) system of the Muon Ionization Cooling Experiment (MICE) Mice is mainly an accelerator physics.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Muon Ionisation Cooling Experiment Overview
MICE Operations Scenario Run 1
UK Financial Plan & Risks
MICE CM31 Schedule summary
Presentation transcript:

Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment

Aim: to demonstrate the principle of ionization cooling as well as the ability to safely operate a cooling channel. 2

Ionization Cooling - Theory 3

Ionization Cooling - MICE 4 Measure muons going into the cooling channel Measure muons coming out of the cooling channel Liquid Hydrogen RF Cavities

MICE Final Layout 5

Challenges Cooling channel is predicted to produce ~ 10% cooling. We would like to measure this to ~ 1%. Require an emittance measurement resolution of 0.1% Timing wrt RF phase from TOF. Operate RF cavities in magnetic fields. Hydrogen safety (LH 2 in proximity to RF cavities!) 6

7 7

Organisation Spokesmouse – A. Blondel (Geneva) Deputy Spokesmouse – M. Zisman (LBNL) Executive Board Technical Board Collaboration Board Editorial Board Speakers’ Bureau WBS structure: 8

Project Management Project Management Team: –Project Manager: R. Apsimon –Technical Coordinator: A. Nichols –Hall Manager: W. Spensley –Hall Foreman: A. Jamdagni, P. Flower –ISIS Liason: C. Rogers –MICE Operations Manager (rotating position) Project on good footing, however: –R. Apsimon & P. Flower have been granted retirement. 9

Technical Coordination Big-ticket items committed: –South shield wall support structure –Air conditioning units –Concrete floor removal Design work almost complete: –False floor –North wall shield support structure –DSA roofing and walkways Remaining design work: –MICE hall roof layout –Installation drawings for CDM records 10

Magnetic Shielding Design complete for complex south wall. North wall design underway. Final quote for magnetic steel plates. Big impact on other work and operation of experiment. Mezzanine closely coupled to walls. Part of H 2 system. Needs to be built with walls. 11 Maximised the net benefit to the experiment. Can run Step I and complete the construction.

MICE Beam Line 12

13 MICE Beam Line

Beam Line Status Permission obtained to use target in ISIS for three runs over the past week. Mechanical installation of decay solenoid complete – not tested yet, problems with the refrigerator All quadrupoles and dipoles installed. Some power supply and water problems to be fixed on a few quadrupoles. 14

Decay Solenoid Transfer line is connected and has checked out OK. The electrical connections to the solenoid are done and most of the pipe work is done. The remaining pipe work does not require access to the DSA and will be complete in the coming weeks. Plan to start a cold test on 14 th April and arrangements are being made for the relevant experts from Linde and PSI to be present to support this test. 15

Second Target Before we can bring the target that is in ISIS into routine operation, a second target operating elsewhere at RAL is required. Second target is due to be complete on 15 th May. Poor QA in the previous manufacturing process has been identified and corrected. ISIS are becoming more comfortable with the target operation and so far have consistently increased our budget of “dips” as we approach the previous limit. 16

MICE Control Room Almost complete. DAQ racks filling up, cabling has begun. Slow controls, DAQ and target PCs installed and used for data taking. PPS racks complete and installed. Network in place, further work still required. 17

First MICE Beam! On the evening of 29 th /30 th March the MICE target, D1 and D2 were used to produce a beam and deliver it into the MICE hall. A number of different detectors were used to measure the particle production. With D1 set at 400 A and D2 set at 170 A, the predicted maximum rate of protons was observed in the GVA2 counter in the Decay Solenoid Area! 18

MICE Detectors 19

TOF System PMT assemblies show an increasing rate of failure under heavy testing. 8 tubes returned to Hamamatsu. Expected delivery at RAL in early May. 20 Italy

KL, SW Calorimeters Tests and calibrations of the KL are ongoing. Trigger counters with magnetic shielding have been built. Test and calibration runs of the KL have begun. Construction & testing of SW prototype successful. 21 Italy

CKOV Both CKOV detectors have been installed at RAL. First pion signals were observed in the past week. 22 USA

Tracker Tracker 1 is now complete. Tracker 2: –All stations complete and QAed. –Waveguides in production. –All components for space frame available. Location pieces for installation in solenoid all manufactured. Spare stations: –Bodies being machined. 23 US, UK, Japan

Software G4MICE (MICE Simulation, Reconstruction and Analysis software) continues to be developed and is now also used for MANX studies. MICE now has a Virtual Organisation on the GRID. Tracker Station QA data analysis was performed on the GRID. Monte Carlo studies are ongoing. 24

TrackerQA Analysis Data from 12 Stations (6-17) analysed. Total of 12,389,135 events processed. 167 of 173 files transferred (6 failures are being investigated). Total of GB data was transferred, unzipped and reconstructed. Total time from starting first job to end of last job: 4 hours and 6 minutes! 25

Funding Agencies Committee 26 MICE spokesperson and project manager. ISIS Director Representatives of each funding agency. Terms of reference: –Receive reports from MICE Project Board and monitor progress of international MICE project. –Receive and review reports from each funding nation on contributions to the overall project. –Consider cost and schedule issues for the project. –Monitor risk and approve contingency. –Review and endorse management structure. –Prepare the funding and financial aspects of the international project for phase 2. –Agree the annual budgets, future profile and schedule. Next meeting: 11 th April

UK Funding Situation STFC funding short fall of £80M announced at the end of Given permission to negotiate the coil contract. The target date for letting contract is 11 th April. This is a bit optimistic, but should still be possible in April. Consequence is step IV is late compared with the previous schedule. UKNF has been asked to present a 3 year plan with budget guidance. This is very good news – we can make a plan not just stumble through another financial year. 27

ISIS User Runs To date we have been operating the target during machine development periods. We have demonstrated the ability to run parasitically (the normal mode of operation for MICE). Once ISIS/RPA are convinced of the radiation and operational safety, MICE will be able to operate during ISIS user runs. It may be necessary for ISIS to cancel one user run. With warning it may be possible for us to mitigate the effect on the schedule. 28

Conclusions - Status Step I of MICE has started! Both dipoles have been powered and particles observed by beam line instrumentation and the CKOV detectors. Need to successfully operate the second target, install TOF0 and TOF1 and KL and to complete the false floor and iron shield in order to complete stage 1. 29

Conclusions – Planning Step two should occur in the September-October run after the spectrometer magnet arrives (August). Step three should occur late 2008 or early Focus pair order has been agreed, with first delivery expected in October Coupling coils and RF cavities are consistent with this. 30