New Jersey Turnpike Authority November 19, 2009 New Jersey Turnpike Interchange 6 to 9 Widening Program Presented by Lisa M. Kenney, P.E. 1.

Similar presentations


Presentation on theme: "New Jersey Turnpike Authority November 19, 2009 New Jersey Turnpike Interchange 6 to 9 Widening Program Presented by Lisa M. Kenney, P.E. 1."— Presentation transcript:

1 New Jersey Turnpike Authority November 19, 2009 New Jersey Turnpike Interchange 6 to 9 Widening Program Presented by Lisa M. Kenney, P.E. 1

2 Interchange 6 to 9 Widening Program Program Overview 2 Interchange 6 Interchange 9

3 Typical Section 3

4 4 Section 7 Section 8 Section 6 Section 5 Section 4 Section 3 Section 2 Section 1 Interchange 6 to 9 35 Miles of the Turnpike 26 Construction Contracts Up to 6 Specialty Contracts Coordinated CM Approach Interchange 6 to 9 35 Miles of the Turnpike 26 Construction Contracts Up to 6 Specialty Contracts Coordinated CM Approach

5 Construction Contracts ● Classifications: 1. Grading and Drainage 2. Paving 3. General Construction, Highway 4. Bridge Structures 5. Heavy Highway ● Ratings: F. up to $5 Million G. up to $10 Million H. Unlimited 5 Range: $5 Million to $210 Million Schedule: Mid 2009 to Mid 2014

6 Proposed Contract Award Schedule

7 New Jersey Turnpike Authority November 19, 2009 New Jersey Turnpike Interchange 6 to 9 Widening Program Presented by Lisa M. Kenney, P.E. 7


Download ppt "New Jersey Turnpike Authority November 19, 2009 New Jersey Turnpike Interchange 6 to 9 Widening Program Presented by Lisa M. Kenney, P.E. 1."