1 T-76.115 Project Review RoadRunners [IM1] Iteration 02.12.2003

2 T-76.115 Project Review 2 Agenda  Project status (15 min)  Planned goals  Planned deliveries  Project metrics  Risks  Used work practices (5 min)  Completed work (20 min)  Test report  User interface design  Architecture design  Plans for the next iteration (5 min)

3 T-76.115 Project Review 3 Status of project  Project is in time  All planned tasks are started  No major changes in project group or in requirements

4 T-76.115 Project Review 4 Status of planned goals of the iteration  Goals in priority order:  Goal 1: Designing core architecture  Goal 2: Implementing core architecture  Goal 3: Testing core architecture  Goal 4: Implementing user interface  Goal 5: Testing user interface  Goal 6: Writing system test plan document

5 T-76.115 Project Review 5 Status of planned deliverables of the iteration  Deliverables  Updated project plan  Updated requirements document  Architecture design  User interface specifications  Test case specifications  Test report  Test plan  Progress report (slideshow)

6 T-76.115 Project Review 6 Realization of the tasks  Meetings -18,5  Only 4 project group meeting  Everyone didn’t participate the customer meetings  Personal SE practise +10  Exercise was more extensive than expected.  Use case User Interface +13,5  Design and implementation are reported both into this task. Part of these hours should be under User Interface design -task  Prepare testing -9, Execute and report tests -9  This task is also for unit testing. Some modules have not been started yet  Inspection -5  Project manager was only one who inspeceted documents  User interface design -6,5  Some of this tasks hours were reported in Use case User Interface  Write/update tech. specs -35  Hours for this task is reported to the Architectural design

7 T-76.115 Project Review 7 Working hours by person  jkatajal couldn’t continue implementation because of other module depencies.  pnoponen was sick long term during phase  rraisane took some of pnoponen’s tasks. Realized hours in this iterationPlan in the beginning of this iteration Latest plan

8 T-76.115 Project Review 8 Software size in Lines of Code (LOC)  All modules are not needed yet and the implementation of these modules is started in next phase.

9 T-76.115 Project Review 9 Risks  The current situation regarding the risks:  Timetable risk has been realized:  One of the project member has been sick during this phase.  Risk effect was not high, since task were divided to the others group members  Identified risks:  Customer requirements are too vague and do not stabilize enough before I1  Distributed development  Java -competence is distributed unevenly  New tools  Timetable  Juha will be away 4 weeks during phase IM3  Juha has to do those hours in next and last phase and the work load will be heavy

10 T-76.115 Project Review 10 Work practices  In this phase following practices are used:  Time reporting  Version control  Personal SE assignments  Test driven development  Communication practices  Meeting practices  Design patterns  Documentation practices  Configuration management  Architectural design  Iteration planning  Documenting and document delivery  Project review  Use cases  Risk management  Coding convention

11 T-76.115 Project Review 11 Results of the iteration  Updated project plan  Next phase tasks and risks  Use cases  Updated requirements document  Use cases updated  Architecture design  User interface specifications  Test report  Unit tests done in this phase  Test plan  What, when, who and how

12 T-76.115 Project Review 12 Test report  All modules have not been implemented yet. They will be implemented and tested in next phase

13 T-76.115 Project Review 13 User interface (1/8)  There have been two customer meetings during I1-phase about user interface  Design aspects:  Tool is easy to use  Windows -like  At the moment UI has menus but no functionality

14 T-76.115 Project Review 14 User interface (2/8)  Main view

15 T-76.115 Project Review 15 User interface (3/8)  File-menu

16 T-76.115 Project Review 16 User interface (4/8)  Edit-menu

17 T-76.115 Project Review 17 User interface (5/8)  View-menu

18 T-76.115 Project Review 18 User interface (6/8)  Insert-menu

19 T-76.115 Project Review 19 User interface (7/8)  Tools-menu

20 T-76.115 Project Review 20 User interface (8/8)  Help-menu

21 T-76.115 Project Review 21 Software Architecture (1 /13)  Logical Architecture

22 T-76.115 Project Review 22 Sofware Architecture (2/13)  Package GUI  MainView  PresentationView

23 T-76.115 Project Review 23 Software Architecture (3/13)  GUI - MainView

24 T-76.115 Project Review 24 Software Architecture (4/13)  GUI – PresentationView

25 T-76.115 Project Review 25 Software Architecture (4/13)  GUI - Menu Structure

26 T-76.115 Project Review 26 Software Architecture (5/13)  Package Controller  CommandFactory

27 T-76.115 Project Review 27 Software Architecture (6/13)  Controller - Layer and Layers Controllers

28 T-76.115 Project Review 28 Software Architecture (7/13)  Package LayerManager  RMTLayerManager

29 T-76.115 Project Review 29 Software Architecture (8/13)  Package GraphicLibrary

30 T-76.115 Project Review 30 Software Architecture (9/13)  Package Help  Written in HTML  External Browser

31 T-76.115 Project Review 31 Software Architecture (10/13)  Package ExternalDocumentHandler  Supplementary implementations:  External documents saving and launching  Copying Roadmap to clipboard  Exporting Roadmap

32 T-76.115 Project Review 32 Software Architecture (11/13)  Package Storage  non-volatile storage for a Roadmap  Stored in XML

33 T-76.115 Project Review 33 Software Architecture (12/13)  Package Engine

34 T-76.115 Project Review 34 Software Architecture (13/13)  Basic sequence diagram - Adding Activity

35 T-76.115 Project Review 35 Plan for the next iteration (1/2)  Goals  mandatory use cases are implemented  User manual draft is written  Peer testing arrangements is done  Deliverables  Updated project plan  Updated requirements document  Updated technical specification  Updated test cases  Test report and test log  User's manual  Progress report

36 T-76.115 Project Review 36 Plan for the next iteration (2/2)  Task schedule and dependencies