1 EURISOL Design Study NUPECC MEETING LNF - DECEMBER 5th, 2003

2 The EURISOL status report The Task Group reports are to be supplied as Appendices to the EURISOL Report, and are now at the Printer. Proofs will be received shortly, and printing should take place during December 03. The Task Group reports are to be supplied as Appendices to the EURISOL Report, and are now at the Printer. Proofs will be received shortly, and printing should take place during December 03. The main document, "The EURISOL Report" itself is almost complete, and will be circulated to the EURISOL Steering Committee members for final comment and corrections, and will then be printed in early January 2004. The main document, "The EURISOL Report" itself is almost complete, and will be circulated to the EURISOL Steering Committee members for final comment and corrections, and will then be printed in early January 2004. 600 copies of the Report plus the 5 separate companion volumes of the Appendices will be mailed out thereafter. A CD version will also be available, together with the report, and also separately. 600 copies of the Report plus the 5 separate companion volumes of the Appendices will be mailed out thereafter. A CD version will also be available, together with the report, and also separately.

3 EURISOL DESIGN STUDY ACTION GENERAL INFORMATION Aim of this specific programme is to remove the Structural weaknesses of European Research This activity promotes the development of a fabric of research infrastructures of highest quality and performance in Europe and their optimum use on a European scale. Aim of this scheme is to contribute, to feasibility studies and technical preparatory work for a potential new infrastructure which have a clear European dimension and interest. SPECIFIC PROGRAMME STRUCTURING THE ERA RESEARCH INFRASTRUCTURES DESIGN STUDY AREA OF INTERVENTION SUPPORT SCHEME INSTRUMENT SSA (SPECIFIC SUPPORT ACTION) This instrument aim to contribute actively among other objectives the preparation of future activities

4 FP6-2003-INFRASTRUCTURES-4 CALL SPECIFIC INFORMATION Total budget for the call: 70 M Requested budget: About 9 M Deadline: 4 March 2004 Pre-notification proposal: before the end of 2003 Acronym: EURISOL DS Consortium agreement: not required Duration of the project: 48 months The Community support will take the form of grant up to a maximum of 50% of the total cost of the Design Study WRITING GROUP: G.Fortuna, P. Butler, Y. Blumenfeld Consultant for Beta-beams: M. Lindroos COORDINATING INSTITUTION: GANIL Technical Coordinator: John Cornell

5 EURISOL DESIGN STUDY: THE SCIENTIFIC GOALS Production of a Detailed Engineering Design (DED), of the facility, in particular in relation to its most technologically advanced aspect (i.e. excluding the detailed design of standard elements of the infrastructure) Carrying out the Technical Preparatory Work (TPW) related to components, subsystems, material or techniques (dedicated software is included) that are critical for the future development of the new facility

6 EVALUATION CRITERIA FOR SPECIFIC SUPPORT ACTIONS The evaluation criteria are organized in four different areas, to each area specific weight and threshold are given. The final threshold of the proposal is : 3.5/5 EUROPEAN ADDED VALUE (weight: 1; threshold: 3/5) the extent of the European significance and interest of the proposed infrastructure, in particular in terms of the needs of the potential users and of the opportunities for multidisciplinary research S&T EXCELLENCE (weight: 1; threshold: 3/5) The extent to which: - the proposed new infrastructure is scientifically and technologically original and innovative ; - the proposed study and work is scientifically and technologically well structured, also in relation to the overall development plans of the new infrastructure.

7 EVALUATION CRITERIA FOR SPECIFIC SUPPORT ACTIONS RELEVANCE TO THE OBJECTIVES OF THE SCHEME (weight: 1; threshold: 3/5) The extent to which: - there is a clear scientific or technological need for the proposed detailed engineering design and technical preparatory work; - the proposed study and work is capable of exploring the funding and, where appropriate, the regional and transregional dimensions of the proposed infrastructure. QUALITY OF THE MANAGEMENT (weight: 1; threshold: 3/5) The extent to which: - the project management and the competence of each partner are appropriate for the intended study and work; - there is a clear description and justification of the corresponding budget, divided by tasks and by participants

8 PROPOSAL STRUCTURE A COMPLETE PROPOSAL HAS TWO PARTS: PART A AND PART B It is a set of forms collecting necessary administrative information (activity code, abstract, organisation legal name, address, legal status, cost model, total funding requested, etc) The co-ordinator fills in forms A1 and A3 Participants fill in the A2 form The scientific and technical content of the proposal will be given in detail. It describes, among other things, the nature of the proposed work, the participants and their roles in the proposed project. It will be prepared by the Writing Group PART A PART B

9 PREPARATION O F THE EURISOL.DS PROPOSAL: IMPORTANT MILESTONES YEAR 2003 MAY 12th MAY 12th THE WRITING GROUP (G. FORTUNA, P. BUTLER, Y. BLUMENFELD) IS APPOINTED BY THE EURISOL STEERING COMMITEE AT THE ORSAY MEETING) THE WRITING GROUP (G. FORTUNA, P. BUTLER, Y. BLUMENFELD) IS APPOINTED BY THE EURISOL STEERING COMMITEE AT THE ORSAY MEETING) END OF JULY END OF JULY THE CALL FOR COLLECTING LETTERS OF INTEREST TO PARTICIPATE IN THE EURISOL. DS IS LAUNCHED. SEPTEMBER 20th SEPTEMBER 20th FOURTY LETTERS OF INTERERST FROM ABOUT 20 DIFFERENT INSTITUTIONS ARE COLLECTED BY THE WRITING GROUP. OCTOBER 2nd,3rd OCTOBER 2nd,3rd AT THE EURISOL STEERING COMMITTEE MEETING HELD AT LNL 11 DIFFERENT TASKS ARE IDENTIFIED AND THE TASKS LEADERS APPOINTED. NOVEMBER 14th NOVEMBER 14th AT ORSAY FIRST OPEN MEETING OF THE TASK LEADERS WITH THE WRITING GROUP. A PROVISIONAL WORK PLANNING OF THE VARIOUS TASKS IS PRESENTED AND DISCUSSED.

10

11

12 TASKSLEADERE-MAILINSTITUTE * NATURE OF WORK Liquid Metal Target/Ion Source 1 + F. Groeschel Friedrich.Groeschel@psi.chPSI PW - PRO - E Direct Target/Ion-Source 1 + J. Lettry Jacques.Lettry@cern.chCERN PW - PRO - E Solid Converter Target/Ion–Source 1 + L. Tecchio Luigi.tecchio@lnl.infn.itINFN PW - PRO – E Safety & Radioprotection D. Ridikas ridikas@cea.fr CEA SACLAY PW Heavy-Ion Accelerator Design M-H. Moscatello moscatello@ganil.frGANIL PW -PRO Proton Accelerator Design A. Facco alberto.facco@lnl.infn.itINFN PW - PRO SC Cavity Development S. Bousson bousson@ipno.in2p3.frIPNO PW –PRO Beam Preparation A. Jokinen ari.s.jokinen@phys.jyu.fiJYFL PW - PRO - E Physics and Instrumentation R. Page rdp@ns.ph.liv.ac.uk U LIVERPOOL PW - PRO Beam Intensity Calculations (Also Protons v Heavy Ions) K.H. Schmidt k.h.schmidt@gsi.deGSI PW – E Beta Beams Aspects M. Benedikt Michael.Benedikt@cern.chCERNPW Global Coherence and Layout TO BE DEFINED *PW=Paperwork PRO=Prototype E =Experiment N.1 2 3 4 5 6 7 8 9 10 11 12

13

14 BRIEF DESCRIPTION OF THE TASKS Direct target & 1 + ion source: the objective of this task is the development of a target and ion source for radionuclide production that can accommodate up to 100 kW power from a beam of protons or heavier ions. The work package should also investigate how to significantly improve the efficiency for the release and ionisation process over that of present target and ion source systems. (J. Lettry) Liquid metal target & 1 + ion source: the objective of this task is the development of a LIQUID METAL CONVERTER target that can accommodate up to 5 MW proton power. The work package should also investigate the efficient production of singly charged ions of neutron rich radionuclides in the secondary fissile target and ion source system. (F. Groeschel) Solid Converter Target and 1 + ion-source this task should continue the work already conducted, within the task Target and Ion Sources of EURISOL- RTD -, studying in depth the feasibility and the reliability of neutron converters based on solid materials in the beam power domain of some hundred KW. In other words, it should move from a conceptual design to a much more engineering oriented study, which should better outline and start to freeze technical choices for such crucial facility component, especially in relation with the RIB production target coupling. (L. Tecchio) 2 1 3

15 BRIEF DESCRIPTION OF THE TASKS Heavy Ion Accelerator Design: this task should continue the work already of the task Post Accelerator and Mass Separator of EURISOL-RTD -, studying in depth dynamics, beam transport and matching of the beam characteristics with the needs of the future experimental campaigns. This task will move from a conceptual design to a much more engineering oriented study, which should better outline and start to freeze technical choices for the subsystems and components of the HI-Accelerator included in the Eurisol machine chain. (M. H. Moscatello) Safety and radioprotection: in the framework of this task calculation of radiation production and activation should be performed. The methods for shielding against prompt radiation and for the containment of activity should be studied. This task also should investigate the handling of targets and in particular the disposal of spent targets. The conformity of the proposed installation to the legislation shall be insured. (D. Ridikas) Proton Accelerator Design: the task Proton Accelerator Design should continue the work already conducted, within the task Proton Driver of Eurisol RTD, deepening the study of dynamics, beam transport and matching of the beam characteristics with the feasibility of the neutron converter and production target in terms of sustainable power. In other words, this task will move from a conceptual design to a much more oriented engineering study, which should better outline and start to freeze the technical choices for subsystems and components of the proton driver. (A. Facco) 4 5 6

16 BRIEF DESCRIPTION OF THE TASKS Beam preparation : this task is concerned with several aspects of beam preparation for injection into the post-accelerator: beam bunching and cooling; species purification (e.g. classical magnetic separation or ion trap); charge breeding, multi-user capability. (A. Jokinen) SC Cavity Development: with this task we intended to attack, as first priority, the technical open problems related to the construction of complete cryomodules. It is worthwhile mentioning that such cryomodules should fit the configuration and the design choices of the driver and post accelerator proposed for the EURISOL facility. (S. Bousson) SC Cavity Development: with this task we intended to attack, as first priority, the technical open problems related to the construction of complete cryomodules. It is worthwhile mentioning that such cryomodules should fit the configuration and the design choices of the driver and post accelerator proposed for the EURISOL facility. (S. Bousson) Physics and instrumentation: this task should build upon the conclusions of the report published within the FP-5 Eurisol contract (see http://www.ganil.fr/eurisol) to select few key scientific goals and identify the required experimental methods using novel detector technologies. (R. Page) 7 8 9

17 BRIEF DESCRIPTION OF THE TASKS Beta beam aspects: the objective of this task is to liaise with the target group to optimize 6He and 18Ne production and the beam preparation group for the development of pulsed ECR source; to liaise with the post-acceleration group; to develop the design of the storage ring/ rapid cycling synchrotron, decay ring and stacking scheme. (M.Benedikt) Beam Intensity Calculations: in the framework of this task a procedure for calculating beam intensities for various accelerator and target configurations in a consistent manner should be devised, in order to compare and choose between different technical solutions. In particular, production yields using primary proton, deuteron and heavy ion beams should be investigated for specific radio-nuclides. The production of nuclei very far from stability by fragmentation of intermediate energy radioactive beams should be explored. The conducting of a limited number of experiments to validate the calculation procedures is encouraged. (K. H. Schmidt) Global Coherence and Layout: to be defined 10 11 12

18 INPUTS FROM ORSAY MEETING Need of better defining the border lines of the various tasks Need of better defining the border lines of the various tasks Need of a strong (sub)coordination of the 3 accelerators (targets) related tasks Need of a strong (sub)coordination of the 3 accelerators (targets) related tasks Strong indication of concentrating the resources on accelerators and targets tasks(6M out of 9M) Strong indication of concentrating the resources on accelerators and targets tasks(6M out of 9M) Need of involving SMEs and non- european( VI FP) partners( Triunf, Vinca…..) Need of involving SMEs and non- european( VI FP) partners( Triunf, Vinca…..) Dec.1st,03: final instructions including tabular forms to the task leaders Dec.1st,03: final instructions including tabular forms to the task leaders

19 MANAGEMENT SUPPORTING GROUP SCIENTIFIC SECRETARY ADMINISTRATION TECHNICAL COORDINATOR PROJECT ADVISORY COMMITTEE 3 Members STEERING COMMITTEE MANAGEMEMENT GROUP + Representatives of the participating institution 1 Meeting/Y Approval of the planning Monitoring of the use of resources COORDINATION BOARD Management Group +Task Leaders 2-3 Meetings/Y Scientific&Technical Planning Task Coordination&Global Coherence Task 1 Task 2 Task n MANAGEMENT GROUP COORDINATOR+2 Members Responsibility for the Execution of the contract ANNUAL PARTICIPANTS MEETING 1 Meeting/Y Information Plan between the Project and the Community ANNUAL PARTICIPANTS MEETING 1 Meeting/Y Information Plan between the Project and the Community

20 Preparation o f the Eurisol.ds Proposal: Important milestones YEAR 2004 JANUARY 8th JANUARY 8th DEADLINE FOR THE PREPARATION OF AN ADVANCED DESCRIPTION OF THE TASKS CONTAINING: WORK PLANNING, MILESTONES, DELIVERABLES AND REQUESTED RESOURCES. DEADLINE FOR THE PREPARATION OF AN ADVANCED DESCRIPTION OF THE TASKS CONTAINING: WORK PLANNING, MILESTONES, DELIVERABLES AND REQUESTED RESOURCES. JANUARY 26th JANUARY 26th PARIS: JOINT MEETING OF THE WRITNG GROUP AND THE EURISOL STEERING COMMITTE TO EXAMINE THE STATUS OF THE PROPOSAL AND ITS GLOBAL COHERENCE. FEBRUARY 16tH FEBRUARY 16tH CERN: OPEN MEETING OF THE WRTITING GROUP AND THE TASK LEADERS FOR THE UPDATE OF THE PROPOSAL DRAFT


Download ppt "EURISOL Design Study NUPECC MEETING LNF - DECEMBER 5th, 2003."