FAIR – Facility for Antiproton and Ion Research

Similar presentations


Presentation on theme: "FAIR – Facility for Antiproton and Ion Research"— Presentation transcript:

1 FAIR – Facility for Antiproton and Ion Research
In 2015, 8 years and 1187 Million € later FAIR – Facility for Antiproton and Ion Research GSI GmbH + FAIR GmbH Observers CN DE ES FI FR GB GR IN IT PL RO RU SE

2 Present Committee Structure of the International Project FAIR
CN DE ES FI FR GB GR IN IT PL RO RU SE 13 potential ‘M e m b e r s t a t e s’ ISC International Steering Committee STI Working Group Scientific + Technical Issues AFI Working Group Administrative + Funding Issues FAIR Project PAC QCD LFI Legal Framework Issues PAC NUSTAR PAC APPA FCI Full Cost Issues Mini-TACs Cryogenics Warm magnets Cold magnets Power Supplies Beam Instrumentation p-Linac TAC CORE Cost Review Groups Observers:

3 FAIR Baseline Technical Report
CN DE ES FI FR GB GR IN IT PL RO RU SE FAIR Baseline Technical Report Official FAIR project description 6 Volumes with more than 3500 pages and more than 2600 authors FAIR BTR Volume 1 Executive Summary Volume 2 Accelerator and Scientific Infrastructure Volume 3A Experiment Proposals on QCD Physics 3.1 CBM Volume 3B Experiment Proposals on QCD Physics 3.2 PANDA 3.3 PAX 3.4 ASSIA Volume 4 Experiment Proposals on Nuclear Structure & Astro Physics (NUSTAR) 4.1 LEB-SuperFRS HISPEC/DESPEC 4.3 MATS LASPEC 4.5 R3B ILIMA 4.7 AIC ELISe 4.9 EXL Volume 5 Experiment Proposals on Atomic, Plasma & Applied Physics (APPA) 5.1 SPARC HEDgeHOB 5.3 WDM FLAIR 5.5 BIOMAT Volume 6 Civil Construction and Safety For down load of the report: Introduce BTR in particular Executive Summery. Vol 3 to 5 contain: Technical proposal of en experiment and one finds: Executive Summary, Introduction and Overview, Physics case, Systems.description, Implementation and Installation, Commissioning, Operation, Safety , Organization and Responsibilities, Planning, Relation to other Projects , Other issues , References and Acknowledgements

4 EU support for FAIR related activities in FP6
EU-6FP-CNI: FAIR injector SIS18 intensity upgrade, HADES upgrade + R3Bmagnet EU-Support: 10,4 M€ EU-6FP-Design Study: Secondary Beams (RIB and Antiprotons) EU-Support: 9 M€ EU-6FP-I3 programmes I3HadronPhysics: FAIR related EU-Support: 10,8 M€ EURONS: FAIR related EU-Support: 2 M€

5 Project Status and next steps:
Building Development plan legally settled All environmental impact studies are accepted; Re-forestation and natural compensation measures are concluded and contractually settled  Controlling report for the preparatory phase accepted by GSI Supervisory Board Core facility and Specifications defined Layout defined Project cost estimates (cost book, WBS) scrutinized and validated by expert groups Prototyping has started Scientific base programme is defined Baseline Technical Report ready and issued 21 March (~ 3500 pages, ~2500 authors)

6 Project Status and next steps:
 Legal documents and Governance structure (two-company model) finalized and agreed upon by the ISC (by laws to be completed; tax status to be confirmed)  Roadmap presented to the ISC. Goal: foundation of FAIR GmbH in May/June 2007 ( Joint Core Team) The International Steering Committee confirmed all this joint preparatory work and its results as fully conforming to the requirements of the FAIR MoU and as " the Project." Consequence: all conditions to finalize negotiations on governmental level are met.

7 Project Status and next steps:
1. Finalization of by laws (AFI sub-group: national experts most welcome) 2. Establishment of the Joint Core Team (transition to FAIR GmbH); calls coming soon (after October ISC) 3. Appointment of shareholders 4. Negotiations and final checks of legal documents

8 Signature of Convention and Final Act
Proposed FAIR – Roadmap: Establishment of FAIR GmbH STI AFI joint meeting ISC/SH ConventionFinal Act meetings ISC ISC AFI AoA 07/ / Nomination of Shareholders + Completion of negotiations Signature of Convention and Final Act Contracting Parties Negotiations (ongoing, 'till end of 2006) First meeting: start senior staffing Signature AoA Share-holders (SH) Constitutive Meeting of the Council Formation FAIR GmbH Convention, Final Act, AoA; Joint Core Team Bylaws, draft FAIR GmbH structure and kick-off staffing Mandate for IKAB ISC Convention, Final Act, AoA; Bylaws (first draft) Bylaws, draft FAIR structure AFI STI Monitoring of technical planning and project costs (ongoing process up to the formation of FAIR GmbH) Bylaw Subgroup Completion of draft Bylaws Elaboration of the Bylaws (ongoing) Joint Core-Team Technical project decisions (follow up design changes) / FAIR preparation tasks (ongoing process up to the foundation of FAIR GmbH) IKAB Technical evaluation of potential in-kind contributions (ongoing process up to the formation of FAIR GmbH)

9 DRAFT: Organizational plan of the FAIR GmbH
External Committees: Scientific Advisory Committees Accelerator Advisory Committee Resource Review Boards DRAFT: Organizational plan of the FAIR GmbH Council - Shareholders assembly Management (2 managing directors) FAIR Director, Director for Finances and Administration management team (directors office) audit &controlling public relations EU projects safety Finances and Administration Research Accelerator Integration Financing and budget Bookkeeping & accounting Contract follow up General administration Mech. Interfacing quality management project coordination NUSTAR resource coordinator technical coordinator CBM HESR Electr. Interfacing Finance Committee Scientific Council visitors science prog. engineering documentation PANDA APPA Civil Construction planning Regulatory aspect & Permits NESR p-Bar TARGET RESR/CR Super-FRS p-LINAC SIS100 SIS300 HEBT + member states relations Injector Upgrade

10 DRAFT: FAIR Joint Core Team
External Committees: Scientific Advisory Committees Accelerator Advisory Committee Resource Review Boards DRAFT: FAIR Joint Core Team Council - Shareholders assembly Management [1] management team [2] (directors office) audit &controlling public relations EU projects [1] safety Finances and Administration [4] Research [4] Accelerator [6] Integration Financing and budget Bookkeeping & accounting Contract follow up General administration Mech. Interfacing quality management project coordination NUSTAR resource coordinator technical coordinator CBM HESR Electr. Interfacing Finance Committee Scientific Council visitors science prog. engineering documentation PANDA APPA Civil Construction planning Regulatory aspect & Permits NESR p-Bar TARGET RESR/CR Super-FRS p-LINAC SIS100 SIS300 HEBT + member states relations [2] Injector Upgrade [FTE at startup]

11

12 SC magnets for SIS300 : France, Italy and GSI
sc cable development curved dipole prototype BNL follow up of „GSI001“ 4 T, 1 T/s SIS300 Quadrupole Field calculations, Design, cryogenics

13 FAIR accelerator developments in Russia and Spain
SIS300 BINP Novosibirsk IHEP Protvino + Rosatom UNK dipole Magnet, power converters, vacuum components on sc magnets for NESR/RESR e--Isotope Collider SIS100 JINP Dubna Short NUCLOTRON-type prototyp at GSI

14 FAIR accelerator developments in China and India
Variable Energy Cyclotron Center, Kolkata Institute for Modern Physics Lanzhou Center of Advanced Technology Indore Institute for Plasma Physics Hefei Saha Institute of Nuclear Physics, Kolkata Superferric dipoles for Super-FRS and CR and high intensity beam stoppers

15 HESR Consortium FZ Jülich, TSL Sweden and
HESR Consortium FZ Jülich, TSL Sweden and PANDA experiment collaboration Collaboration >350 participants 107 events/s TSL 14 m Pelletron Electron energy MeV 30 m cooling length 30 m cooling length

16 Key technology: Fast Cycling Synchrotrons
SIS100 magnets: 50 K yoke with superconducting coil (Nuclotron JINR Dubna) Developments: Reduction of AC losses during ramp, achievements: 40 W/m -> 13 W/m Bmax= 2 T, dB/dt = 4T/s, f = 1 Hz SIS 300 magnets: cos - magnet Developments: Reduction of AC losses during ramping by improved cable and coil design Efficient conductor cooling Bmax = 6 T, dB/dt = 1 T/s „GSI001“ 4 T, 1 T/s by BNL (HERA: 4 mT/s, RHIC: 70 mT/s, LHC: 8 mT/s)

17 Conclusions on Commitments for Accelerator parts
CN DE ES FI FR GB GR IN IT PL RO RU SE Conclusions on Commitments for Accelerator parts No written commitments exist on in-kind contributions, besides Sweden for Cryring CN-China: Interest expressed verbally for design and construction of CR and Super-FRS dipoles DE-Germany: GSI: items to be specified FZ-Jülich: HESR design and construction ES-Spain: Dipoles NESR and RESR, power supplies, vacuum, FI-Finnland: items to be specified FR-France: items to be specified (design of SIS300 quadrupoles), GB-United Kingdom: items to be specified, meeting foreseen October 12th, GR- Greece: items to be specified, no contact so far IN-India: Energy Buncher (4x 80 t sc dipoles), beam stoppers, verbally agreed IT-Italy: SIS300 dipoles proposed verbally PL-Poland: items to be specified RO-Rumania: items to be specified RU-Russia: SIS100 magnets, SIS300 magnets, e--RIB collider, SE-Sweden: Cryring, part of Electron Cooler, other items to be specified