Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.

Similar presentations


Presentation on theme: "Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract."— Presentation transcript:

1 Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract Sum:$11,182,000 Total Project Cost:$13,682,854 Change Orders to Date (1):$2,874 Current Phase:1, 1a, 1b (On Schedule) Estimated Completion:24% September 2009

2 Leestown Middle – Renovation Rendering of Final Façade September 2009

3 Leestown Middle – Renovation Work Completed in Last 30 Days: Phase 1 A, B & C demolition efforts on-going. Phase 1B Asbestos abatement on-going. Phase 1 A, B & C hollow metal door frames. Phase 1 A & B interior masonry wall erection on-going. Phase 1 A & B interior masonry in-fill & patch work started. Phase 1 A, B & C Erection of Structural steel started. Phase 1 A, B & C setting of bar joists started. Court yard seating walls and concrete paving are on-going. Foundations for the courtyard addition are on-going. Metal stud walls in Administration Suite are complete. Cafeteria soffits are on-going. Above ceiling ductwork has started in the Cafeteria. September 2009

4 Leestown Middle – Renovation Current Work Effort (September): General demolition in Phases 1A, B & C will continue. Plumbing, HVAC, electrical demolition on-going. Structural steel and bar joists will continue to be erected Metal roof decking to start. Electrical and Plumbing rough-ins on-going. Masonry load bearing masonry at Kitchen to be completed. Phase 1C (Courtyard addition) foundation to be completed. Phase 1C slab to start. Erection of two story Fire Wall to begin. Installation of hollow metal door frames on-going in Phase 1B & C. Phase 1A & B, Work at existing built-up roofs to start. Installation of new built-up roof at Phase C. September 2009

5 Leestown Middle – Renovation New Addition at Kitchen Steel Erection at Courtyard Addition September 2009 Seating Wall at Courtyard New Addition Kitchen Serving Line


Download ppt "Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract."