Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.

Similar presentations


Presentation on theme: "Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall."— Presentation transcript:

1 Progress Report 12/13/11

2 Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall foundations poured Building Insulation Tower Foundation Completed Rough in of Fire Protection System Interior Plumbing, Roof Drains Work Scheduled January: Complete Roofing Frame Interior Walls Rough in M & E Erect Tower Run Electrical Service Run Natural Gas Service Start Masonry Screen Walls Complete Exterior Brick Window Installation

3 Progress 12/13/11 West Mechanical Screen WallRoof Blocking

4 Progress 12/13/11 Tower FoundationCall Center

5 Office Corridor Rough In Progress 12/13/11

6 Staff Support Rough InCall Center


Download ppt "Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall."