Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.

Similar presentations


Presentation on theme: "Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010."— Presentation transcript:

1 Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$9,061,000 Change Orders to Date (1):$2,878.14 Current Phase:1 (On Schedule) Estimated Completion:19% August 2009

2 Cassidy Elementary – Renovation Rendering of Final Façade August 2009

3 Cassidy Elementary – Renovation Work Completed in Last 30 Days: Storm sewers installed on south side and across new front parking lot. Grading complete around new Morton Parking Lot. Concrete curbs and subgrade installed. Grading started at sidewalks and playground. Concrete retaining walls in place. Fire Protection water pit installed at Cassidy Rd. Gas main installed. Sanitary sewer manholes and connector piping installed. Demolition continues with new stage opening and new openings and doorways for corridor extensions. Stairway demolition is approximately 75% complete. Foundations for stage complete. Music Classroom addition foundation, 1 st floor slab, 2 nd floor joist and slab installed. Masonry bearing walls and steel column/beams complete. Interior masonry partition walls on going. Plumbing rough-ins have continued as masonry walls are installed. Electric conduits and rough-ins continue in Admin Addition above ceiling and in masonry walls as needed. August 2009

4 Cassidy Elementary – Renovation Current Work Effort (August): Storm sewers will continue as site work allows. New 3” domestic water main service will complete. Site grading will complete around the playground. Sidewalk/paving work will complete at playground area. Chimney demolition to begin the first week of September – pending confirmation that chimney swifts have vacated. Stage concrete slab and masonry bearing walls to be complete. Roof joists for Music Rm. and Stage Addition to be in place. HVAC ducting and piping to start in the Admin. Addition and existing building in Phase 1 area. Sprinkler piping to start in the Admin. Addition and existing building in Phase 1 area. Electric conduit and rough-ins to continue. August 2009

5 Cassidy Elementary – Renovation New Admin. Addition 2 nd Fl. New Playground Retaining Walls August 2009 Interior Gym New Stage & Music Room Addition


Download ppt "Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010."