1 Newark CSD Phase II Capital Improvement Project Board of Education Report August 2013

2 Sanitary Storm Sewer Work at Wood Lane Drive Adjacent to Bus Garage Sanitary Storm Sewer Work at Wood Lane Drive Adjacent to Bus Garage Installation of Perkins Elementary Roof Installation of Perkins Elementary Roof

3 High School Cafeteria Demolition and Interior Wall Construction High School Cafeteria Demolition and Interior Wall Construction

4 High School Access Road Site Work And Curbing

5 Kelley Intermediate Retaining Wall

6 High School  New Corridor Ceiling System and Lighting  Turnover of New Food Service Office  Boiler Feed Tank and Condensate Feeds  “B” Shift New Corridor Wall Tile Work Will Be Underway  New Doors and Hardware Will Be Proceeding After School Hours Middle School  “B” Shift New Corridor Wall Tile Work Will Be Underway  New Kitchen Grease Seperator Will be Completed Kelley Intermediate  New Nurse’s Office Will Be Turned Over For District Use  Kitchen Tile Work Is Anticipated To Be 80% Complete With The Balance Being Completed During “B” Shift  New Kitchen Grease Seperator Will Be Completed Lincoln Elementary  Door And Hardware Replacements Ongoing Perkins Elementary  New Kitchen Grease Seperator Will Be Completed  Sheet Metal Trim Work On The Roof Will Be Substantially Completed Site Work  Anticipate Having All Asphalt Binder In Place At Paving Locations, Top Coarse To Follow


Download ppt "Newark CSD Phase II Capital Improvement Project Board of Education Report August 2013."