Presentation is loading. Please wait.

Presentation is loading. Please wait.

Update on FCPS Construction/Renovation Projects May 2009.

Similar presentations


Presentation on theme: "Update on FCPS Construction/Renovation Projects May 2009."— Presentation transcript:

1 Update on FCPS Construction/Renovation Projects May 2009

2 Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$9,061,000 Change Orders to Date:$0 Current Phase:1 (On Schedule) May 2009

3 Cassidy Elementary – Renovation Rendering of Final Façade May 2009

4 Cassidy Elementary – Renovation Work Completed in Last 30 Days: New staff parking lot @ Tates Creek Rd. cut to subgrade. Subgrade for new 2-Story Administration/Classroom Addition completed and foundations begun. Original Stage and Music Room demolition complete. Miscellaneous interior demolition continued as needed. Current Work Effort (May): Stone installed in new parking lot for temporary staging area. New Music Room/Mechanical Room Addition foundation and concrete slab will be complete. New 2-Story Administration/Classroom Addition foundation and concrete slab will be complete. Masonry to begin with concrete block walls on 2 additions. Underground sanitary and plumbing rough-in work to start under new additions. Underground electric feeds and below slab rough-in to continue. May 2009

5 Cassidy Elementary – Renovation New 2-Story Admin Addition foundation New Staff Parking Lot subgrading, Tates Creek Rd May 2009 New Underground Detention System excavation New Music Rm./Mech. Rm. Addition site

6 Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August, 2010 Contract Sum:$5,001,150 Change Orders to Date:$0 Current Phase:1 May 2009

7 Russell Cave Elementary – Renovation Rendering of Final Façade May 2009

8 Russell Cave Elementary – Renovation Work Completed in Last 30 Days: Building pad and foundation bearing have been tested and approved. Footings and foundation walls: 125 feet of footings have been poured and 61 feet of foundation wall have been poured. Existing sprinkler line has been relocated. Current Work Effort (May): Additional work on footings and foundation at the new addition will continue. Installation of the new leach fields for the septic system will begin installation in the front lawn of the building. New electrical conduits will be installed in the existing crawlspaces to feed wiring to new addition and the existing kitchen. New cooler/freezer and hood roof curb for kitchen renovation is scheduled for delivery the week of June 8 th. Work will begin as soon as school is out. May 2009

9 Russell Cave Elementary – Renovation Foundation Work 5.5.09 May 2009 Foundation Work 5.5.09

10 Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: W/S Construction Substantial Completion Date:August, 2010 Contract Sum:$9,920,194 Change Orders: $36,900 (#1--Demo) Current Phase:1 May 2009

11 Arlington Elementary – Renovation Rendering of Final Façade May 2009

12 Arlington Elementary – Renovation Work Completed in Last 30 Days: Demolition completed Work at Site to begin in mid-May May 2009

13 Arlington Elementary – Renovation Demo – Main Bldg. May 2009 Demo – Gym

14 Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August, 2010 Contract Sum:$10,769,400 Change Orders to Date:$0 Current Phase:Phase 1 to begin June 1 May 2009

15 Bryan Station Middle – Renovation Rendering of Final Façade May 2009

16 Bryan Station Middle – Renovation Work Completed in Last 30 Days: GC conducting preparatory activities Work at Site to Begin June 1 May 2009

17 Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$11,182,000 Change Orders to Date:$0 Current Phase:Phase 1a, 1b, 1c to begin June 1 May 2009

18 Leestown Middle – Renovation Rendering of Final Façade May 2009

19 Leestown Middle – Renovation Work Completed in Last 30 Days: Pre-construction meeting held on 5/5/2009. Work at Site to Begin June 1 May 2009

20 Lafayette High Stadium – Replacement Architect: Strand & Associates General Contractor: Set to bid July 1 Substantial Completion Date:July, 2010 Contract Sum:TBD Change Orders to Date:$0 Current Phase:Construction Documents May 2009

21 Lafayette High Stadium – Replacement UPDATED – Existing Campus May 2009

22 Lafayette High Stadium – Replacement UPDATED – Existing Football Stadium May 2009

23 Lafayette High Stadium – Replacement UPDATED – New Football Stadium May 2009

24 Central Bus Garage – Adaptive Reuse Architect: Lucas/Schwering Architects General Contractor: James R. Leake & Sons, Inc. Substantial Completion Date:August, 2009 Contract Sum:$2,782,000 Change Orders to Date:$0 Current Phase:Construction May 2009

25 Central Bus Garage – Adaptive Reuse Façade May 2009

26 Central Bus Garage – Adaptive Reuse Proposed Floor Plan May 2009

27 Tonights Agenda Items Project Agenda Item Arlington Elementary Approval of BG-4 – Final Payment to Contractor for Demolition Work Superior Demolition: $44,724.30 Total Demolition Cost: $124,148 Lafayette Stadium Approval of Design Development & Construction Documents Total Estimated Cost: $5,795,500 Liberty Elementary Approval of Change Order #5 Total Credit for Unused DPOs: ($17,392.32) William Wells Brown Elementary Approval of Change Order #7 Total Credit for Unused DPOs: ($13,041.47) Change to GC Contract: ($439.62) May 2009


Download ppt "Update on FCPS Construction/Renovation Projects May 2009."

Similar presentations


Ads by Google