CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,

Similar presentations


Presentation on theme: "CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,"— Presentation transcript:

1

2 CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed, tile and grout installed - 2 nd Floor: Final coat of paint, tile and casework installed - 3 rd Floor: Tile and casework installed - Attic: doors installed (no hardware yet) East Wing - Exterior: Masonry and shingles complete, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework and counter tops being installed - 2 nd Floor: Painting, tile work mostly completed, casework being installed - 3 rd Floor: Mudding and taping drywall, rough sanding Central Lounge Area - Masonry completed West Parking Lot - Paving completed CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed, tile and grout installed - 2 nd Floor: Final coat of paint, tile and casework installed - 3 rd Floor: Tile and casework installed - Attic: doors installed (no hardware yet) East Wing - Exterior: Masonry and shingles complete, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework and counter tops being installed - 2 nd Floor: Painting, tile work mostly completed, casework being installed - 3 rd Floor: Mudding and taping drywall, rough sanding Central Lounge Area - Masonry completed West Parking Lot - Paving completed

3 Brick and cast stone completed at Northwest lounge and stair area, curtain walls nearing completion.

4 Northwest lounge area curtain walls nearing completion.

5 Brick and cast stone complete on East wing. Northeast stair curtain wall not yet installed, flashing has started.

6 Brick and cast stone completed at central lounge and stair. Weather barrier also installed on cornice.

7 Temporary exterior enclosures installed.

8 Temporary heat installed throughout entire building to accommodate acceptable working conditions and protection for products.

9 First floor West corridor study/lounge area, metal stud framing completed.

10 First floor West corridor four bedroom apartment, kitchen cabinets and some counter tops installed. First floor West corridor four bedroom apartment, kitchen cabinets and some counter tops installed.

11 First floor West corridor bedrooms, final coat of paint applied, visual display rails installed, shelving installed. First floor West corridor bedrooms, final coat of paint applied, visual display rails installed, shelving installed.

12 First floor East corridor studio apartment, kitchen cabinets installed, counter tops soon to be installed. First floor East corridor studio apartment, kitchen cabinets installed, counter tops soon to be installed.

13 First floor East corridor bathrooms, tile floor and cabinets installed. First floor East corridor bathrooms, tile floor and cabinets installed.

14 Cabinet Unit Heater installed in West corridor staircase. Cabinet Unit Heater installed in West corridor staircase.

15 West corridor third floor, curtain walls installed in private study room. West corridor third floor, curtain walls installed in private study room.

16 East corridor two bedroom corner apartment ready for first coat of paint. East corridor two bedroom corner apartment ready for first coat of paint.

17 Third floor central lounge area drywall being installed. Third floor central lounge area drywall being installed.

18 Forms set for stoops located at the Northwest entrance. Will soon be pouring concrete. Forms set for stoops located at the Northwest entrance. Will soon be pouring concrete.

19 Bioswale located between the West wing of the building and the West parking lot.

20 Storm sewer line running from West parking lot to bioswale in place.

21 West parking paving complete.

22 Concrete work completed at loading dock area. Concrete work completed at loading dock area.


Download ppt "CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,"