GLAST LAT Project ISOC Subsystem1 Response to Peer Review RFA 6  Request: –Need to provide more information on the planned and actual staffing profiles.

Similar presentations


Presentation on theme: "GLAST LAT Project ISOC Subsystem1 Response to Peer Review RFA 6  Request: –Need to provide more information on the planned and actual staffing profiles."— Presentation transcript:

1 GLAST LAT Project ISOC Subsystem1 Response to Peer Review RFA 6  Request: –Need to provide more information on the planned and actual staffing profiles. Identify which areas that are needed now are not filled, what is being done to fill them, and their role in being able to prepare for the ISOC CDR. The ground software engineer for example would seem to be a prerequisite for preparing for the CDR, let alone actually conducting it. Would also seem to need a test engineer

2 GLAST LAT Project ISOC Subsystem2 Response  The staffing profile for the ISOC has been developed and the budget for activities agreed upon with SLAC management. –See chart on next page for staffing by function –The large jump in FY05 reflects the CD4 milestone (delivery to NRL for environmental test) and the end of the construction phase of the project; at this point most LAT staff (e.g. SAS, FSW etc) are in the ISOC.  We have hired a software engineer (Steve Culp) who is developing an architecture for the ISOC operations software.  We have hired a software engineer (Jim Lemon) who will implement the ISOC databases  We have hired a technical writer (Lee Steele) who will develop the remaining ISOC documents including the Operations handbook.  We will need additional software developers/physicists later in CY 04. We have no current unfilled slots.

3 GLAST LAT Project ISOC Subsystem3 ISOC Staffing Plan Plan matches actuals through July 04

4 GLAST LAT Project ISOC Subsystem4 ISOC Organization ISOC Manager 4.1.B.10 Command, H&S Commanding Health & Safety Configuration 4.1.B.11 FSW Thermal Control Trigger Filter Testbed 4.1.B.12 Performance V&O Calibration Performance Trending Standard Source Monitoring IRF Generation 4.1.B.13 Science Products Level 1 CRs, gammas, diagnostics Level 2 Transients, GRBs Pipeline Server 4.1.B.14 Science Analysis Software Simulation Calibration Reconstruction & Event Classif. Transient Source Analysis Databases