GLAST LAT Project Online Peer Review – July 20, 2004 4.1.9 - Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review.

Similar presentations


Presentation on theme: "GLAST LAT Project Online Peer Review – July 20, 2004 4.1.9 - Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review."— Presentation transcript:

1 GLAST LAT Project Online Peer Review – July 20, 2004 4.1.9 - Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review Online Peer Review July 21, 2004 Summary Ric Claus Online Manager SLAC Gamma-ray Large Area Space Telescope

2 GLAST LAT Project Online Peer Review – July 20, 2004 4.1.9 - Integration and Test R. Claus 2 Conclusion We have made great progress. We have a well established scripting framework –Run Control Message Logger Environmental Monitor Register Browser Data visualization –Scripts –E-logbook –Data persistence, archiving and parsing –CM – versioning, releases, installation procedures –Single event display –Issue tracker –Subsystem support All for only $19.95 + S&H… –But wait! There’s more: You get the documentation absolutely free!

3 GLAST LAT Project Online Peer Review – July 20, 2004 4.1.9 - Integration and Test R. Claus 3 Concerns Timely delivery from subsystems –FSW (LATc, Housekeeping stream) –SAS (pipeline, now delivered…) Subsystem focus on their I&T over LAT I&T –Multiple philosophies –Merging work needed to ensure delivered scripts will work in the LAT I&T environment Greater than expected support requirements –EM-2 (we’re not quite ready to treat it like flight yet) –GASU commissioning –PRU Road-show

4 GLAST LAT Project Online Peer Review – July 20, 2004 4.1.9 - Integration and Test R. Claus 4 Summary Presented Online System features and interfaces Presented list of completed and not yet completed items Presented plan for completing unfinished items Presented verification and validation plan  Software is never finished –There will always be change requests –This will be brought under control via a CCB (LAT-MD- 03492)  Aim to be ready with something that meets the baseline EGSE requirements


Download ppt "GLAST LAT Project Online Peer Review – July 20, 2004 4.1.9 - Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review."