Group M3 Nick Marwaha Craig LeVan Jacob Thomas Darren Shultz Project Manager: Zachary Menegakis February 23, 2005 MILESTONE 6 Component Layout DSP 'Swiss.

Similar presentations


Presentation on theme: "Group M3 Nick Marwaha Craig LeVan Jacob Thomas Darren Shultz Project Manager: Zachary Menegakis February 23, 2005 MILESTONE 6 Component Layout DSP 'Swiss."— Presentation transcript:

1 Group M3 Nick Marwaha Craig LeVan Jacob Thomas Darren Shultz Project Manager: Zachary Menegakis February 23, 2005 MILESTONE 6 Component Layout DSP 'Swiss Army Knife' Overall Project Objective: General Purpose Digital Signal Processing Chip

2 STATUS Design Proposal (Done) Architecture (Done) Size Estimates/Floorplan/Verilog (88% - comb/Wallace alterations) Gate Level Design (85% - comb/Wallace alterations) Component Layout (Done - However, continue to optimize) To Be Done Complete layout of functional blocks Wallace Tree Multiplier, etc. Schematic Make remaining adjustments for comb/Wallace Verification Test for adjusted blocks

3 DESIGN DECISIONS Comb Made Adjustment for functionality in Real number domain. Wallace Tree Multiplier Currently implementing the basic Wallace Booth Recoding intended next

4 DESIGN DECISIONS Porosity of Basic Components Using only Metal 1 and Poly in order to ease global routing Use Metal one AND Metal 2 for basic components Imaginary Numbers Working on soft IP while verifying current design has tossed off all old complex components.

5 MENTAL BREAK

6 WALLACE TREE MULT. Traditional Wallace Tree Booth Recoding Wallace Tree

7 OUR WALLACE TREE

8 TRANSISTOR COUNT (updates)

9 FLOORPLAN UPDATE

10 UPDATE – TEXT VERSION Since Monday @ 3pm: Craig – Worked on Wallace Tree Darren – Worked to get old missed milestones caught up (Structural) Jake – Worked on Floorplan Nick – Got on a plane…

11 PROBLEMS & QUESTIONS Booth Recoding Still walking through Problem: Timing issues with top level design. Haven’t tackled yet (fixing lower blocks to avoid complications*) * scientific method: only test one variable at a time