1 Mauro Savrie' INFN Ferrara
BES III Italy Update on CGEM CGEM Detector layout Present status Time schedule gas system for CGEM Cooling system IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

2 Mauro Savrie' INFN Ferrara
CGEM-IT Detector 3 layers: L3 L2 L1 Layout: Anode, Gem1,Gem2,Gem3, Cathode (2mm,2mm,2mm,2mm,5mm) 30 permaglass structural rings 6 permaglass service flanges 2 supporting flanges 28 Gas connectors ( inlets+outlets) 2 interconnecting flanges (end March) 78 HV cards Tooling: 15 aluminium moulds Microscope table: visual Gem foil insp. Planar gluing table Cutting Gem/anode Foils table Tooling for Detector assembly Clepsydra Positioning table Centering device ( Layers assembly) 2 interconnecting flanges: il disegno sara’ finito per la fine di Marzo IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

3 CGEM-IT/MDC interface
flange1 flange2 East side (gas inlet-bottom) West side (gas outlet-TOP) Dimension of CGEM-it: Rmin: 68mm; Rmax: 181 mm; Lmax: n.g. Lmax: 1045mm To be replaced: Flanges 1 east and west will disapper flange2 (west side) will stay in place Flange2 ( east side ) will be a new one or modifed CGEM: Rmin=68mm; Rmax,anode=179.2;Rmax,ing.=180.7 Cilindro di separazione: Rmin=182.5mm Clearance:1.8mm Lunghezza disponibile per CGEM: L=1046 IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

4 CGEM-IT update New Ring Aluminium Permaglass
East Supporting Flange West Flange 2 to be modified West Flange 2:fixed West Supporting Flange New Ring It holds the separation cylinder It is screwed on West Flange Aluminium Permaglass Supporting flanges: INFN Ferrara New Ring: IHEP IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

5 Mauro Savrie' INFN Ferrara
CGEM-IT update Supporting flanges modified IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

6 Mauro Savrie' INFN Ferrara
CGEM Layer 1 Mechanics: General drawings: completed and approved Tooling & materials: Aluminium moulds: delivered Accepance test in LNF: done Permaglass rings: already checked and ready Service flanges & spare rings: expeted by the end of March Kapton: GEM,Anode,Cathode, Ground Plane (no planar gluing): delivery by March 8 but the Anode end of March. acceptance ( Visual & HV test ): in LNF by the end of March L1 construction: L’ anodo non era di buona qualita’ ed viene riprocessato: 3 settimane Cathode: already started beginning March Anode, Gem1,Gem2,Gem3: ready beginning of April L1 assembly : second half of April IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

7 Mauro Savrie' INFN Ferrara
CGEM Layer 2 Mechanics: General drawings: all executive drawings done Tooling & materials: Moulds: Cathode  second week in April Permaglass rings & Service Flanges: 6/14 ordered (expected by mid April?? ) Kapton: Gem,Anode,Cathode, Ground Plane (planar gluing): Anode circuit: beginning of April Cathode : beginning of April Gem1-3: flushing to 3 microns Ready ( undulation compensation) acceptance ( Visual & HV test ): by the end of April (LNF) Check the tables and tooling for tests in LNF end of April L2 construction: should start first week in May Permaglass Federico deve fare le tavole e poisi fanno gli ordini I circuiti delle GEM e il catodo presentano leggere ondulazioni che possono essere compensate mediante ricottura in forno in atmosfera di N2 L2 construction: Start: first week in May Completed: End of July IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

8 Mauro Savrie' INFN Ferrara
CGEM Layer 3 Mechanics: 3D model to be completed: close to be done executive drawings: Moulds and accessories: ordered. Permaglass rings and flanges : executive drawings (end April) Cathode, Anode & GEMS: executive drawings (end April) Tooling & materials: Moulds: Expected by the end of May Modify gluing table and other facilities for the tests in LNF ( LNF) Modify interface ring for clepsydra Kapton: Gem,Anode,Cathode, Ground Plane (planar gluing): Drawings ( Gatta/Melchiorri): mid April Anode circuit : End of June G1-3, Cathode, gnd plane: End of June acceptance ( Visual & HV test ): in LNF Beginning July L3 construction: Start: first week in August…..hopefully Completed: End of October IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

9 Mauro Savrie' INFN Ferrara
CGEM-it assembly Tooling necessary for assembling: Layers: Clepsydra: changes needed for L1 and L3 assembly ( new rings side out) Ready Tooling for centering GEMs while assembling the layer Done CGEM-it: work ongoing IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

10 Mauro Savrie' INFN Ferrara
CGEM summary & issues Layer 1 all items available by the end of March at the latest Layer 2 not on a critical path: Anode design and production Gem flushing ( Cu to 3 µm ) Cathode & other designs ready Orders already placed Layer 3 A lot of work to do but we are still on schedule IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

11 Mauro Savrie' INFN Ferrara
F.E. Cooling Two system : Cold liquid flow INFN Torino Responsibility & coordination: Beppe Giraudo Cold Air Flow Measuring system is ready and working Mockup ( half detector ) is equipped We stated measuring with air flow at ”room Temperature” Airvortex device: arrived and tested Measurements with Airvortex are in progress IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

12 Mauro Savrie' INFN Ferrara
Air Flow Cooling Test Two adjacent channels Power:2.2 W Tmax=58-60°C Two adjacent channels Power: 3.7 W Two steps cooling Tmax= 75-85°C IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

13 Mauro Savrie' INFN Ferrara
Air Flow Cooling Test all channels Power: 2.5 W Tspread= °C All channels Room temperature ~1 °C spread IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

14 Mauro Savrie' INFN Ferrara
Air Flow Cooling Test all channels Power: 2.5 W Tspread= °C All channels Room temperature After re-calibration ~1 °C spread IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

15 Mauro Savrie' INFN Ferrara
Air Flow Cooling Test with Airvortex IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

16 Air Vortex Cooling Test
all channels Power: 2.4 W Tspread= 8-36 °C Cooling stability IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

17 CGEM Concluding remarks
MDC/CGEM Integration Critical items (to be fixed by in New Aluminium ring Separation cylinder Clearance: already during the first Integration meeting CGEM/MDC: ΔR~1.8mm; CGEM/beam pipe:ΔR~10mm Insertion Tooling Fix the milestones & line IHEP in March Gas System Same as for MDC seems to be a good solution If we choose Ar/C4H10 we need to define a max allowed leakage Fix the IHEP in March Cooling system: test with cold air: not very promising Cold liquid system: very good results from Beppe Giraudo (INFN-Torino) Ci sono problemi per I crates dell’ elettronica off-detector Gigi e Angelo IHEP 2017/03/14 Mauro Savrie' INFN Ferrara

18 Mauro Savrie' INFN Ferrara
Thank You IHEP 2017/03/14 Mauro Savrie' INFN Ferrara