By Henry Ogoye Head of Corporate Planning and Strategy 9 th December 2013 Investment Opportunities- KAA.

Similar presentations


Presentation on theme: "By Henry Ogoye Head of Corporate Planning and Strategy 9 th December 2013 Investment Opportunities- KAA."— Presentation transcript:

1 By Henry Ogoye henry.ogoye@kaa.go.ke Head of Corporate Planning and Strategy 9 th December 2013 Investment Opportunities- KAA

2 2 2 Outline  Background  Traffic Performance and Outlook  Investment Areas and  Investment Climate

3 3 3 KAA: Background -Established in 1991 by an Act of Parliament, the KAA Act -Provides and manages aviation infrastructure, facilities and services. -Manages: -4 IA- Nairobi, Moi, Eldoret and Kisumu ; -4 DA- Wilson, Malindi, Lokichoggio and Wajir; and -6 AS- Ukunda, Manda, Kitale, Garissa, Lodwar, Kakamega. -Nairobi Airport- flagship facility -Main gateway in the East & Central Africa region, -Currently serves over 30 scheduled airlines, -Catchment area: EU, the ME, the FE and African Regio n, -Accounts for about 75% of national aviation traffic and -Among the busiest airports in Africa w.r.t. pax (cargo) traffic

4 4 4 Nairobi Airport: Traffic Performance Vs Design Capacity

5 5 5 Nairobi Airport: Traffic Performance Vs Design Capacity (Cont’d)

6 6 6 Nairobi Airport- Traffic Outlook: 2012-2030

7 7 Nairobi Airport- Unit 4 and Re-organization -Terminal 4 – 2.5 million capacity. Acquisition & installation of BHS, PBB, Security, ICT & CE in progress. Cost US$ 110 M- AFD, WB & KAA. Partial commissioning - 2014 -T4 Arrivals Building – February 2015. Estimated cost US$ 25.8 M- WB -Reorganization of Units 1,2 and 3 for modernization and space – 2016 Estimated Cost-US$ 150M. EIB – US$93 Million. -Contractors /Funding.

8 8 Terminal Unit 4

9 9 View from the East

10 10 View after expansion programme for unit 1 to 4 Level 2 separation Walkways infill 1 Infill 2 New Apron Multi-Storey Car Park Unit 1 Unit 4 Unit 2 Unit 3

11 11 Green Field Terminal –178,000 M 2 terminal building on 4 levels –50 international Check-in positions –32 Contact and 8 Remote gates –45 Aircraft stand apron –Landside and Airside roadwork –Associated utilities –Railways terminal- construction- KRC

12 12 Green Field Terminal Cont. –Passenger Boarding Bridges - JBT Aerotech Corporation (USA) –Airport Security Equipment – L-3 (USA) –Airport Seats – Kusch Co. (Germany) –Airport Information systems – Airolusion (UK) –Electrical Switchgear, Control Systems & Generators – Schneider Electric (France) –Generators – Caterpillar (USA) –Baggage Handling System – Vanderlande Industries B.V - Netherlands 12

13 13 Green Field Terminal (Cont). –Estimated Cost: US$ 654 Million- Loan + Own Funds –Contractor: Pascall + Watson architects/Anhui Construction Group JV – UK/China –Supervision- Loius Berger Group, Inc –Status: Ground breaking - 3 rd December 2013. -Investment Opportunities : Duty free, Transit Hotel- 50 rooms and Commercially Important Persons Lounge

14 14 Greenfield bird’s eye view

15 15 Second Runway –Length: 5.5 km- Code F: 60m wide by 15m shoulders, –Direct flights to New York 6403 NM at 32 ton payload 89% LF, –ICAO CAT II compliant to allow landing and takeoff in bad weather, –Estimated Cost: US$ 180Million, –Investment Opportunities: -Detailed Design under AfDB funding; and -Funding/Construction /supply of equipment

16 16 Moi Airport Pavement Works –Pavement rehabilitation to support operations; –Estimated Cost: US$100 million: World Bank ; –Tendering for construction scheduled to commence in 2014; and –Investment Opportunity: Construction and Equipment Supply.

17 17 Other Investment Opportunities –Cargo warehouse in Kisumu –Special Economic Zone at Nairobi Airport (NA) to host MUB; –Investors to participate in mapping of potential businesses for the SEZ- NA; –2 nd Specialized Freight Area- NA; and –Airport City- convention centers, airport hotel, hospitals, shopping malls and golf course- NA.

18 18 Investment Climate –PPP Act 2013 and associated Regulations- legal and regulatory certainty to investors, –GoK also putting in place the necessary infrastructure to ease cost of doing business in Kenya and –Attractive fiscal regime.