CMS CB, 22 June 20071 CMS Centre Status Lucas Taylor CMS Centre Project Manager CMS Collaboration Board CMS Week, June 2007 1.CMS Centre Status 2.New offices.

Similar presentations


Presentation on theme: "CMS CB, 22 June 20071 CMS Centre Status Lucas Taylor CMS Centre Project Manager CMS Collaboration Board CMS Week, June 2007 1.CMS Centre Status 2.New offices."— Presentation transcript:

1 CMS CB, 22 June 20071 CMS Centre Status Lucas Taylor CMS Centre Project Manager CMS Collaboration Board CMS Week, June 2007 1.CMS Centre Status 2.New offices in PS area 3.Video-conferencing

2 CMS CB, 22 June 2007 Lucas Taylor 2 Requirements Phase (Jan – Mar ’07 - see last CMS Week) CMS Centre” RTAG CMS NOTE - 2007 / 010 Functions and requirements –Offline DQM, calibration, rapid analysis… –Computing operations –Communication with P5 Control Room, LHC@FNAL, other remote centres Since last CMS Week –detailed technical studies –design work –project plans, costs… CMS Centre Vision Similar concepts 24 consoles Meeting rooms Office space LHC @ FNAL Already operational

3 CMS CB, 22 June 2007 Lucas Taylor 3 Technical Design Phase (Apr-May ’07 - baseline planning) Radiation –AB / SC: measured PS stray radiation, simulations –PS reconfigured, backup plan (concrete) Safety Commission Inspections –Measurements, evaluation of regulatory compliance –Fire safety, lighting levels, noise, temperature, air- conditioning, ventilation, –Ergonomic assessments - layout, workstations, furniture.. Acoustics –Measurements & simulations by external consultants

4 CMS CB, 22 June 2007 Lucas Taylor 4 Technical Design Phase (Apr-May ’07 - baseline planning) Taking account of these studies + experience of others… –CERN Control Centre (CCC) –LHC@FNAL – also for CMS so aim to be consistent –Erich Keller AG – control room construction company …designed the “CMS Centre” and associated needs for technical services –Electrics, air-conditioning, networks, telephones… –Refurbishment / civil eng. - floors, ceilings, doors … –Explored alternatives to minimize costs HVAC options, cheaper materials, simpler consoles… Thanks to CERN / TS and AB, IT, PH, SC and FNAL

5 CMS CB, 22 June 2007 Lucas Taylor 5 buildings 6,8,9 Projector CMS Centre Office Projector 1m x 2m1m x 2ms1m x 2m Corridor width: 1.4 m Corridor width: 1.2 m Width from pillar to console: 0.5 m Projector Meeting Room (AB) Rest area / kitchen Outreach 26.0 m Corridor width: 1.2 m Office / Small Meeting Room Office / Small Meeting Room 11.4 m Meeting Room (CMS) Technical Design Phase (Apr-May ’07 - baseline planning) Main room 25 – 40 people ~same size as basketball court Meeting room: 40 people Meeting room: 20 people

6 CMS CB, 22 June 2007 Lucas Taylor 6 Projector 1m x 2m1m x 2ms1m x 2m Corridor width: 1.4 m Corridor width: 1.2 m Width from pillar to console: 0.5 m Projector 26.0 m Corridor width: 1.2 m 24 Operations / Monitoring Consoles Technical Design Phase (Apr-May ’07 - baseline planning) 2-3 screens for interactive work Services cabinet PCs, cables, ventilation 2-3 monitoring screens (e.g. displays from Control Room) CERN Control Centre

7 CMS CB, 22 June 2007 Lucas Taylor 7 Baseline Plan Green Light Review - 18th Jun ‘07 Assessed scope (WBS) and costs Agreed how to proceed –budget authorization for TS Dept –Project management and control Technical work starts next week From CMS S. CittolinTriDAS PM M. Della NegraEx spokesman M. KasemannComputing PM P. McBrideComputing PM A. PetrilliResource Manager D. SticklandControl Room PM L. TaylorCMS Centre PM From TS Dept. M. NonisHead TS-FM Y. BodyCooling, Ventilation A. FavreElectrical

8 CMS CB, 22 June 2007 Lucas Taylor 8 Installation & Commissioning (Jul ‘07 – Mar ‘08) Requirements defined (RTAG)Mar 07 Technical evaluation / design studiesMar–Jun Baseline plan completeJun –WBS, schedule, costs “Green Light Review”Jun Technical Service InstallationJul–Nov IT systems installationNov–Dec Commissioning of applications Jan–Feb 08 CMS Centre ready for LHC data-takingMar 08 –Currently we are ~ 2 weeks ahead of original schedule

9 CMS CB, 22 June 2007 Lucas Taylor 9 New Office Space in the PS Area

10 CMS CB, 22 June 2007 Lucas Taylor 10 Video- and Phone-Conferencing CERN Meeting Rooms –Completed a technical assessment of CMS rooms 40: S2-A01, S2-B01, R-A-10, R-B10, 2-A01, 5-A01 PS Area: 8-1-016, 354-1-015, 354-1-016; P5 / SCX5, 28-S-029 –Full phone/video system in all rooms: ~ 500 kCHF –Decide priorities B40 auditorium, new room(s) in PS area … ? Some smaller rooms fitted for phone-conf only EVO now in production: http://evo.caltech.eduhttp://evo.caltech.edu –Groups please try it (VRVS support to early 2008)

11 CMS CB, 22 June 2007 Lucas Taylor 11 Video- and Phone-Conferencing Support At CERN: IT-UDS has made new proposal for support –In spirit of LCG recommendations of RTAG12 –Installation / management of equipment (we purchase) –Integration and on-call support of rooms / systems VRVS / EVO and H.323 (ECS / HERMES) –Phone-conferencing service – is still evolving –Integration with InDiCo: real / virtual room booking, click to launch collaborative tools, event archiving… General EVO support –Assess any remaining EVO development effort required to satisfy CMS needs and level of operational support –Propose a small technical advisory group Together with ATLAS, CERN, external experts … Priorities, compromises, alternatives?…and their costs –Aim for clear LHC-wide approach and funding model

12 CMS CB, 22 June 200712 Q & A 1.CMS Centre Status 2.New offices in PS area 3.Video-conferencing