How to keep the SPS running for another 25 years V. Chohan ( based on Input from N. Gilbert & many Equip. Groups) IEFC Workshop 12 th Feb 2010.

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
CONSOLIDATION ON CIVIL ENGINEERING AND TECHNICAL INFRASTRUCTURE P. Alves, M. Nonis, P. Pepinster, W. van Baaren 6 th ST Workshop – March 2003.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
ATC / ABOC Days – Session 4 – January D. Smekens AT-MCS-MNC 1 MAGNETS FOR SPS & BEAM LINES MTTR & Spare Policy for the LHC Injectors & Exp.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
‘Review’ of the machine protection system in the SPS 1 J. Wenninger BE-OP SPS MPS - ATOP 09.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
IEFC 2010 Workshop How to keep the PS operational for the next 25 years. 12-February-2010 R.Brown EN/MEF/ABA.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
A second Thyristor Controlled Static Var Compensator for SPS
Extraction and beamline progress B.Goddard TE/ABT.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
Essential Consolidation Items for LIU-PSB Collection from LIU-PSB WP holders.
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 1 SPS Magnet Test Campaign and Consequences for LS1 J. Bauche*, P. Catherine,
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
R2E/Availability Workshop Report - RadWG October 22 nd 2014 R2E/Availability Workshop 2014 October th 2014 R2E/Availability Workshop RadWG - Brief.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
What’s Falling Apart in the Injector Chain ? PS/SPS Days January 2005.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Linac4-PSB 160 MeV connection readiness review
ABT-EC EYETS Activities 2nd reports
Situation of the Static Var Compensators at CERN.
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
TE-MSC activities in SPS during LS2
LIU – EVM status and next steps
AD consolidation activities in LS2
TE-ABT Activities for LS2
Possible causes for SPS ZS2 misalignment
Installations, modifications, consolidation in 2005:
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
Renovation of the 45-year old PS magnets
the CERN Electrical network protection system
SPS activities during LS2 TE-EPC (Power Converter Group)
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Business opportunities related to CERN electrical network
Interlocking of CNGS (and other high intensity beams) at the SPS
Experimental Areas – LS2 planning
Review of hardware commissioning
ILO Industrial Opportunities Days, 6-7 June 2019
Presentation transcript:

How to keep the SPS running for another 25 years V. Chohan ( based on Input from N. Gilbert & many Equip. Groups) IEFC Workshop 12 th Feb 2010

General remarks : lots of information collected Review system by system, many slides, some with much detail as known…. – Vacuum, RF, Magnets, Kickers & septa, Beam Instrumentation, Interlocks, Cooling & Ventilation, Electricity, Power Convertors, Cabling, Handling, Dumps, RP, Tunnel Infrastructure etc…. IEFC Workshop 12 Feb 2010

Vacuum A report is in preparation for the injector chain First “estimate” – Operation to 2022 replace 50-70% of system hardware – Operation to 2035 replace 100% SPS – Spares (windows in target areas?) – TIDVG upgrade – MKE? Any major consolidation campaign (ABT, MSC, RF etc…) would involve a lot of vacuum activity IEFC Workshop 12 Feb 2010

Vacuum ( M. Jimenez) IEFC Workshop 12 Feb 2010

RF (Erk Jensen) In addition to the usual annual maintenance activities, the following items will require a consolidation for the next 20/25 years, considering we keep the present RF configuration: - spare couplers TWC200; - spare couplers TWC800; - spare tetrodes (budget ~ 1 MCHF/year); - Siemens and Philips amplifiers: replacement of RS2004 and YL1530 tetrodes by new diacrodes; replacement of RS2004 drivers by RS2058 drivers (major projects). This does not include the major upgrades needed to increase intensity IEFC Workshop 12 Feb 2010

Magnets (EDMS no: ) The magnets replacement programme (replacing weakest magnets every year) must continue – 2 year LHC runs?? Maintain a vigorous maintenance plan – Dielectric tests, endoscopic inspections, inter-turn testing, water hoses, maintain a healthy stock of spare coils and magnets Specific concerns – Water erosion, inter-turn shorts & fatigue of pole shim bolts – Study of water erosion problems – Good supply of spare coils – Replace pole shim bolts as part of the maintenance plan IEFC Workshop 12 Feb 2010

Beam transfer systems ( Full table) – Replace septa HV generators, diluter – LSS4&6 new fast pulsed magnets – Spare MKDV/H magnets – Replace timing systems – Buy Thyratrons for 25 years of operation (single supplier) Some of this is included in present Consolidation programs General remarks – for the septa equipment; consolidate the TPST (protection shield for thin septum magnets in LSS2) which turns out to be insufficiently rigid. – For the kickers, the usual maintenance activities, combined with the consolidation project already integrated in the White Book, will allow a normal operation for the next 20/25 years. – cable replacement campaigns : most probably in LSS1 (2010/2011 shutdown) and LSS2; possibly in LSS4 and LSS6 as well, but it is still hard to see what the radiation damage will be once the LHC is in full operation. IEFC Workshop 12 Feb 2010

BT (1) IEFC Workshop 12 Feb 2010

BT (3) IEFC Workshop 12 Feb 2010

Beam Instrumentation “Normal” replacement/upgrade of hardware will continue – Wire scanners New fast BWS prototype developed for installation from 2014, for PS SPS & LHC – BLMs New system for PSB in 2013 (LINAC4) PS and SPS afterwards – Beam position & trajectory systems SPS replacement planned for 2013 IEFC Workshop 12 Feb 2010

Electricity ( EN/EL) Existing Consolidation (44MCHf) – Covers 18kV substations, loops etc. Other items include – Replace 2 400/18kV transformers (8MCHf) – Replace SMB 18kV cable network (7MCHf) – Replace all TGBT switchboards (7MCHf) – Replace 40/72 18/4kV transformers (2.3MCHf) – Cable replacement in tunnel (40MCHf) – Remove unused cables (30MCHf) IEFC Workshop 12 Feb 2010

EN/EL details: F Duval Low voltage items (below) will be 60 years old and don’t comply anymore with safety rules & standards. 100% of them are considered in the estimation. Mitigation have to be discussed….! Upgrade works: 2 of the 3 400/18kV power transformers: roughly 8MCHF Those transformers are 37years old and will be 62 years old in 2035… SMB 18kV cable network (38km)was not included in the today consolidation plan despite of the same bad shape as the 18kv loop cable network. 7MCHF All TGBT switchboards (40 pieces) installed in will be 60 years old in 2035… 7MCHF All Power boxes “coffret force” (170 pieces) have to be changed; those are already 35 years old and built partially with plastic.. 0,75MCHF 18/0,4kV transformers replacement of 40 of 72 transformers 2,3MCHF All LV Power cables will be partially changed 17MCHF All safety lighting system 1,4MCHF All toolings and removal for LV Items 1,3MCHF Control cables are partially part of a continuous renovation program and will not be considered but le remaining part has to be changed once before MCHF A huge quantity of unused cables were/are abandoned in cable trays despite of continuous warning from our part, cable renovation as per previous items is not possible without removing unused cables from full cable trays and some cable trays update and renovation works have to be done 30MCHF Supervision and control has to be updated following all renovation works 0,35MCHF IEFC Workshop 12 Feb 2010

Power Converters MPS (dipoles & quadrupole converters) renovation is underway – (7MCHf) AuxPS and LHC transfer lines recently upgraded/installed annual maintenance not sufficient, a true consolidation over yrs of several millions ( G. Le Godec ) Two static VAR Compensators (BEQ2 & 3) will require replacement after 20 years operation (2022 & 2027) – The spare SVC, BEQ1, “will reach the end of it’s lifetime soon and will be dismantled” …. Spare? North area power converters will need replacing or renovation IEFC Workshop 12 Feb 2010

Power Converters SPS + Areas some general details + example of age/nos. in N.Area.. IEFC Workshop 12 Feb 2010

Access and safety systems SPS: PPS replacement is planned to start in /6? – Current “obsolete” system will be maintained as necessary Safety & Fire alarm systems will be maintained as long as necessary – Renovation??? IEFC Workshop 12 Feb 2010

Interlocks BIC is already in operation for SPS machine and transfer lines The WIC is deployed for SPS transfer lines only – TT40, TT41, TT60, TI2 & TI8 – Main ring magnet interlocks have never been renovated, could be replaced with WIC (800kCHf) IEFC Workshop 12 Feb 2010

Dumps, collimators.. Beam stoppers - Standard maintenance SPS – Scrapers: planned for consolidation – TIDVG Improved spare under constructions Experimental area equipment, target stations, collimators etc also need urgent maintenance – Some work is included in existing consolidation 2011 & 2012 IEFC Workshop 12 Feb 2010

Cooling & Ventilation In addition to the usual annual maintenance interventions General consolidation is necessary – reliability reasons, in order to reduce operation down-time, – reduce costs due to increasing repetition of breakdowns – difficulty to obtain spare parts (piping consolidation SPS, replacement of SPS tunnel safety valves, North area cooling tower and its rejected water (CO2 injection), …). The absence of a modern PLC based control system prevents (CCC) remote monitoring – only general alarms exist Safety concerns the presence of asbestos the new Legionella legislation (Fr, 2004) noise levels outside the legislation (SPS discharge water pumps, replacement of non-conform pressure vessels SPS, firefighting circuits, …); IEFC Workshop 12 Feb 2010

2.SU Work needed in the SPS Complex for the next 25 Years C. Podevin BE-ABP-SUIEFC February SURVEY & ALIGNMENT : SURVEY & ALIGNMENT : ABP/SU Anneau SPSFrequencyDurationUnit costNrTotal cost 1Annual tilt and altimetric control on quadrupolesEvery year2 wks SFr SFr Annual alignment correction on main magnets and maintenance on othersEvery year1 to 6 wks SFr SFr Global smoothing of all components in all directionsEvery 6-7 years4 months SFr SFr Total SFr TT10 1Annual altimetric control on floor pointsEvery year2 days SFr SFr Global smoothing of all components in all directionsEvery 6-7 years2 months SFr SFr Total SFr TT20 / TDC2 1Annual altimetric control on floor pointsEvery year (TT20) & 2 years (TDC2) 3 days SFr SFr Global smoothing of all components in all directionsEvery 6-7 years2.5 months SFr SFr Total SFr TT60 / TI2 1Annual tilt and altimetric control on quadrupolesEvery 2 years2 wks SFr SFr Global smoothing of all components in all directionsEvery 6-7 years2.5 months SFr SFr Total SFr TI8 1Annual tilt and altimetric control on quadrupolesAlmost every year2 wks SFr SFr planimetric control on quadrupoles and local smoothing correction on quadrupoles and other components (due to tunnel instability) Almost every 2-3 years 1 month SFr SFr Global smoothing of all components in all directionsEvery 6-7 years2.5 months SFr SFr Total SFr TT41 (CNGS) 1Annual tilt and altimetric control on quadrupolesAlmost every year2 wks SFr SFr planimetric control on quadrupoles and local smoothing correction on quadrupoles and other components (due to tunnel instability) Almost every 2-3 years 1 month SFr SFr Global smoothing of all components in all directionsEvery 6-7 years2.5 months SFr SFr Total SFr TOTAL SFr

Other systems Cranes, lifts, handling equipment are in the existing Consolidation plan SC/RP radiation monitoring - Ramses deployment is in the existing Consolidation plan Tunnel Infrastructure under study - Civil Engineering IEFC Workshop 12 Feb 2010

Additional SPS Upgrades will also come within 25 years….. The work to be done for an SPS upgrade is still a matter of study – by the SPS-upgrade working group, to be presented in June 2011 for possible commissioning in and cannot be dealt now. a summary of the work of this committee in its chairperson’s presentation is : &confId= &confId=42645 Some hypotheses are already being focused: these include coating of all dipole vacuum chambers, modification of injection kickers, RF system, beam dump system, collimation, beam diagnostics. IEFC Workshop 12 Feb 2010

spares

Conclusions ( S.Baird – Chamonix 2010) This is just a start – Some BUT DEFINITELY NOT ALL of these activities are included in current Consolidation programs. Strong and vigorous maintenance programs are very important IEFC Workshop 12 Feb 2010