Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.

Slides:



Advertisements
Similar presentations
LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
Advertisements

M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
R2E Status Report 18 th LSC Meeting, August 18 th 2013 CERN Radiation 2 Electronics (R2E) Project 18 th LSC Meeting August 16 th 2013 R2E Status Report.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
17 july 2008 Inner Triplets upgrade – 2013 Very first Schedule.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
EN-CV interventions during YETS
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
R2E relocation & shielding activities Anne Laure Perrot EN/MEF- LE R2E project meeting, 23 rd October 2012.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Installation of the T600 at Fermilab CSN2, September 22,
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
R2E relocation & shielding activities: status report Anne Laure Perrot EN/MEF- LE On behalf of the R2E coordination team LS1 Committee – meeting #48, 27.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
K. Foraz on behalf of OSS members
BE-BI Activities and Status: LHC and Injectors
TE-MSC activities in SPS during LS2
SMACC Tenth report [15 min] 13/09/2013
EYETS David Hay EN-OSS.
ELENA installation and commissioning status
Status of LHC installation & New Installation Schedule
K. Foraz on behalf of OSS members
AD consolidation activities in LS2
on behalf of the RF group
Update of cryogenic activities
The LHC - Status Is COLD Is almost fully commissioned
LS1 Committee January 24th, 2014
Long Shutdown for the LHC: Vacuum Beam Pipes
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
MPE main activities planned for LS2
SPS Planning for the EYETS Meeting 8 (07/12/2016)
EYETS septa status Septa activities TE/ABT Thierry Masson
EYETS septa status Septa activities TE/ABT Thierry Masson
K. Foraz on behalf of OSS members
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
LHC installation status
Experimental Areas – LS2 planning
Hardware Commissioning
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1

AD & LEIR 27/09/2013 LSC - EN-MEF-OSS 2 AD – BHN06: coils delivered at CERN on 30/10. Test will follow ATRAP area partially dismantled (very good collaboration) – UHM3107 and UVM3207 tanks : removed once again out of the machine for an inspection and the replacement of some gaskets – KFI tanks reinstallation expected mid Oct postponed to November – installation of the new access point is completed LEIR – Sector 1: All equipment back, DHV12 alignment control done, Cooling water restarted – Sector 2: Leak on a flange being repaired, bake-out in place – Access system - In service ATRAP area partially dismantled AD access system LEIR – Sector 2 ready

PS Done – New access system doors : SWY hardware installation completed – SMH57: exchange of pumps completed In Progress – CV Consolidation in progress – Consolidation of the 7 PS main magnets started 4 MU have been already removed from beam line and delivered to the Magnet workshop. – Septum 16 External Shielding in progress – Cabling campaign (PS ring) in progress – General equipment maintenance: Instrumentation, Beam Stoppers, (EN/STI) consolidation/maintenance program – PS Tunnel Air leakage sealing project (2 nd /3 phase): Air tightness of wall between TT2 and nTof completed – Power House renovation b355 started 11/10/13 LSC - EN-MEF-OSS3 MU14 removal Air units –center of ring TPS15- MTV cables

PSB Completed. – Installation of the new magnet support for the BTY.QFO.108 magnet (beam dump project). – Commissioning of the access control MAD – Successful replacement of the BI.SMH Septum magnet stack In progress – PSB beam dump replacement project on schedule. Reassembly and final survey of the BTM & BTY lines ongoing. – Cooling circuit upgrades to the main bending and quadrupole magnets. – CV consolidation and maintenance, kickers, Septa, vacuum beam instrumentation, Magnet and Beam stopper, cabling campaign. Forecast – Installation of the newly designed BCT’s – Installation of the newly designed Pick ups (UES) – Replacement of the injector line PR137 crane. – Renovation of the machine ring cranes PR134, 135 & /08/2013LSC - S. Baird4

SPS BA1: – Irradiated cabling campaign in on-going Kicker cables already removed and the installing of the new kicker cables is in progress. TT10: – The new support beams have been installed – Injecting into the crown of the tunnel is now the next step in the process. Other works: – TE/ABT have begun conditioning of the kickers in BA4. – This will continue until the end of November – TE/ABT are in the process of replacing Septas in BA2 – This will continue until the end of the year – EN/CV are replacing blocked pipework in TT20. – On-going – BE/ABP have noticed that the jacks provided for the large quads in sextant 6 are not adapted for the high load and keep on moving…They need to go back again and change them (61710,61810 and 61910) – This will not affect the schedule 20/09/2013LSC - EN-MEF-OSS5

Injectors progress curves 11/10/13LSC - EN-MEF-OSS6

LHC - P1 R2E – Pt1: – Finished Optical Fiber UJ-UL14/16 Ethernet UJ-UL14 Relocation of cryogenics equipment UJ-UL14 – In progress Commissioning Cryo Relocation of Power Converters UJ-UL14 Cable campaign UJ-UL16 LSS1: – DFBX: consolidation of current leads finished – Cable tray for forward detector finished – 13kA upgrade and displacement of the DQR finished – Modification of the DQR water pipes from next week (emptying) 01/11/13LSC - EN-MEF-OSS7 UL 14 activities

LHC – P1  P2 Arc 12 : – Finished SMACC: – W bellows opened – M openings finished and insulation removal – UPS replacement in RE 18 and 22 – In progress SMACC – Shunt installation started – Desolder and Solder BB started DFBA consolidation QRL compensator replacement header D Point 2 – SU maintenance finished – Cryogenic maintenance in progress LSS2 – Consolidation of the DFBX in progress – BTVSI installed – BTVST delayed due to a problem with EB welding machine in AP 01/11/13LSC - EN-MEF-OSS8

LHC - P2  P3 Arc 23 – SMACC M opening in progress (32%  82%) – UPS replacement going on in UJ32, finished in RE 28 – QRL Xray campaign in progress – Electrical maintenance P3 completed LSS3 – Cabling campaign Acceptance left side next week Connectors on right side ongoing 01/11/13LSC - EN-MEF-OSS9 UJ32– UPS replacement

LHC - P3  P4 Arc 34 – In progress Magnets reconnection completed SMACC: – W bellows completed Cryogenic consolidation completed QRL X-rays – New line C compensator deformed but not leaky P4 electrical maintenance – Forecast SMACC – M openings 01/11/1310 P4 electrical maintenance

LHC – P4  P5 LSS4 & P4 – Water cooled cables consolidation finished Short circuit tests next week – Electrical maintenance ongoing – New cooling tower installation in progress – Cryogenic maintenance Arc 45 – In progress QRL pumping Magnet reconnection (end Nov.) » AIV2 tests to be repeted – W opening (65%  85%) – DFBAI.5L – damaged bellow – repair finalized !!!!! – CRG consolidation 01/11/13LSC - EN-MEF-OSS11 DFBAI repairing UX45 - Cryogenic maintenance

LHC – P5 LSS5: – TOTEM Cabling finished Piping work postponed week 47 – New walk-ways installation in progress – Forecast New TCLP end mid-November R2E – P5 – Racks installation finished today – Safe room extension in progress – ERD (power converters boards) installation in progress – Relocation safety equipment in progress 01/11/13LSC - EN-MEF-OSS12 UL557 – Racks installation TOTEM cabling

LHC – P5  P6 Arc 56 – In progress QRL compensator replaced being tested SMACC – Non conformities being solved – W closure (priority to sector 67 ) – (46%  80%) – 1/14 vacuum subsectors being leak tested (W) » 6 sub-sectors validated DFBA consolidation – 5R – DFBAJ completed – DFBAK.6L – SHM disconnection in progress, transport scheduled on w47 New cables for BLM completed QRL pumping EPC 60A racks re-installation – Forecast UPS replacement 01/11/13LSC - EN-MEF-OSS13 QRL pumping

LHC – P6 LSS6 & P6 – Finished Cables pulling – In progress Cables connectors and tests Water cooled cable campaign in progress – priority on DFBAK.6L 600A upgrade TCDQ installed  waiting for the TCSP to close beam vacuum Walk-ways installation – Forecast MKB-MKD tests from next week – Issue BPMSB – chlorine traces found on surface – surface bake-out in 2 weeks 01/11/13LSC - EN-MEF-OSS14

LHC – P6  P7 Arc 67 – SMACC in progress: Diodes consolidation finished M lines vacuum tests (71%  71%) W Closure activities in progress (32%  70%) 4/14 vacuum subsectors leak tested (W) and 4/14 in progress Beam pipes leak test successful ! DFBA consolidation – 6R DFBAL finished – 7L DFBAM being finalized – QRL compensator finished and tested – BLM new cables installation in progress – Optical fiber from W46 LSS7 – Modification of air ducts finished – 600A upgrade in progress – Consolidation on HRL valves ongoing – Mechanical work on beam vacuum to close A5L7 ongoing – NEG activation of A7R7 next week – No warm magnet transport – in situ consolidation R2E – P7: – Fixation of fireproof racks finished – UPS installation in progress – UTA installation in progress 01/11/1315 Chilled water pipes dismantling being estimated Leak tests

LHC - P7  P8 Arc 78 – Splice consolidation in progress Shunt installation completed Insulation boxes installed 22  136/212 M weld 30% Non conformities solving Diodes 67% DFBA consolidation in progress, DFBAO solution under study Ball test performed successfully! 01/11/13LSC - EN-MEF-OSS16 27L8 -bus-bars insulation

LHC - P8 LSS8 &P8 – TDI and MCBH removed – BPTX installation tbc – BTVST ready for surface bake-out next week – 2 nd MKI installed next week – Cable campaign ongoing (right side) – Survey with the duct ongoing – NEG activation of I5R8 in 2 weeks – UW maintenance just started R2E - P8 – Shielding installation in US85 in progress 01/11/13LSC - EN-MEF-OSS17 Survey duct P8 US85 shielding installation

LHC – arc 81 Arc 81 - SMACC -DFBA consolidation (ends end Nov.) -Splices activities -BB de-soldering completed -BB re-soldering in progress (44%  75%) -Shunt installation (27%  90%) -QRL compensator replaced and tested successfully ! 01/11/13LSC - EN-MEF-OSS18

Insulation boxes installation follow-up 01/11/13LSC - EN-MEF-OSS19 Courtesy - M. Pojer

Overall progress Injectors – Proposal of Rende being analyzed – Good progress of work LHC – Good progress, but ~3 wks delay SMACC Some co-activities with other activities to organize (optical fibers, electrical maintenance..) – Some issues Electron beam welding machine in AP; TCSP production delay Bus bar insulation boxes… 01/11/13LSC - EN-MEF-OSS20

LHC Overall Schedule – broken line 01/11/13LSC - EN-MEF-OSS21