Survey activities during LS1 Dominique Missiaen On behalf of the SU section.

Slides:



Advertisements
Similar presentations
K. Potter RADWG & RADMON Workshop 1 Dec WELCOME TO THE 4th RADWG & RADMON WORKSHOP 1 December 2004.
Advertisements

CERN IT Department CH-1211 Genève 23 Switzerland t Mobile services: Sunrise SWAP Rodrigo Sierra IT/CS.
Intervention Priority Management This talk will show the CERN priority list, the corresponding check list and the tools used by operators to diagnose a.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
THE ALIGNMENT OF THE LHC DURING THE SHUT-DOWN D. Missiaen.
H. MAINAUD DURAND, A. HERTY, A. MARIN, M. ACAR PERMANENT MONITORING OF THE LHC LOW BETA TRIPLETS: LATEST RESULTS AND PERSPECTIVES.
MEF - Machines & Experimental Facilities Technical Stop #4 29 th August - 2 nd September 2011 Summary Julie Coupard Schedule and Coordination LHC-TS4 -
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
ECFA Preparatory Group "Shutdown constraints and radiation and activation effects”. W. Zeuner, W. Riegler, R. Lindner, B. Di Girolamo, G. Corti, C. Schaeffer,
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
Machine Detector Interface for the HL (MDI) CERN, April 15, 2011 Austin Ball, Helmut Burkhardt, Marzio Nessi.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Alfa-Omega Team Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków.
Radiation Protection LS1 - Collaboration with CERN Technical Groups - Lessons learnt Stephane Bally (CERN), Sandro Di Vincenzo (CERN) Indico
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
LS2 Other LHC Experiments Mike Lamont Thanks to: Michael Rijssenbeek (AFP) Joachim Baechler (TOTEM) Karl-Heinz Hiller (ALFA)
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
June 1 rst, Consolidation for E-cloud and High Voltage cards N.Vauthier TE-CRG LS1 projects review:
6th ST workshop, Thoiry, 1-3 April ST-HM Design Section Strategy and working methods 3rd April 2003 C. Bertone ST-HM.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
SU ACTIVITIES PENDANT LS1 CMS ALICE. Antje Behrens | SU pendant LS1 day| | EDMS | page 2 CMS Quoi (quelles activités prévues pendant.
ECRs and ES for the LHC Last presentation on the 26 th of August 2015 (LMC 232) S. Chemli for EN-MEF-DC LMC xxx.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
STATUS REPORT: ALIGNMENT OF COLLIMATORS P. BESTMANN /O. ABERLE Collimation Working Group 26/09/2011.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Cooling & Ventilation feed-back M. Nonis – EN/CV.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
1 Safety and Database Subsection ADO - PO - SA Main safety projects / activities Main safety projects / activities RP issues RP issues Patrols Patrols.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
OLAV3 Engineering Integration and installation of experimental beam pipes: the case of LHC 7/8/20111P.Lepeule for VSC group.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
The integration of 420 m detectors into the LHC
SURVEY EXISTING TECHNIQUES AND REQUIREMENTS Jean-Christophe GAYDE, Pascal SAINVITU (CERN EN-MEF-SU-EM) Infrastructure For LHCb Upgrade Workshop February.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
TE-CRG Activities D. Delikaris, TE-CRG.
Roberto Saban TS HC Review bis Outline  Interviews of all the Group Leaders loosely or tightly concerned by hardware commissioning proposing them.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Managing the survey activities during the Long Shut-down 1 Dominique Missiaen D. Missiaen, Iwaa14, October 2014, IHEP, Beijing, China1.
D. Missiaen – 13/06/2014. D. Missiaen 13/06/ Agenda Introduction to alignment techniques Reserved space for Survey The CERN Co-ordinates System.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
Survey for SPL Dominique Missiaen BE-ABP/SU. Outline 12/11/2008 Dominique Missiaen BE-ABP-SU, Survey for SPL 2  Scope & Main Parameters  Technical Description.
EDMS N° V.1 TE-EPC Activities during LS1 V. Montabonnet [TE-EPC]
Remote Measurement and Alignment Applications for Survey and Alignment P. Bestmann for BE/ABP/SU
Warm Magnets - LS1 Feedback J. Bauche, on behalf of the TE-MSC-MNC Team.
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
ALIGNMENT OF THE NEW TRIPLETS
News and Introduction from CERN June 15th, 2005
ICE SECTION The coolest place to be! Elias Métral
Performance monitoring framework for the technical infrastructure
Equipment simplified model SMR UR safety
Francois and Lau EATM 17 July 2012
Installation of an Instrument on a CERN machine
Accelerator and Experiment Interface Session: LS2, LS3
MPE main activities planned for LS2
East Hall under construction
K. Foraz on behalf of OSS members
BLM planning 03/03/2014.
Review of hardware commissioning
Presentation transcript:

Survey activities during LS1 Dominique Missiaen On behalf of the SU section

Agenda D. Missiaen EN-MEF-SU2 A brief overview of all the activities done for the LS1and some results The strategy of SU during the LS1 Infrastructure support Issues What went well and what could be done better Resources Conclusions

SU activities D. Missiaen EN-MEF-SU3 In 2013 Injectors : PSB, PSR, TT2/FT16, SPS, TI2 LHC Fast levelling Smoothing of the LSS Alignment of the 18 exchanged cryo-magnets Low beta quads monitoring system : maintenance

SU activities D. Missiaen EN-MEF-SU4 In beginning 2015 Injectors : end of PSR and TI8, scans of PSR and PSB, SPS north area (6 lines completely measured and 2 realigned) LHC Alignment of the new/replaced components (collimators, Roman pots, BPMxx,..) Smoothing of the ARCS below 80k Low beta quads monitoring system : installation of the validation systems

SU activities D. Missiaen EN-MEF-SU5 Experiments LHC experiments : Survey infrastructure (upgrade of all geodetic networks and link to LHC geometry) Measurements during opening, maintenance and closure of the 4 LHC big detectors Installation of new detectors and related infrastructures Replacement of beam pipes Development and installation of monitoring systems (ATLAS ADEPO, LHCb IT Monitoring) Non LHC experiments NA62 installation, COMPASS Drell Yan, CAST, HIE-ISOLDE…

Strategy D. Missiaen EN-MEF-SU6 Estimation of the quantity of work gave us the number of needed staff Max 14 people from the SU contract 3 are based permanently at CERN and were trained since 2011 The 11 others arrived a couple of weeks before the start of LS1 and trained by the permanent ones 2 PJAS were paid by BE/EN and PH The experiments collaborations provided (as usual) support from several institutes 1 Temporary labour for mechanical installation ComplexCERN staff Extra staff needed LHC (C201) SPS25 (C201) PS13 (C201) Experiments61 (C201) 2 PJAS(Krakow) 2 (Atlas-DUBNA) 2 (CMS- wisconsin &Debrecen) 1 (LHCb -Gatchina) 1 (Alice) Maintenance low beta quads 31S107 Estimation of 2011

Access/Impact D. Missiaen EN-MEF-SU7 IMPACT No major problem but it is time consuming Sometime difficult to cope with the changing planning of the experiments : time to get the impact approved (2 days for ATLAS) ALICE and CMS -> Global IMPACT except for some areas MAD : Lost of time because are too sensitive Access sometimes difficult because of lifts breakdown and maintenance LHC Sectors patrolled too early => a lot of time lost in transport

ECRs/Layout database D. Missiaen EN-MEF-SU8 Availability of data in the Layout DB Perfect for the LHC For the SPS, will be OK at the end of LS1. A bit late ! ECRs some equipment installed in the triplets areas without any ECR

Safety D. Missiaen EN-MEF-SU9 Radiation : WDP LHC LSS7 : very good help from the RP team PSR, PSB : a bit heavy for the first time but useful for the future SPS (BA1, extraction areas, north area…) : avoidable unexpected events and circumstances were leading to higher doses than expected in the WDP Protection barriers/fences Some of them were NOT dismantled even if the work was finished for several weeks (TI2, TI8 and LHC)

Coordination/Planning D. Missiaen EN-MEF-SU10 Despite the coordination efforts, some coactivities were Very important in the LSS (time slots not respected by some others) Heavy for the ARCS : cohabitation with ELQA, HC, CSCM Shift work, a lot of time lost in transport Alignment of new components : at the end of ls1, the planning was tight, the pressure was enormous, the planning was changing almost every day Low beta quads planning was not so clear

Coordination/Planning (Experiments) D. Missiaen EN-MEF-SU11 Permanent co-activities in the experimental caverns Independant plannings for the 4 LHC experiments Frequent changes in the plannings, even at the last minute (SU must be flexible) in particular CMS due to very tight schedule Work charge not always smoothly distributed (peaks of dense activity) Unexpected tasks due to experiment technical constraints SU is in permanent contact with the Technical Coordination of each experiment (crucial)

Issues D. Missiaen EN-MEF-SU12 Ventilation problems which pertubates measurements Good reactivity of the CV team but in some cases the air current was still too important Adjustment/alignment systems to be improved for some equipments (collimators, roman pots) Degradation of some very fragile SU equipment in LHC Alert systems Low beta monitoring systems

Issues D. Missiaen EN-MEF-SU13 Each time we go in the tunnels we discover new obstacles : In the LHC new equipments installed in the reserved survey area (LHCb exp, BGV, etc) Some cables too close to fiducials «Cryo footbridges» In the PS Some line of sights are not accessible any more, they have to be re-established The action is already on going to solve it

Issues D. Missiaen EN-MEF-SU14 Responsability to be clearly re-defined in the triplets regions between SU and MSC concerning the supporting system (notches, etc) The fixation of the Q2s on the floor using strings

What worked well ? D. Missiaen EN-MEF-SU15 All the work foreseen was done and even more Due to the very good quality, flexibility and involvment of people Due to the training, procedures and tooling which were tested before Due to the detailed knowledge and prior acquired experience of the experimental areas by SU staff and collaboration support New instrumentation and software improvements : gain in time and precision, well adapted to experiment environment especially for ALARA rules

What could be improved ? D. Missiaen EN-MEF-SU16 For the arcs components smoothing : Could we measured during warm up and not during cool down ? Less coactivity ? Coud we measured at warm and not at cold ? A test should be done to validate this For experiments More accurate planning would help in some cases or particular periods More modern/automatic instrumentation

Ressources D. Missiaen EN-MEF-SU CERN staff/23.5 non staff (4.5/10 for experiments) Availability of experimental collaboration staff is mandatory All the non CERN staff has gone away 5 LD and 2 are retiring before LS2 ComplexCERN staff Non CERN staffcomments Accelerators811 C2011 staff spent a lof of time in planning mgt => 1 staff missing for office work Experiments4.53 C201 2 PJAS Krakow 2 Atlas - DUBNA 2 CMS - Wisconsin & Debrecen 1 Alice – Gatchina 0.2 LHCb Maintenance low beta quads+ alerts 32 FSU 0.3 PJAS Krakow 1 staff missing for field work Total15.5 (5LD) 23.5

Conclusions D. Missiaen EN-MEF-SU18 whatI - keepII - improveIII - change Safety : radiation WDP : very useful for future intervention The design of equipment in order to reduce the dose taken for a whole intervention and not team by team Access conditions Globally OKReduce IMPACT approval delay (ATLAS) MAD are a bit too sensitive Support received Coordination for the exchange of magnets in SPS Infrastructure Layout database availability for LHC Layout database to be up to date for SPS Planning/coordin ation Strong collaboration with the Technical Coordination of Experiments and with the LS1 coordination Planning in the caverns Planning dedicated for the triplets areas ? The coactivities were too important during the LHC LSS and Arcs smoothing Organisation of the SU works New instrument to save time in the Experimental caverns Survey reserved space have to be integrated and respected