Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group1 AB-CO MTTR & Spare Part Policy for the LHC Injectors, Experimental Areas & other Facilities.

Slides:



Advertisements
Similar presentations
AT Equ. Groups / AB-CO Control responsibility Sharing.
Advertisements

FESA 3 Implementation Status Stephane Deghaye BE/CO On behalf of the FESA team and many users.
WG on possible controls restructuring 1 Controls activities of the AB equipment groups A. Butterworth E. Carlier, R. Losito, A. Masi, JJ. Gras, Q. King.
Reliability Week 11 - Lecture 2. What do we mean by reliability? Correctness – system/application does what it has to do correctly. Availability – Be.
SYSchange for z/OS By Pristine Software April 2009 Thomas Phillips April 2009 SYSchange Pristine Software.
European Organization for Nuclear Research PLC services Jerónimo Ortolá, Jacky Brahy EN-ICE Workshop 23 April 2009.
Industrial Control Engineering Industrial Controls in the Injectors: "You (will) know that they are here" Hervé Milcent On behalf of EN/ICE IEFC workshop.
Isabelle Laugier, AT/VAC/ICM Section February 7 th 2008.
Accelerator Complex Controls Renovation, LHC Excluded Purpose and Scope M.Vanden Eynden on behalf of the AB/CO Group.
Overview of Data Management solutions for the Control and Operation of the CERN Accelerators Database Futures Workshop, CERN June 2011 Zory Zaharieva,
The TIMING System … …as used in the PS accelerators.
CERN IT Department CH-1211 Genève 23 Switzerland t Some Hints for “Best Practice” Regarding VO Boxes Running Critical Services and Real Use-cases.
E. Hatziangeli – LHC Beam Commissioning meeting - 17th March 2009.
Pierre Charrue – BE/CO.  Preamble  The LHC Controls Infrastructure  External Dependencies  Redundancies  Control Room Power Loss  Conclusion 6 March.
Controls renovation WorkshopFE Software 1 Front-end software C.H.Sicard.
06/05/2004AB/CO TC RF controls issues Brief overview & status Requested from AB/CO Hardware, Timing, VME/FESA for LEIR, SPS, LHC Controls for LHC RF Power.
Installation and Maintenance of Health IT Systems
14 December 2006 CO3 Data Management section Controls group Accelerator & Beams department Limits of Responsibilities in our Domains of Activities Ronny.
CERN Accelerators Topology Configuration and Change Management Engineering Department Thomas Birtwistle, Samy Chemli – EN/MEF/DC.
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
CERN Equipment Management Integrates Safety Aspects EDMS Doc Eva Sanchez-Corral Mena, Stephan Petit / CERN 1 CERN Equipment Management Integrates.
Christophe Mugnier, on behalf AB/PO Group ATC-ABOC days, 23 January 2008 AB/PO equipment review and Stand-by service description for the power converter.
Eugenia Hatziangeli Beams Department Controls Group CERN, Accelerators and Technology Sector E.Hatziangeli - CERN-Greece Industry day, Athens 31st March.
Draft for approval in ABMB, 4 Feb 08 Andy Butterworth Claude-Henri Sicard for the Controls Coordination Committee (CO3) 22 Jan 20081ATC/ABOC Days.
Application Development for Operations in the Coming Years Mike Lamont.
Wojciech Sliwinski BE/CO for the RBAC team 25/04/2013.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Nov, F. Di Maio, M.Vanden Eynden1 CO Proposal concerning AB Front-End Software Responsibilities First detailed proposal based on the global Front-end.
CERN Control Standards Front-End Computer Layer Stéphane Deghaye BE/CO/FE
Computing Facilities CERN IT Department CH-1211 Geneva 23 Switzerland t CF Automatic server registration and burn-in framework HEPIX’13 28.
BP & RS: BIS & SLP for AB/CO Review, 23 h Sept Realisation of the interlocking between SPS, LHC and CNGS and open issues Beam Interlock Systems.
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
LIU-PSB Configuration Management EDMS Documentation, Layout and ECRs Thomas Birtwistle EN-MEF-DC.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
High Availability Technologies for Tier2 Services June 16 th 2006 Tim Bell CERN IT/FIO/TSI.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
26 Jan 06Marine Pace - AB/CO1 LEIR Controls : Gain of Experience for the Running-in of LHC Marine Pace on behalf of AB/CO and LSA.
AT Control Forum First Meeting. Introduction  The AT Controls FORUM :  Is responsible for coordination of the overall strategy for controls activities.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
LS1 Review P.Charrue. Audio/Video infrastructure LS1 saw the replacement of BI and RF analog to digital video transport Was organised in close collaboration.
The ACCOR Project Status Report and Outlook for 2010 and beyond M.Vanden Eynden on behalf of the ACCOR Project Team 1M.Vanden Eynden (BE/CO) - IEFC Workshop,
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
DIAMON Project Project Definition and Specifications Based on input from the AB/CO Section leaders.
22/09/05CO Review: FESA IssuesJJ Gras [AB-BDI-SW] 1/18 AB-CO Review FESA  The Functionality  The Tools  The Documentation  The Support  Maintenance.
Standby Services or Reliance on Experts for Accelerator control? Claude-Henri Sicard AB/CO ATC/ABOC Days 2007.
LHC Section Meeting 1.eLogbook 2.LHC Controls Security Panel.
– Machine Controls Coordinators (MCC): team and role – Overview of renovations during LS1 – Proposal for after-LS1 Commissioning organization ACCOR PROJECT.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
Agenda 1 BOSS Meeting - 27/5/ : :10 Introduction and aims of the workshop 10‘ 09: :25 Priorities from OP for PSB and transfer lines 15'
The OP Viewpoint on the Accelerator Complex Controls Renovation R. Steerenberg on behalf of the OP group Accelerator Complex Controls Renovation Workshop.
© 2001 By Default! A Free sample background from Slide 1 Controls for LEIR AB/CO Technical Committee - 18 th March 2004.
Radio Frequency Andy Butterworth AB/RF Accelerator Controls Renovation WS 3 Dec 2008.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
AB-CO Exploitation 2006 & Beyond Presented at AB/CO Review 20Sept05 C.H.Sicard (based on the work of Exploitation WG)
What means QA for PLC Programming Philippe Gayet ATC/ABOC Days.
AB-CO Review Controls for BDI
V4.
Accelerator Controls Renovation Project “ACCOR”
Status and Plans for InCA
Looking back on 2014 and Perspectives for the MPE Group in 2015
Castor services at the Tier-0
Installations, modifications, consolidation in 2005:
Olof Bärring LCG-LHCC Review, 22nd September 2008
Renovation of the Accelerators Controls Infrastructure and its Assets Management Asset and Maintenance Management Workshop November 14th, 2013 Cl.Dehavay.
the CERN Electrical network protection system
Experience with an IT Asset Management System
Presentation transcript:

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group1 AB-CO MTTR & Spare Part Policy for the LHC Injectors, Experimental Areas & other Facilities ATC-ABOC Days Jan 23rd, 2008

M.Vanden Eynden on behalf of the AB-CO Group2 Agenda Injector Complex Controls Infrastructure –What is coming up? –Today’s reality CO Majors Components –Inventory –Spare Parts Policy –MTTR –Specific Risks CO First line Support Conclusions

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group3 Agenda Injector Complex Controls Infrastructure –What is coming up? –Today’s reality CO Majors Components –Inventory –Spare Parts Policy –MTTR –Specific Risks CO First line Support Conclusions

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group4 WHAT IS COMING UP? Controls infrastructure model and practices used for LHC will progressively be applied to the injector complex –CO provides core hardware and software components Front-end, back-end and console platforms with O/S Standard collection of hardware modules FESA RT software framework –Equipment groups rely on AB-CO for the procurement and installation of hardware components and FESA framework for their specific developments (BI, BT, RF) –For some systems, CO has full responsibility for the installation and operational support of complete control solutions (LHC WorldFIP for PO and QPS, Machine protection, Cryogenics, etc)

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group5 WHAT IS COMING UP? Consequences –We move, for all machines, towards a unique and coherent model of shared responsibilities between Eq.Groups and CO (prepared at CO3, under ABMB approval) –CO involvement for SPS will increase FESA as RT software framework Layout and asset management DBs Front-end Hardware renovation –EQ.Groups involvement at PS front-end level will increase Progressive re-engineering of GM classes Development and deployment of FESA classes CO still in charge of > 40 FESA classes over a total of 125

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group6 TODAY’S REALITY PS complex CO group is still in charge of almost all front-end hardware and software systems CO « piquet service » as first line support to OP SPS Lighter HW and SW involvement of CO compared to PS CO list of experts, best effort In general for all injectors Hardware obsolescence is a concern and must be addressed Poor layout and asset management compared to LHC Large Initiatives will be taken by CO already in 2008 in order to deploy new FE solutions from 2009 onwards

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group7 Agenda Injector Complex Controls Infrastructure –What is coming up? –Today’s reality CO Majors Components –Inventory –Spare Parts Policy –MTTR –Specific Risks CO First line Support Conclusions

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group8 MAJOR COMPONENTS Front-end Systems Machine Timing System PLCs File and Application Servers On-line Databases Operator Consoles Machine Interlocks Application Software For each layer : Inventory, Spare Policy, MTTR, Risks

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group9 MAJOR COMPONENTS Front-ends –Inventory 800 operational diskless FE systems for the entire Accelerator complex: –LHC : 380 (185 VME, 185 Industrial PC, 10 cPCI) –SPS : 190 –PS Complex : 220 Hardware Components: –VME and cPCI complete systems (crates, CPU, etc) –Industrial PCs (2U crate + motherboard) –AB-CO “Standard LEGO” of about 50 VME and PCI modules »Timing receiver modules (CTR-x) »DAC and ADCs, Scopes, Function generators, etc

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group10 MAJOR COMPONENTS Front-ends –Inventory Software Components –About 125 different Equipment classes written in GM –GM to FESA adaptor for new FE upgrades ABP1 ATB12 BI32 BT3 CO44 OP3 PO7 RF16 AT-VAC7 Total125

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group11 MAJOR COMPONENTS Front-ends –Spare Parts Policy 10% of installed volume –MTTR Hardware –All hardware components can easily be replaced in case of failure –PS complex: Guaranteed “CO piquet” –SPS: list of experts, best effort Software –MTTR depends on nature of the problem »Software configuration problems can be fixed by piquet »Specific GM problems handled during normal working hours (very few remaining experts today!) »FESA : dedicated support line during normal working hours –CO in charge of ONLY the corrective maintenance of all 125 GM classes, until these will be re-written in FESA

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group12 MAJOR COMPONENTS Front-ends –Specific Risks Several components are reaching their end of life time –VME processors and crates (Wes) > 10 years old –Out of stock for some Obsolete HW modules (GFAs, MIL- 1553, …) CO has taken the following actions –Annual preventive maintenance of FE systems –Re-engineering of Obsolete core hardware modules such as GFAs, MIL-1553 (mid-2008) –Upgrade of some operational systems with new HW modules in order to re-establish spare parts for obsolete modules –Bulk orders for new VME crates (mid-2008) –Major on-going market surveys for »New generation of VME CPUs running Linux (mid-2008) »New generation of Industrial PCs (PICMG 1.3) as a more cost-effective platform (mid-2008) that will replace VME when appropriate

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group13 MAJOR COMPONENTS General Machine Timing (GMT) (1) ‏ –Inventory VME MTGs Cluster in the CCR –Three central timing systems: LHC, the LHC Injector chain (LIC), and the CTF. (LN4 is coming) ‏ –The LHC and LIC central timing systems have a hot backup that can be switched between in case of failure or maintenance Long distance fibre (SM) distribution from CCR towards SPS surface buildings and Meyrin site Local Copper distribution (repeaters, fan outs) ‏ Timing receiver modules in almost every front-end machine (PMC, PCI and VME form factors). There are still many (~150) TG8 modules used especially in the PS complex.

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group14 MAJOR COMPONENTS General Machine Timing (GMT) (2) ‏ –Spare Parts Policy 10% of installed volume –MTTR List of experts, best effort Hardware failures can be solved quickly Potential Software problems with MTGs managed by HT section –Specific Risks Availability of timing experts outside working hours Timing team members can not always replace each other –Documented procedures related to specific failure scenarios will be put in place this shut-down to reduce dependencies on experts as much as possible.

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group15 MAJOR COMPONENTS PLCs –Inventory 2 main suppliers (Schneider & Siemens) 300 References for more than assets for entire CERN ALL components are COTS and can be procured in 2 to 4 weeks Obsolescence survey will be reinforced –Spare Policy each equipment group responsible for his PLCs CO has spares components for Cryogenics, PIC, WIC, Collimators However AB-CO is currently organising a central spare policy under the authority of the GUAPI (PLC users group) –One central store at CERN for critical components, for all PLC users (Cf LTC 16) –accessible 24/24 to all PLC users –One store at each supplier premises with a delivery delay of 24 hours max –All spares existing at CERN will be Inventoried in D7i (MTF) and a discussion will start on how we (the CERN plc users) will manage them. –Target Q –MTTR Hardware failures can be solved quickly, and the components will be available –Specific Risks To avoid the loss of application software a new software repository system in being installed

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group16 MAJOR COMPONENTS File and Application Servers –Inventory 150 Proliant machines installed in CCR Used for Cryogenics, LSA, NFS storage, Front-end Boot server, Logging, Fixed Displays, etc Extreme care has been taken for these servers to ensure the lowest downtime –Redundant power supply from 2 different power sources –Redundant Raid 1+0 disk with hot swap capabilities –ECC memory used and intelligent memory controller with online memory disable function –Spare Policy Each type (G3, G4, G5) has 1 fully equipped running spare in the CCR. Spare Disk, Fans, Power Supplies also available in the CCR –MTTR List of experts, best effort In case of complete failure of one server, the hot spare will be renamed to the broken one, with automatic installation of the software packages needed and automatic restart of the services. In addition, local private backups (in addition to the IT central one) allow to recover quickly from a major disk failure

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group17 MAJOR COMPONENTS Operator Consoles –Inventory Standard PCs and 19” TFT screens Running WinXP or Linux SLC4 100 deployed in the CCC and 140 deployed in the CERN technical buildings These consoles are NOT critical for operation –MTTR CO has spare PCs and Screens The re-installation of one console is automatic –Specific Risks N/A

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group18 Interlock Systems LHC & Transfer Lines Injector Complex PIC 36 syst. protecting ~800 LHC electrical circuits None WIC 8 systems protecting ~150 magnets 5 systems protecting ~800 magnets LEIR: 1 system & ~50 magnets BIC 17 systems & ~200 User Permit connections 12 systems & ~100 User Permits connections SPS ring: 6 systems & ~30 User Permits FMCM 12 and 14 units none –Spare Policy 10% of installed volume –MTTR List of Experts, best effort –Specific Risks N/A MAJOR COMPONENTS

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group19 MAJOR COMPONENTS On-Line Databases (Cf session 4 - T.Smith) –Inventory Settings “LSA” database – for SPS, TLs, LEIR... and LHC Controls configuration database – controls system topology Measurement database – short term read-back data Logging database – long term archived data Hosted and monitored by IT in Bldg 513 Major IT efforts towards better resilience (RAC, March 2008) –Spare Policy, MTTR and Support IT-DES : see ATC-ABCO session 4 - T.Smith IT can only propose best effort –Specific Risks Unavailability of the LSA database makes it impossible for the operator to act on accelerator parameters S.Myers -> Risk Analysis proposal

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group20 MAJOR COMPONENTS Application Software (Cf session 3, E.Hatziangeli) –Inventory All generic X-Motif and Java application programs (knobs, working sets, Automatic Beam Steering, …) General services : LASER, Passerelle, … –MTTR and Support Operational problems fixed by list of CO/AP experts Generic X-Motif applications: CO ensures ONLY corrective maintenance until the introduction of INCA by end 2009,10 Generic Java applications: many improvements ready for 2008 start-up. CO will introduce only high priority modification requests –Specific Risks N/A

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group21 Agenda Injector Complex Controls Infrastructure –What is coming up? –Today’s reality CO Majors Components –Inventory –Spare Parts Policy –MTTR –Specific Risks CO First line Support Conclusions

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group22 Organization –Team of 5 to 6 technicians –Each member on service during one week –Callable by CCC Operation 24/24 during accelerator run (~ 32 weeks) –Applies to ‘standard CO’ controls (hardware/software), mostly Front-end –Manages spare parts –Tracing: E-logbook, Follow-ups CO FIRST-LINE SUPPORT

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group23 Scope –Piquet called by OP for: PS Complex (Lin2, PSB, CPS, Lin3, LEIR, Isolde, AD) CTF3 –For SPS and North area, OP SPS team uses expert call list CO FIRST-LINE SUPPORT

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group24 Proper Functioning –Training: Basic skills, knowledge of geographical, technical details –Regular information from CO sections (SW or HW updates, new installations, planned interruptions) –Weekly Contact with Operations team (planned changes, follow-ups) CO FIRST-LINE SUPPORT

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group25 Domain of Intervention –Quality assurance: ensure new systems put in exploitation are correctly delivered (files, startup) configured and documented. –Diagnostic: identify causes of failure within the different layers of control system –Procedures: non-destructive resets, setting-ups –Hardware interventions: identify and replace failing components, re-initialize systems (front-ends, HW modules, timing distribution, MIL-1553, etc) –Software: Restoring operational data, correct configuration of front-end equipments or generic applications, FE startup sequences CO FIRST-LINE SUPPORT

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group26 CO FIRST-LINE SUPPORT

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group27 (2007 not yet detailed, has similar figures) Yearly total (registered): 268 –HW 111 –SW 133 –External 15 Outside working hours*: 35 –Total Duration (h) 53 –Mean duration (h) 1h30 Requiring follow-up: 67 * not counting issues solved by phone/rlogin CO FIRST-LINE SUPPORT

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group28 Agenda Injector Complex Controls Infrastructure –What is coming up? –Today’s reality CO Majors Components –Inventory –Spare Parts Policy –MTTR –Specific Risks CO First line Support Conclusions

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group29 CONCLUSIONS Spare Policy –available today for all CO hardware components, with sufficient margins –CERN wide spare policy for PLCs due for Q Hardware Obsolescence –On-going program for the re-engineering of obsolete hardware modules –New contracts for AB (Q2 2008) for the medium term procurement of new Front-end platforms (VME, Industrial PCs) Front-End (GM) and Application (X-Motif) Software –Will remain as is, with CO corrective actions when required, no new developments

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group30 CONCLUSIONS First Line Support –We still inherit from the situation prior to the AB restructuration PS complex : CO piquet (guaranteed response time) maintained in 2008 SPS : list of experts, best effort LHC : list of experts, best effort –CO piquet act as first line for the PS complex –CO piquet can diagnose problems BUT has real intervention “competence” on the front-end layer ONLY –For other systems, the “expert” intervention is mandatory to fix the problem (back-ends, timing, AP software, DBs, …) –As proposed by CO3 : the question of first-line support should be agreed at the ABMB level, in particular the expected guaranteed response time in case of blocking problem for the overall LHC injection chain?

Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group31 CONCLUSIONS 2009 and beyond –Injector renovation project will align the injector controls infrastructure and limits of responsibility to the ones used for the LHC machine (CO3 proposal) –CO is actively developing the core building blocks in 2008 (New Front-end platforms, FESA 3.0, INCA)