TPC Collaboration Meeting 2-3.9.02Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental.

Slides:



Advertisements
Similar presentations
SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Advertisements

Lau Gatignon, EATM, 7 October  The T9 and T10 lines have been running smoothly from mid July and the T11 beam started up very smoothly for CLOUD.
The CERN-JINR Collaboration J. Engelen March 27, 2006.
Centauro and STrange Object Research (CASTOR) - A specialized detector system dedicated to the search for Centauros and Strangelets in the baryon dense,
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
1 MOSFIRE is a Multi-Object Spectrometer for the Near Infra-Red (wavelengths ~ μm) We are deep in the component fabrication and procurement phase.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
TB Peter Glässel, Heidelberg1 TPC Status.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
ACORDE FOR TPC TEST Status report. Top Modules Bottom Modules.
LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Construction and Installation of the CLIC Experimental Area
Hans-Åke GustafssonLHCC review January 31, ALICE meets LHCC referees 31/01/ :00  Milestones report H-A Gustafsson  FMD questions H. Boggild.
Experimental hall in Japanese mountain site Y. Sugimoto 1.
TB Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
1 Responsibilities & Planning DCS WS L.Jirdén.
Q&A on T2K construction of beam line near detectors budget collaboration (contribution from each) T2KK.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
The Construction of the LHC Detector Gas Systems ? Ferdi Hahn PH-TA1-GS Detector Steering Meeting 4th of June 2004.
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
1 CERN related research program in Nuclear Physics High energy nuclear physics –ALICE experiment »Installation and Commissioning »Data taking.
Forum March 2003H.Taureg1 Magnetic Fields in ALICE Mapping and Monitoring.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
1 BDS and Detector schedules for discussion at MDI meeting August 15, 2006 Andrei Seryi with input from Martin Gastal, Yasuhiro Sugimoto et al.
ILD Magnet & calorimeters integration meeting Questions to be addressed 01-02
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
The ALICE Experiment at the CERN LHC P. Kuijer for the Alice collaboration ICHEP 2002.
ILD requirement for assembly space and time 2015/11/3 Yasuhiro 1.
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
UPDATE ON ID INTEGRATION Alice TB, E.Rosso ALICE TECHNICAL BOARD CERN, Ettore Rosso / CERN 1. 3 rd Cone 2. V0_L and Si_3 support 3.
Technical FORUM, Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,
ALICE Arturo Tauro Werner Riegler.
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
Construction Schedule for Baseline and Hybrid A’ Configuration 1 5 th September, 2014 J-POWER MDI-CFS Meeting - Ichinoseki City, JAPAN.
TB Peter Glässel, Heidelberg1 Preparing TPC Installation.
28 April th ALICE RRB J. Schukraft 16th ALICE RRB Collaboration Status Project Status  Integration, large structures  Detectors (selection) 
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
Status of TTF3 Coupler Assembly Program November 26, 2007 Jeff Tice.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview.
ELENA installation progress F. Butin / ELENA collaboration.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
ALICE 5 o’clock meeting Wk 51.
EHN1 Extension planning
The LHCb Installation Story
ALICE Status 4th CERN-Korea meeting
LHC Experimental Vacuum Systems Status October ‘07
ALICE 5 o’clock meeting Wk
Update of experimental hall in Japanese mountain site
The SABRE Crystals Frank Calaprice.
SuperB Experimental Hall
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
Baby-MIND for T2K collaboration
ALICE 5 o’clock meeting Wk
Technical Support Activities in PH-ADO-PO
Presentation transcript:

TPC Collaboration Meeting Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental hall in temporary position No pre-installation of magnet, absorber, Muon filter, Muon chambers in SXL2  Assembly of absorber at Point 2 Assembly line in SX2 – if agreement with Sarov  No displacement of TPC and clean-room Keep clean room in SXL2  Installation of TPC / ITS / Vacuum chamber This installation has a duration of 6 months and is regarded as a block We assume that no other activity can proceed in parallel  TDR / TOF / PHOS have two installation periods Period 1: Before TPC/ITS/Va Period 2: After the installation of TPC/ITS/Va (Vacuum chamber in place)

TPC Collaboration Meeting Peter Glassel 2 Installation Phases  Phase 1 now – Large structures for Muon arm  Phase – TRD/TOF/PHOS/HMPID  Phase – TPC/ITS/Vacuum  Phase – Commissioning PMD and FMD, V0, T0, Si3 on RB24 side Last TOF modules Shielding / machine interface / close L3 magnet etc

TPC Collaboration Meeting Peter Glassel 3 Installation of detectors into space-frame  Installation shaft 7 x 15 m2  Working position outside the magnet  Installation in the space-frame 1 st Period; outside / inside the L3 magnet 2 nd Period; after TPC/ITS/Va installation

TPC Collaboration Meeting Peter Glassel 4 Installation mile stones  Close L3 magnet back door Best guess to-day is beginning of 2004  Installation of space-frame In the new planning the space-frame is moved from SXL2 and installed in the experimental area in June 2005 I.e. pre-installation testing in SXL2, involving the space-frame, must end at this date