K.Honkavaara, LCLS ICW06 LCLS Injector Commissioning Workshop, SLAC, October 9-11, 2006 Linac Experience at FLASH Katja Honkavaara University of Hamburg.

Slides:



Advertisements
Similar presentations
Commissioning August & September. 2 Agenda 11:20 Coffee 11:30 Introduction Sue S 11:35 Controls (an overview) Brian M 10:55 Controls & Data Acquisition.
Advertisements

E. Schneidmiller and M. Yurkov (SASE & MCP) C. Behrens, W. Decking, H. Delsim, T. Limberg, R. Kammering (rf & LOLA) N. Guerassimova and R. Treusch (PGM.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
P. Emma, SLACLCLS Commissioning – Sep. 22, 2004 Linac Commissioning P. Emma LCLS Commissioning Workshop, SLAC Sep , 2004 LCLS.
P. Emma, SLACLCLS FAC Meeting - April 29, 2004 Linac Physics, Diagnostics, and Commissioning Strategy P. Emma LCLS FAC Meeting April 29, 2004 LCLS.
RF Systems and Stability Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
R. Corsini, CLIC Project Meeting - 24 th May 2013 CTF3 1 CTF3: Highlights of the 1 st run R. Corsini for the CTF3 Team 1.
FEL Beam Dynami cs FEL Beam Dynamics T. Limberg FEL driver linac operation with very short electron bunches.
BPMs and HOM-BPMs for the XFEL Linac N. Baboi for the BPM and the HOM teams (DESY, CEA-Saclay, SLAC, FNAL, Cockroft/Daresbury) XFEL Linac Review Meeting,
Influence of the Third Harmonic Module on the Beam Size Maria Kuhn University of Hamburg Bachelor Thesis Presentation.
Low Emittance RF Gun Developments for PAL-XFEL
TTF-II Status & Prospectives Nick Walker DESY 5 th ITRP Meeting – CALTECH.
~ gun3.9 GHz cavity Bunch compressor 3 ILC cryomodules 45 deg. spectro injector main linac user area disp. area transport line Overview of.
SPPS, Beam stability and pulse-to-pulse jitter Patrick Krejcik For the SPPS collaboration Zeuthen Workshop on Start-to-End Simulations of X-ray FEL’s August.
Recent Experiments at PITZ ICFA Future Light Sources Sub-Panel Mini Workshop on Start-to-End Simulations of X-RAY FELs August 18-22, 2003 at DESY-Zeuthen,
FLASH Operation at DESY From a Test Accelerator to a User Facility Michael Bieler FLASH Operation at DESY WAO2012, SLAC, Aug. 8, 2012.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
R. Corsini, CLIC Project Meeting October 24, 2012 CTF3 Experimental program for end 2012 R. Corsini for the CTF3 Team 1.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
Electron Source Configuration Axel Brachmann - SLAC - Jan , KEK GDE meeting International Linear Collider at Stanford Linear Accelerator Center.
FLASH. Free-Electron Laser in Hamburg Lessons from FLASH FLASH Upgrade FLASH II Lessons Siegfried Schreiber DESY FLS 2010 SLAC 1-6 March 2010.
FLASH II. The results from FLASH II tests Sven Ackermann FEL seminar Hamburg, April 23 th, 2013.
DESY / Hans Weise TTF / VUV-FEL Status and Some Words of Fast Kickers Hans Weise / DESY DESY meeting with KEK ILC Delegation (March 7th 2005)
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Bruno Muratori (for the EMMA team) STFC, Daresbury Laboratory EMMA commissioning 02/09/08.
Max Cornacchia, SLAC LCLS Project Overview BESAC, Feb , 2001 LCLS Project Overview What is the LCLS ? Transition from 3 rd generation light sources.
Y. R. Roblin Hall A beamline and accelerator status.
John Carwardine 20 April 09 Preliminary planning for Aug/Sept studies.
P. Urschütz - CTF3 Collaboration Meeting 2007 CTF3 commissioning & operation in 2006 P. Urschütz for the CTF3 operations team  Commissioning of the Delay.
Simulations - Beam dynamics in low emittance transport (LET: From the exit of Damping Ring) K. Kubo
DaMon: a resonator to observe bunch charge/length and dark current. > Principle of detecting weakly charged bunches > Setup of resonator and electronics.
John Carwardine January 16, 2009 Some results and data from January studies.
First Electrons at the Fermilab superconducting test accelerator Elvin Harms Asian Linear Collider Workshop 2015, Tsukuba 24 April 2015.
Instrumentation at ATF / TTF Accelerator Test Facility (KEK) Tesla Test Facility – FLASH (DESY) ESA / LCLS (SLAC) Marc Ross, SLAC.
Experience with Novosibirsk FEL Getmanov Yaroslav Budker INP, Russia Dec. 2012, Berlin, Germany Unwanted Beam Workshop.
ApEx needs for CeC PoP Experiment December 11, 2015.
What did we learn from TTF1 FEL? P. Castro (DESY).
Operational experience and recent results from FLASH (VUV FEL at DESY) E. Saldin, E. Schneidmiller and M. Yurkov for FLASH team Milestones Parameters of.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
ESLS Workshop Nov 2015 MAX IV 3 GeV Ring Commissioning Pedro F. Tavares & Åke Andersson, on behalf of the whole MAX IV team.
Beam Commissioning Adam Bartnik.
E-XFEL Status and First Beam Results
LLRF'15 Workshop, Shanghai, Nov. 4, 2015
Slice Parameter Measurements at the SwissFEL Injector Test Facility
Auxiliary Positron Source
Notes on Machine Protection for long bunch trains
Longitudinal Diagnostics for start-up
Accelerator Layout and Parameters
Revised Commissioning Strategy
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
LINAC4 commissioning plans etc.
What did we learn from TTF1 FEL?
Electron Source Configuration
Diagnostics overview and FB for the XFEL bunch compressors
Injector: What is needed to improve the beam quality?
Advanced Research Electron Accelerator Laboratory
FEL-Beam-Dynamics Group
Linac/BC1 Commissioning P
Linac (WBS 1.2.2) Vinod Bharadwaj April 23, 2002
LCLS Commissioning P. Emma, et al
CLIC Feasibility Demonstration at CTF3
Maximum Credible Beam Event Paul Emma et al
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
First results of micro-bunching and COTR experiments at FLASH
Linac Diagnostics Commissioning Experience
LCLS Injector Commissioning P
European XFEL Status Winni Decking, DESY
Bunch Compressor Beam Line Optics
Presentation transcript:

K.Honkavaara, LCLS ICW06 LCLS Injector Commissioning Workshop, SLAC, October 9-11, 2006 Linac Experience at FLASH Katja Honkavaara University of Hamburg and DESY Linac commissioning Operation as a user facility Some selected topics

K.Honkavaara, LCLS ICW06 Present layout of FLASH Linac 250 m bypass5 MeV127 MeV370 MeV Bunch Compressor Undulators Collimator Bunch Compressor Accelerating StructuresDiagnostics FEL diagnostics 400…730 MeV

K.Honkavaara, LCLS ICW06 Linac commissioning strategy Injector commissioning run February-May, 2004 Summer 2004 –Installations in tunnel finished (modules, waveguides, vacuum, magnets, diagnostics, cabling) –Conditioning of modules (couplers) Experience of module conditioning and operation already from TTF1 –Commissioning of klystrons and modulators Commissioning of the linac sector by sector as soon as a sector is ready for beam operation (modules, magnets); commissioning of other sectors continued parallel –RF-gun: 1-Sep-2004 → –Injector (ACC1+BC): 6-Oct-2004 → –Beamline up to collimator: 15-Oct-2004 → –By-pass line: 22-Oct-2004 → –FEL beam line: 1-Dec-2004 →

K.Honkavaara, LCLS ICW06 Linac commissioning steps First beam to dump via by-pass 31-Oct-2005 Adjustments LLRF (phases, gradients, feedback) Magnets (polarity, optics) Commission diagnostics (toroids, screens+cameras, BPMs, loss monitors) Adjustments and optimization Beam parameters Beam optics and transport Diagnostics LLRF Stability SASE First beam through ACC2/3 15-Oct-2004 First SASE 14–Jan-2005 First beam through ACC4/5 25-Oct-2004 First beam through collimator 3-Dec-2004 First beam through undulator 13-Dec-2004 Start of linac operation 1-Sep-2004 First user experiments June 2005 Injector commissioning Feb-May, 2004 Beam operation Gun section Injector Commissioning Modules (cavities, couplers) Cryo measurements Klystrons + Modulators Magnets Operation SASE delivery Change of photon wavelengths Long bunch trains Bunch train pattern User facility

K.Honkavaara, LCLS ICW06 Restart RF-gun and establish beam in gun section Beam based solenoid and laser beam alignment using a camera in the diagnostics cross LLRF adjustments of RF-gun Stability measurements (charge, energy) Momentum and dark current measurements Conditioning of ACC1 cavity 7 Piezo-tuner studies ACC1 Dark current studies ACC5 Cryo measurements LLRF preparation for modules Commissioning magnet power supplies along the linac 6-Oct-2004 → Beam operation in injector (up to ACC2) ACC1 with unbalanced gradients: 4 first cavities ~12 MV/m, 4 last ~20 MV/m Commissioning of magnet controls (cycling, control by DOOCS) and diagnostics (toroids, BPMs, BLMs, camera system) Start of linac commissioning, Sep-Oct-2004 Beam operation in injector

K.Honkavaara, LCLS ICW06 First beam through ACC2/3 ACC2/3: Adjustment of cavity phases, gradient and phase calibration, LLRF adjustments Polarity of magnets Calculated nominal optics taken a start point for quadrupole settings; empirical fine tuning First unaccelerated beam through ACC2/3, October First beam at entrance of ACC4, chicane off, October-16, 2004, Screen 5DBC3 Screen 3UBC3 First accelerated beam through ACC2/3, October nd bunch compressor = BC3 Screen 3UBC3

K.Honkavaara, LCLS ICW06 Beam through the 2 nd bunch compressor Screen 11BC3Screen 5DBC3 First beam through BC3 chicane, October-21, 2004 Typical beam images before and after BC3 in SASE operation Screen 3UBC3 Screen 5DBC3 2 nd bunch compressor (BC3) is S-shape chicane OTR screen in second dispersive section of the chicane to measure energy and adjust on-crest phase of ACC2/3 –No on-line monitoring of energy and phase Screen 3UBC3 Screen 11UBC3 Screen 5DBC3

K.Honkavaara, LCLS ICW06 First beam to dump via by-pass ACC4/5: Adjustment of cavity phases, gradient and phase calibration, LLRF adjustments, tuning cavities ACC5 ACC4/5 operated with low gradient (~ 5 MV/m) corresponding to total beam energy of 450 MeV –First lasing planned with wavelength of 32 nm Calculated nominal optics taken as a start point for quadrupole settings Difficult to achieve full transmission to the dump: polarity of several quads were wrong Optics of by-pass line still not fully understood; presently by-pass only rarely used, and therefore we have not put much effort to improve situation First beam up to collimator, October-25, 2004 First beam up to dump via by-pass, October-31, 2004

K.Honkavaara, LCLS ICW06 First beam downstream of collimator FEL beam line ready for beam operation Dec Calculated nominal optics taken as a start point for quadrupole settings, empirical adjustments required First beam through collimator dogleg (collimators open) up to undulator entrance relatively easy But no transmission through undulator Collimator Energy collimator dipole Collimators with adjustable gap: 4 mm, 6 mm, 12 mm, or open (30 mm) Dipoles for energy collimation First beam through collimator Dec-3, 2004 Screens between collimator and undulator

K.Honkavaara, LCLS ICW06 First beam through undulator to dump Several trials to get beam through undulator without success –Complication: losses in undulator have to be kept small Reason identified by manual check of all quadrupoles in/upstream undulator: –Two quadrupoles upstream undulator had a wrong calibration by a factor of 3.6, one had a short –Quadrupole in diagnostics block downstream first undulator module horizontally moved out of nominal position by 2 mm; micromover was not mechanically fixed After fixing: beam through undulator quickly → start of photon diagnostics commissioning and SASE search First beam through undulator to dump, Dec-13, 2004 Screen 12EXP, downstream of undulator Quadrupole doublet between undulator modules. Fine adjustment of quad position using a micromovers (hor & vert)

K.Honkavaara, LCLS ICW06 First lasing (32 nm) Over Christmas 2004 we had 2.5 weeks break in operation Jan → –Start-up + beam in by-pass –LLRF adjustments Jan → –Set-up beam in FEL mode First lasing: Jan First lasing: January-14, 2005

K.Honkavaara, LCLS ICW06 September - December, 2004 Lot of studies and commissioning done during autumn 2004 parallel to establishment of beam operation through the linac Commissioning of diagnostics tools (hardware and software) –Camera system –Emittance measurement and matching in injector –BPM –Transverse deflecting cavity LOLA –Diagnostics using coherent radiation –Beam loss monitor system LLRF adjustments and developments HOM measurements Magnets: cycling, integration to DOOCS

K.Honkavaara, LCLS ICW06 After first lasing: January – June 2005 Beam time shared between –SASE search and characterization –Diagnostics commissioning (BPMs, coherent radiation diagnostics, camera system, toroids, beam loss monitor system, phase monitors, LOLA) –Beam optics, transportation, optimization (transverse emittance in injector, beam based alignment linac/undulator, dispersion, …) –Noise and stability studies, correlations –LLRF adjustments and developments –HOM measurements Typically every shift has a different program –Disadvantage: machine settings often different from shift to shift –But: since lot of commissioning was still on-going, program of a shift often determined by availability of experts May 2005 → well defined blocks for different studies and SASE optimization –Clear improvement of SASE performance

K.Honkavaara, LCLS ICW06 User Facility FLASH is a user facility since August 2005 Blocks for user experiments and machine/FEL studies clearly separated: –2-3 weeks blocks dedicated for FEL studies (machine improvements related to FLASH operation, preparation of a user run) are followed by –4-5 weeks block of users experiments: stable SASE radiation delivery –2-3 times per year a block of 2-4 weeks dedicated to accelerator studies, priority tor further developments (e.g for XFEL and ILC) –1 maintenace shift per week, longer maintenance periods 2-3 times per year User 39% FEL studies 37% Accel. studies 17% Off 7% (Maintenance) SASE beam for users 69% Down 8% Off 4% Tuning 18% Statistics of user runs in Spring/Summer 2006 (7 weeks) Scheduled distribution of beam time in Spring/Summer weeks, 7days/week, 24h/day

K.Honkavaara, LCLS ICW06 Downtime statistics 2006 Trendline (8 weeks average) Maintenance Users FEL study Accel. study

K.Honkavaara, LCLS ICW06 Machine improvement continues Improvements, especially in stability, diagnostics and understanding of beam orbit and optics continues parallel with user runs, typically during FEL study periods Stability –Injection: stability of laser profile, alignment injector section –LLRF: feedbacks and stability New FPGA based hardware with improved precision installed for RF-gun and ACC1 Stabilization of ambient temperatures –Slow feedbacks: orbit, phase, and charge –Improved procedures to obtain and maintain good SASE radiation –Investigation and fixing external noise sources (EMI) Orbit, optics, beam dynamics –Measurements of transfer functions: led to a much better understanding of optics and gave a push in BPM improvements –Dispersion measured and partially corrected –Low beta function optics tested with success: 13 nm lasing achieved within 4 h –Beam based alignment undulator section ongoing, BPM resolution now sufficient –Understanding non-linear beam dynamics started –Emittance measurements continue

K.Honkavaara, LCLS ICW06 Other steps towards design goal Lasing with different wavelengths and switching between wavelengths –Lasing with ~15 different wavelengths between 13 nm and 45 nm achieved –Shortest wavelength: 13.1 nm (limited by electron beam energy) Lasing with different bunch train pattern and long pulse trains (> 30 µs) Lasing with higher repetition rate –Currently 5 Hz running, 10 Hz to be tested Repair and install modules –ACC3 to be replaced, ACC5 repair 4 tuners –Install new module ACC6 to reach 1 GeV (→ lasing down to ~ 6 nm) Install 3rd harmonic cavity –after ACC1 to improve longitudinal beam profile

K.Honkavaara, LCLS ICW06 Selected topics Charge Feedbacks Energy server Beam loss monitoring Electromagnetic interference PETRA ramps HOM measurements Long bunch trains 1 MHz 599 bunches

K.Honkavaara, LCLS ICW06 Charge Measured with toroids Noise from quadrupole magnet power supplies induces large noise in the toroids –Has been mostly removed by ferrites. Work on low noise power supplies required. Noise level now below 1% of 1 nC Laser BBO crystal adjustment needed time to time After adjustment charge stability 1-2% (rms)

K.Honkavaara, LCLS ICW06 Slow feedbacks Feedbacks used to correct slow drifts of charge, ACC1 phase, and orbit (upstream of collimator) Charge feedback: –Sensor: Charge in 3GUN toroid –Actuator: Laser attenuator ACC1 feedback –Sensor: Pyrosignal after BC (coherent diffraction radiation from a slit) –Actuator: ACC1 phase set-point Orbit feedback: –Sensor: BPM signals –Actuator: Steerers

K.Honkavaara, LCLS ICW06 Energy server Electron beam energy determined from dipole current and orbit through collimator dogleg Used as an input for on-line determination of SASE wavelength More accurate energy estimation still by measuring photon wavelength –Typical discrepancy with energy server few %

K.Honkavaara, LCLS ICW06 Beam loss monitor system Linac: Photomultipliers Undulator: photomultipliers + glass fibers (accumulated dose) Beam protection system disables beam operation when too high losses detected in undulator Long bunch trains (> 30 bunches) allowed only when losses along the whole linac are low Crucial for undulator protection and long bunch train operation, but helps also when steering the beam through the linac

K.Honkavaara, LCLS ICW06 Electromagnetic interference (EMI) We do have many sources of interference –High noise level in all ADCs –Noise from magnet power supplies (choppers) in diagnostics –Pulsed power cable testing –Inappropriate grounding scheme, high currents on earth lines –Magnetic disturbance due to PETRA ramps –Temperature induced drifts (phases) Investigation and fixing of external noise sources on-going

K.Honkavaara, LCLS ICW06 PETRA ramps Field changes of 1-2 µT explain observed orbit deviations 800 um Orbit movement at PETRA proton ramp PETRA proton ramps have an effect on beam orbit at FLASH → SASE production was disturbed during ramps Now compensated: stable SASE operation possible also when PETRA is ramping

K.Honkavaara, LCLS ICW06 HOM measurements Signal of dipole mode in a cavity can be used as an indication of the beam position → HOM signals provides a tool for on-line monitoring of beam position in the accelerating module Development of on-line BPM like display of HOM based beam positions on-going Dependence of HOM signal on the module phase under study Large collaboration: DESY, SLAC, Fermilab, KEK, CEA-Saclay Example of ACC5 raw HOM signals Example for vertical steering and dipole mode response in C1 of ACC1

K.Honkavaara, LCLS ICW06 Long bunch trains Up to 600 bunches (1 MHz) through the undulator –500 kHz, 100 kHz, and 50 kHz operation tested as well Lasing with at least 450 bunches (detector limit) Problems: –Toroid protection system not yet in operation –Beam loading compensation and other LLRF adjustments still required for 800 us flat top operation –Activation of beam line components due to darkcurrent (mostly from RF gun) 50 kHz 100 kHz 500 kHz 1 MHz 599 bunches

K.Honkavaara, LCLS ICW06 Schedule and milestones Commission RF gun at PITZ finished Commissioning injector started first beam to dump first lasing at 32 nm saturation at 32 nm achieved FEL experiments start FLASH is a user facility First lasing at 13 nm Lasing with long bunch trains (>30) Variation of wavelength on shift-to-shift basis Shutdown: installation 6 th module etc 1 GeV beam energy 2007 now