Presentation is loading. Please wait.

Presentation is loading. Please wait.

LINAC4 commissioning plans etc.

Similar presentations


Presentation on theme: "LINAC4 commissioning plans etc."— Presentation transcript:

1 LINAC4 commissioning plans etc.
Alessandra Lombardi on behalf of the LINAC4 team OP DAY - 26th January 2012 Archamps

2 OP DAY - 26th January 2012 Archamps
Preinjector 3 MeV Source(s) 2 solenoids RFQ 11 EMQ 3 Cavities 2 Chopper units dump 352 MHz Π-mode Structure 160 MeV 12 Modules 8 Klystrons 12 EMQ 12 steerers 23 m Cell-Coupled Drift Tube Linac 100 MeV 7 Modules 7 Klystrons 7 EMQ 7 steerers 14 PMQ 25 m Drift Tube Linac 50 MeV 3 Tanks 3 Klystrons 1 EMQ 2 steerers 114 PMQ 19 m OP DAY - 26th January 2012 Archamps

3 A. Lombardi – LINAC4 as BKP for LINAC2 – IEFC workshop -23 march 2011
Layout of LINAC4 45keV 3MeV 50MeV 102MeV RFQ MEBT DTL CCDTL PIMS Radio Frequency Quad. 352.2MHz 3 m Low Energy beam transport 2 solenoid 1.8 m 11 EMQ 3 Cavities 2 Chopper units. 3.9 m Drift Tube Linac 3 Tanks 114 PMQ 1 EMQ 19 m Cell-Coupled Drift Tube Linac 7 Modules 7 EMQ 14 PMQ 25 m Π-mode Structure 12 Modules 12 EMQ 22.9 m LEBT H- 160MeV Up to 3 MeV “charge insensitive” In the MEBT line we have to respect the chopping dynamics We need to match to a permanent focusing channel in the DTL and CCDTL A. Lombardi – LINAC4 as BKP for LINAC2 – IEFC workshop -23 march 2011

4 OP DAY - 26th January 2012 Archamps
“The source(s)” 45 keV beam available aug 2012 mid 2013 after 2015 OP DAY - 26th January 2012 Archamps

5 OP DAY - 26th January 2012 Archamps
Preinjector 3 MeV Source(s) 2 solenoids RFQ 11 EMQ 3 Cavities 2 Chopper units dump 352 MHz Π-mode Structure 160 MeV 12 Modules 8 Klystrons 12 EMQ 12 steerers 23 m Cell-Coupled Drift Tube Linac 100 MeV 7 Modules 7 Klystrons 7 EMQ 7 steerers 14 PMQ 25 m Drift Tube Linac 50 MeV 3 Tanks 3 Klystrons 1 EMQ 2 steerers 114 PMQ 19 m OP DAY - 26th January 2012 Archamps

6 OP DAY - 26th January 2012 Archamps
Transfer Line 70deg towards LINAC2 or to DUMP Up 2.5 m step to level with PSB OP DAY - 26th January 2012 Archamps

7 OP DAY - 26th January 2012 Archamps
Nominal Beam at PSB Intensity 40 mA Transverse Ε= pi mm mrad norm rms Alpha= 0 Beta x = 5,2.5,10 m Beta y = 4,2,8 m Dispersion = 0 or 1.2 m Longitudinal ±100 keV rms energy spread ( KeV possible) 160 MeV ± 1.2 MeV (dynamically over 20 µsec) Chopped 1 µsec for the distributor rise time 1 MHz frequency of the PSB as low as just letting few µbunches (50 nsec) OP DAY - 26th January 2012 Archamps

8 OP DAY - 26th January 2012 Archamps
What needs to be set EFFECT ON Focusing LEBT solenoids (2) Intensity and Transverse Emittance MEBT quadrupoles (11) Chopping efficiency DTL CCDTL PIMS quads (22) Intensity Transfer Line quadrupoles (15+18) Intensity , Matching and Dispersion Steering Steerers hor and vert (36) RF Phase and Amplitudes (22) Energy, energy spread OP DAY - 26th January 2012 Archamps

9 OP DAY - 26th January 2012 Archamps
Stages Energy Key issue Completed in the tunnel by LINAC4 stand alone 3MeV RFQ transmission Chopping May 2013 12 MeV Matching to DTL Sep 2013 30-50 MeV Transporting in PMQ channel Dec 2013 100 MeV Setting the RF phases Mar 2014 160 MeV - DUMP Reliability End 2014 Connection to PSB 160 MeV –LBE LBS T0+8months OP DAY - 26th January 2012 Archamps

10 Movable Temporary Benches
Low energy bench (up to 12 MeV) Spectrometer (0.2 %) Slit and Grid Emittance ToF (calibration) Bunch Shape Monitor Halo Monitor (chopping eff.) Medium energy bench (up to 100 MeV) ToF (0.1 %) Emittance via Profiles Bunch Shape Monitor OP DAY - 26th January 2012 Archamps

11 Permanent Measurement Line
4 profile monitors (emittance) Bunch shape monitor (phase spread) OP DAY - 26th January 2012 Archamps

12 OP DAY - 26th January 2012 Archamps
At 160 MeV on the DUMP Fine tuning of the whole LINAC Operational beam parameters at the end of the LINAC to be used as an input to rematch the line and prepare a fast commissioning of the lines. Reliability run OP DAY - 26th January 2012 Archamps

13 OP DAY - 26th January 2012 Archamps
Refurbished LBE LBS Emittance via Q-scan Energy spread and energy swing Draft ! OP DAY - 26th January 2012 Archamps

14 What have done so far +83mm Drift Emittance Meter Solenoid Steerer
Iris Faraday Cup Pre Chopper SEM-Grid BCT Slit

15 RFQ acceptance vs. Measured emittance
What have done so far RFQ acceptance vs. Measured emittance Measured after source vs. Measured at the RFQ input plane and backtracked to the source OP DAY - 26th January 2012 Archamps

16 OP DAY - 26th January 2012 Archamps
What if…we need 50MeV p Need DTL + CCDTL module 4 + all the quadrupoles – not before end 2014 Switch the source to P mode and complete installation new transfer line Reposition BHZ20 E = 0.28 pi rms norm DW=100 keV (1rms) 40 mA 50MeV 400 μsec OP DAY - 26th January 2012 Archamps

17 OP DAY - 26th January 2012 Archamps
Support from OP Software – for diagnostics applications – coordinated by Giulia Bellodi Participation to commissioning of the LINAC ( 3 teams of 3 people with 1 LINAC expert, 1 RF expert , 1 operator) , work on the basis of 2 shifts/day during 2013/2014. 18 man.month of experienced operators (=6 months * 3 operators) in 2013/14 available for Linac4 commissioning. To be aligned with commissioning schedule. Who is going to operate LINAC4 and from where? OP DAY - 26th January 2012 Archamps

18 OP DAY - 26th January 2012 Archamps
Connection to PSB Need 8 months / LHC stop of 6 months Ready from 2015 (Linac4 must be already commissioned) OP DAY - 26th January 2012 Archamps

19 OP DAY - 26th January 2012 Archamps
Summary Plan for commissioning LINAC4 in 5 stages with two temporary measurement benches. We believe that we have sufficient diagnostics to set all the linac parameters (about 130) . Energy spread can be measured properly only at 12 MeV and in the LBS. The present schedule foresees end of commissioning + reliability run at the end of 2014 From 2015 LINAC4 can be connected to the PBS Need a shutdown of 8 months for the connection OP DAY - 26th January 2012 Archamps


Download ppt "LINAC4 commissioning plans etc."

Similar presentations


Ads by Google