ELENA Project GBAR Experimental area L ayout / time scales / questions F. Butin / ELENA collaboration.

Slides:



Advertisements
Similar presentations
TCC2/TDC2 consolidation WG ALARA COMMITTEE PREPARATION for Xmas stop activities S. Evrard T. Wijnands
Advertisements

Daniel Schoerling TE-MSC-MNC 1 Review of AD-ELENA TL dipole Daniel Schoerling on behalf of WP 2.2 ELENA IIC meeting 27 th February 2014.
16/09/ Open Day at CERN 16/10/04 The Open Day working group Activities General access rules Visitors flow Safety measures of the visit points Active.
LINAC3 INSTRUMENTATION STATUS F.Roncarolo – 18 Feb 2015 F.Roncarolo 18 Feb
1 [12-Feb-2014] «BE-RF-PM» CLIC TBM Prototype Status update EDMS №[Number] Dmitry Gudkov 1.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Space reservation and crane limitations linked to refrigeration cold box in TX46 13th HL-LHC Parameter and Layout Committee Meeting C. Bertone, S. Claudet,
Service Management Status 107 th ACCU Meeting 10 March 2015.
13 March MERcury Intense Target (MERIT) Experiment Layout A.Fabich for CERN AB-ATB.
LE SMED Outil d’amélioration Silvia OLIVIERI Décembre 2009.
ELENA Installation follow-up 21/05/2015 Worksite follow-up.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
The new MEF Group S. Baird 12 th December The new MEF Group Mandate for the MEF Group MEF structure Support for LHC experiments Formal meetings/committees.
MKE4 Rearrangement -Updated Drawings -Visit to ECA4 -Visit to LSS4 -SPS Safety File -Safety during intervention MKE4 Rearrangement - TCM 25 August
CES Status J.Osborne 6 November 2009 Status Report from Civil Engineering and Services Working Group J.Osborne GS/SEM for CES Working Group.
GTPE 6 June 2013E.PEREZ-DUENAS & D.LACARRERE1 Transfos (2x 2 MVA) Servers (containers) New LHCb Control Room (CR) + LHC cryogenics CR New Assembly Hall.
IMPACTS OF INSTALLING THE REFERENCE MAGNET PLACEMENT IN B december 2014 Fulvio Boattini & Natacha Lopez Hernandez.
- Hearing Session - Marion Picard - July 28 th, 2011 S TATUS OF H I R AD M AT S AFETY F ILE Outline  Safety file Descriptive part Hazard inventory  Demonstrative.
ISOLDE: Status report building th ISCC meeting CERN, 31 March 2014 Erwin Siesling, Magda Kowalska.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
MG - IEFC meeting 22/01/20101 Linac 3 shielding S. Gilardoni, M. Giovannozzi, S. Baird, R. Brown, S. Damjanovic, T. Otto, M. Widorski, Acknowledgements:
IEFC 22 March 2011T. Eriksson CERN BE/OP How to ensure a bright future of the AD.
Status of renewal of Buildings 115 & 507 Borge & Erwin Siesling.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
Injector De-cabling Project Enlarged meeting # E. HARROUCH, EN-MEF, on behalf of the Injector De-cabling Project Team.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
B508 and 275 Magdalena Kowalska. b275 2 AEGIS laser lab ASACUSA test setup g-BAR? Storage of big parts, test stands? Test setups SSP, detector labs Electronics.
ST/MAforLHC April 2003Sixth ST workshop1 Summary of ST/MA deliverables for LHC Luigi Scibile for the ST/MA group.
Francois BUTIN CERN EN/MEF.  Future of AD is clearer and deserves investment  New AEGIS experiment being prepared, requires new control room  Existing.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
11/4/2005OLAV 1 Workshop CERNW. Maan Fast Vacuum Valves at CERN -Introduction to fast valves -History of fast valves in use/used at CERN -LEP fast shutters.
AD/ELENA (B193) Hall Extension F. Butin. Status The need of a new building for AD was already discussed in 2010, First pre-study shown to GTPE 1st Sept.
Update on the Laser Beam Line
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
LS1preparation & planning status A L Perrot on the behalf of EN/MEF R2E project meeting 11 th May 2012 EN.
Status of the ELENA transfer lines with special consideration of vacuum, hand-over optics and beam time distribution after 2017 W. Bartmann, D. Barna,
AD/ELENA (B193) Integration and constraints F. BUTIN / ELENA collaboration.
Extraction and beamline progress B.Goddard TE/ABT.
NA62 Organisation of the work - proposal 2/24/20161PD/DT/PO-MH.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Lau Gatignon. The open session of this meeting was fully dedicated to the AD program with 6 presentations by AEGIS, ACE, GBAR, ASACUSA, ATRAP and ALPHA.
Horst Breuker Review Oct ELENA Safety and Radio Protection ELENA TDR : Chapter 6; Safety Files in preparation; Descriptive, Demonstrative (Risk.
Horst Breuker ADUC Jan Safety and Radio Protection, Consequences for the Experiments ELENA TDR : Chapter 6; Safety Files in preparation; Descriptive,
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
Injector De-cabling Project Project meeting # 7, S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 1 Coating of the SPS Main Dipoles Vacuum Chambers: Resources Needed for Project.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
ELENA Layout Naming Convention F. Butin / ELENA collaboration.
August 2007Andrea Gaddi, CERN Physics Dept. Detectors Infrastructures & Services Baseline to design detectors infrastructures. Tentative arrangement of.
ELENA installation progress F. Butin / ELENA collaboration.
Steering committee ELENA Project Structure S. Maury, project leader C. Carli, deputy project leader Beam physics and Performance Committee (G. Tranquille,
ELENA Integration F. Butin / ELENA collaboration.
The Next Generation of a Gamma Irradiation Facility GIF++
LIU – EVM status and next steps
MERcury Intense Experiment Experiment Layout
TAXS and TAXN ABSORBERS - OVERVIEW
Dielectric Oil Installations
ELENA installation and commissioning status
Experimental hall design in Japanese site
EXTENSION ELENA = BUILDING 193 Status of integration
SPSC123 Summary Lau Gatignon/EN-EA IEFC, 4 November 2016.
ELENA Technical Coordination
EHN1 Neutrino Installation Plans
YETS Dec 2017 – March 2018 LS Experiments requirements / Services (un)availability F.Butin / EN-EA EACM meetings outcome, thanks to all participants.
Antiproton decelerator
RDR Baseline Layouts for Interaction Region
Installation of Photon Beam Transport to FEH
Experimental Areas – LS2 planning
Polarized 3He target installation
Presentation transcript:

ELENA Project GBAR Experimental area L ayout / time scales / questions F. Butin / ELENA collaboration

ELENA in CERN AD hall F. Butin / ELENA collaboration Existing AD machine ELENA ASACUSAALPHA ATRAP AEGIS BASE GBAR AEGIS 2 All drawings by O. Choisnet

GBAR Exp area layout F. Butin / ELENA collaboration Racks Main access Secondary Access / exit Laser rooms Linac Bunker Laser rooms

GBAR Exp area layout F. Butin / ELENA collaboration Access to Exp area Access to Linac

What CERN will install and pay Shielding around experimental area (not bunker) Cooling water distribution up to valves on the wall Electrical power sockets on the wall Access control / interlock Gas detection / ventilation Laser barracks + concrete slab Racks (SPS type 800 x 600 x 2400 mm) Control room (already available) Storage and preparation space in bdg 393: 20 m2 already available Access to workshop and cleaning room in bdg 393 F. Butin / ELENA collaboration

GBAR Linac Bunker layout F. Butin / ELENA collaboration 2 x 40 cm concrete 40 cm iron

GBAR Linac Bunker structure F. Butin / ELENA collaboration Recycled LEP dipole yokes Concrete Iron

LEP yokes F. Butin / ELENA collaboration Must be filled with concrete, + reservations for lifting bar cleaned, painted, transported About 1000 available…

Lifting jig for LEP yokes F. Butin / ELENA collaboration

Blocks details F. Butin / ELENA collaboration GBAR 03/06/2015 L (cm)l (cm)h (cm)W (kg)MaterialOwner PU (chf) Dwg ref Quantit éPrix (CHF) Réutilisation TFA (blocs en grande qté) Bloc béton DEHA Béton standard M. Lazzaroni1500 CE _B Bloc 1684 béton DEHA Béton standard M. Lazzaroni300 CE _C Bloc 884 béton DEHA Béton standard M. Lazzaroni200 CE _B Bloc 1688 béton DEHA Béton standard M. Lazzaroni500 CE _B Bloc 888 béton DEHA Béton standard M. Lazzaroni250 CE _B Bloc 1684 fonte CERN EN-GJS U-RT M. Lazzaroni9400PSZJSM__ Bloc 884 fonte CERN EN-GJS U-RT M. Lazzaroni4775PSZJSM__ Bloc 844 fonte Taraudé EN-GJS U-RT M. Lazzaroni2300 LHCJRB _B Bloc 842 fonte CERN EN-GJS U-RT M. Lazzaroni2300 PSZJS M__ total brut Total participation ESTIMATION (CHF) blocks 910 tons !

La particularité du bat 193 ne permet pas un accès aisé et rapide pour les livraisons (seule une petite partie des remorques est accessible avec le crochet du PR 591 (zonage orangé). De plus, le stockage sur place est très limité, ce qui implique une réalisation en flux tendu… Livraison des 438 blocs nécessaires :  ~3 semaines/3 personnes -> 2.25 FTE/mois En recouvrement pour une partie Réalisation du blindage :  ~3 semaines/3 personnes -> 2.25 FTE/mois 1 FTE/mois = 8100 CHF soit 4.5 * 8100 = CHF (courtesy S. Pelletier, EN-HE) F. Butin / ELENA collaboration Courtesy: Serge Pelletier EN/HE Transport input

Alternative with more LEP yokes F. Butin / ELENA collaboration

Alternative with more LEP yokes F. Butin / ELENA collaboration Cost cut by about factor 2 Not validated by RP yet Known to have issues Suppresses main access

Consequences of more LEP yokes F. Butin / ELENA collaboration Loses main access Secondary access remains OK with safety rules

Takes a lot of space ! F. Butin / ELENA collaboration Aegis 2 Big impact on ASACUSA laser hut

Time scale All bunker blocks are available at CERN Booking ASAP, when financing is secured Start blocks transfer and assembly in AD hall ASAP (impact on AD): 16th November 2015 Simultaneous assembly estimated to last 4 weeks: could be finished by end 2015 Rest of shielding installation (exp area) + laser barracks depends on GBAR schedule F. Butin / ELENA collaboration

Possible scenarios for antiproton physics up to LS2 Scenarios for Antiproton Physics in 2017 and 2018 Courtesy: C. Carli As shown to SPSC 15 April 2015 LS2 ?

Main questions to GBAR Detailed installation schedule ? Confirm interface with LNE50 transfer line (see drawing AD_LM_0083 and AD_LM_0077) F. Butin / ELENA collaboration Please check Catia model With O. Choisnet !

Main questions to GBAR (2) Updated experiment layout Catia model Estimates of ozone release Number, position and types of power sockets to be installed Negociate with PH a location at CERN for more storage ! Come to a conclusion on Linac shielding (…) F. Butin / ELENA collaboration

Linac Bunker Costing Concrete blocks: 56 kCHF Iron blocks: 646 kCHF Cleaning + paint: 10 kCHF Concrete in LEP yokes: 20 kCHF Transport + handling: 37 kCHF Total: 769 kCHF F. Butin / ELENA collaboration