Lau and Niels, NA62 TD meeting, 17 March 2014. Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting
Lau Gatignon, EATM, 7 October  The T9 and T10 lines have been running smoothly from mid July and the T11 beam started up very smoothly for CLOUD.
Andrea Paoli AdV 1 st Project Review Cascina, November 3 rd, 2008 IME – infrastructure modifications for environmental noise reduction.
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
P.-R. KettleMEG-Review February MEG Beam Line Studies  E5 Z-Branch NOW !!! NOW !!!
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
F.Brinker, DESY, July 17 st 2008 Injection to Doris and Petra Fitting the detector in the IP-region Radiation issues Beam optic, Target cell Polarisation.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Engineering Integration of the Double- Double Bend Achromat (DDBA) into the Diamond storage ring Jim Kay Diamond Light Source Low emittance ring 2013 workshop.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
Matching and Synchrotron Light Diagnostics F.Roncarolo, E.Bravin, S.Burger, A.Goldblatt, G.Trad.
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 T2K Beam Operation Summary (earthquake recovery and beamline survey) NBI 2012 T. Ishii (KEK) for the T2K beam group.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
Apex Target Marco Oriunno, April 23, Design and fabrication by: Marco Oriunno, Dieter Walz, Jim McDonald, Clive Field, Douglas Higginbotham, and.
Undulator Orientation & Electron Beam Spacing Should the undulator frames be toward the central aisle or the tunnel walls? What is the optimum spacing.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Beam line commissioning Preparations for Phase1 Kevin Tilley For Paul Drumm & the beam line group.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
STATUS OF HO Sudhakar Katta TIFR, Mumbai India-CMS meeting, Delhi 27 th Sept 2007.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
East Area, M2, K12 Lau Gatignon / EN-MEF, EATM
The Stripping Foil Test Stand in the Linac4 Transfer Line
LG, 15 March 2007 ATB work for 2007 run1  Repair of ‘guillotine valves’  Repair converter (just after T4 TAX – quite radioactive !)  Invert order of.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
D. Still-FNAL/Tevatron HALO '03 Tevatron Collider II Halo Removal System Dean Still Fermilab Tevatron Department 5/21/2003 Motives for the Collider Run.
All Exp Mtg July 7, 2008 NuMI-MINOS Status Report – Laura Loiacono FAR DETECTOR: FD live time was 95.7% for cosmics last week (ROP7 problems reported at.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Report from HIE-ISOLDE HEBT WG J.Bauche‎, P.Farantatos‎, M.Fraser‎, B.Goddard, Y.Kadi‎, D.Lanaia‎, D.Nisbet‎, E.Siesling‎, G.Vandoni‎, D.Voulot‎, E.Zografos.
SOME CEDAR NEWS Lau Gatignon / EN-MEF TD meeting 12/07/2011  Summary of HAZOP and Zoning meeting  Forthcoming CEDAR related work at CERN.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Lau Gatignon, EATM,  The construction of the CHARM and IRRAD zones is completed and operation at nominal intensity started yesterday.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
PSB H 0 -H - Injection: Sectorisation Analysis C.Pasquino, J. Hansen, P.Chiggiato 1LIU - PSB Ho-H- Injection Meeting.
Installation of the T600 at Fermilab CSN2, September 22,
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Status Report Beam Working Group 31 January 2007 Presented by L.Gatignon  Revised beam design  Requests to AB department for 2007.
1 Building Design Progress Dan Wilcox March 2012.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
S A Griffiths CM42 June 2015 Electrical & Control.
Update on the PSB Cooling and Ventilation Systems
T980 STATUS AND CHANGES FOR
Francois and Lau EATM 17 July 2012
ELENA installation and commissioning status
Possible causes for SPS ZS2 misalignment
EN-STI activities in LHC during EYETS
N-TOF EAR2 - Vertical beam design & construction - Irradiation facility proposal S. Girod EN-EA.
Far Detector Activities Late 2017 – Early 2018
Francesco Gonnella NA62 Collaboration meeting Washington DC, U.S.A.
TEST PLANS for HL LHC IT STRING
Teleconference ACS – FREIA 20th February 2018
Experimental Areas – LS2 planning
East Hall under construction
Presentation transcript:

Lau and Niels, NA62 TD meeting, 17 March 2014

Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10 target Close up roof shield above front end of beam New location for fast valve, move 2 magnets Double separation wall Temporary modifications to ventilation system Prepare final ventilation system renovation Complete vacuum All the rest…..

 The mechanical work on the TCC8 crane has been completed.  Still some remaining work on the electrical distribution.  The crane delivery is foreseen for end March (possibly March 18 th ).  The new crane has no ‘guirlande’, but is powered via a rail. This makes the air separation between TCC8 and ECN3 much easier.  Quite some work depends on the availability / reliability of the TCC8 crane!

 Due to asymmetric profiles and slightly low kaon rate, the alignment of the beam front end has been verified in detail. This included an insert in T10.  This required dismantling of the roof shield and of the TCX dump and of the first QNR quadrupole.  Also one MTR dipole in next to the TAX had to be turned by 180 o.  The TCX and magnets have to be reinstalled, as soon as the crane is available

Contrôle 3D (AT401). T10 insert At some stage….. Now Ecart Alti. : +0.16mm Ecart radial: -0.25mm (coté Salève)

QNR TCX Both are self-aligning Reinstallation as soon as the TCC8 crane is available again

 All the mechanical parts of the T10 target will be replaced  Specification in EDMS document  The shielding itself will be preserved  Replace target box with identical spare  Different target materials were studied, but stay with Beryllium  Replace the T10 collimator  The TBIU unit will be replaced with a new box, containing - a BSI (Titanium foil for intensity measurement) - Two BSPH, two BSPV (split foils) - BBSH and BBSV (SEMP profile scanners) - Two halo foils with slits of 145x2.5 mm (one horizontal, one vertical)  All this will be properly aligned and tested

 Once the alignment of T10 and the from end is done, the roof shield will be completed

 Now that we have agreed to install only one fast valve, it was deemed to install it as far downstream as possible, i.e. just upstream of GTK3.  The 32 cm of longitudinal space required implied a displacement of the two last achromat-2 magnets by 32 cm.  The magnets will be reinstalled soon (requires TCC8 crane).

The order has been placed with Sarvadon. Also a separation will be made in GHN300

 With the double separation wall in place, the air separation between ECN3 and TCC8 should be OK, apart from leaks between the ventilation units.  CV will take care of the pressurization of the double wall.  Therefore we will STOP the ventilation in TCC8 in the technical run at the level of the double wall with dampers. This should rather efficiently stop the air flow from TCC8 into ECN3.  With those measures the operation of the ventilation system should be close to the final version, apart from the bad shape of the ventilation units.

 The study of the final ventilation system is in progress.  Information will be made available on EDMS doc  Installation is foreseen during the first half of 2015, before the start of the 2015 physics run.

 The beam line vacuum remains to be remounted and leak tested, following the various modifications.  The control is being implemented by the vacuum group  The expansion vessel next to the RICH remains to be connected.  The blue tank vacuum is on track. The planning for commissioning is tight due to late closing of the tank (detector arrival) and one should be aware that commissioning can take more time e.g. in case of leaks. As discussed before. It is important to close the tank as early as possible.  Planning: Pumping test for K12, leak test, final test of control system (probably) fits with NA62’s proposed vacuum test in July - August Performed jointly by EN/MEF and TE/VSC (knowledge transfer). Final test with full gas load = pumping before & during physics run. Will be executed by EN/MEF, but under the expert eye of TE/VSC.

 The GL vs I curve of QNL magnets will be measured and parameterised. This should lead to an even better understanding of the optics of P42 (and K12). We have also a better understanding of the gradients in QNR magnets.  Understand / confirm orientation (H/V) of 4-jaw collimators.  Consolidation and realignment of T4 target (late Summer). Replace 200 mm head by a 180 mm head (slightly better for T10 flux).  The gas extraction and the H2 infrastructure must be installed → see next slide  The RP monitoring system will be completed.  Minor improvements to the side shielding of the K12 TAX.  Install a fence at the entrance to the dump tunnel.  Cesar upgrade, details still to be finalised.  Not discussed here: infrastructure not directly related to beam (rack cooling, etc)

To be updated after crane renovation in TCC8

L.Gatignon, SPSC112, Experimental Area Status18