1 MICE PM Report Outcome of Reviews held at CM22 –Motivation for holding them –Outcomes & actions –Observations & follow-ups MICE Video Conference, 20.

Slides:



Advertisements
Similar presentations
Report from MICE project teams Proposed MICE organogram: revised Revised request for resources for financial year 2003/04 Review of iMICE schedules – status.
Advertisements

1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Chapter 10 Schedule Your Schedule. Copyright 2004 by Pearson Education, Inc. Identifying And Scheduling Tasks The schedule from the Software Development.
AFC engineering group meeting on the 26 th of Jan 2004 MICE Absorber Focus Coil work schedule for the next 6 months By Wing Lau, Oxford.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 APRP Meeting MICE UK work packages Costs and schedules Organisation and monitoring Schedule summaries Cost summaries Andy Nichols, STFC, 15/8/11.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
1 Subsystem Reviews Reviews this week: RFCC modules RF Power Infrastructure MICE Infrastructure LH2 system.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
Discussion Document By G How. History LeadershipStructureProcessesInformationEnvironment The path of Shared Services is littered with failed attempts.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE Status (with a UK slant) Paul Drumm, MICE Collaboration UK-NF June 2003.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
Andrew McGettrick ACM Education Council Meeting Denver, CO March 2013 The Education Board and Education Council – an update on activity.
Project Charters Module 3
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Underground Cost Analysis; Option 10 and 11 - TRTP Project Project Segment 8A Corridor October 21, 2012.
LIGO-G M Planning and Implementation Strategy for Advanced LIGO Gary Sanders LSC Meeting Hanford, August 14, 2001.
Date Event Global Design Effort 1 ILC UPDATE Vancouver to Valencia Ewan Paterson Personal Report to SiD Collaboration Oct 27, 2006.
1 MICE CM28 Schedule & Risk Comment Schedule reconstruction and management The ‘straight to Step IV’ discussion How a schedule meeting can work Risks (and.
In the name of Allah the Most Gracious the Most Merciful.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Norman McCubbin1 Report from the Collaboration MICE Project Board (CMPB) Norman McCubbin Director, Particle Physics Department MICE/UKNF Oversight Committee.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
Overview of RUP Lunch and Learn. Overview of RUP © 2008 Cardinal Solutions Group 2 Welcome  Introductions  What is your experience with RUP  What is.
1 MICE PM report – status of Phase II Target update Spectrometer solenoid FC & coupling coils Schedule considerations Project accommodation & management.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
SIT Professional Development- Defining the Consultation Model Permission to reprint granted with appropriate acknowledgement ©2009 DPS.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE CM23 Introduction and Meeting Goals Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
PMI Evening Event - Preston / Dec 2007 Spotting & catching problem projects before it's too late Neil Johnson Project & Programme Management Capability.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 MICE RLSR Summary of Issues Relating to Question One of Review charge ‘ Given a resource-limited, year-by-year schedule for the project, how reasonable.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
Status of the MICE Construction Project
MICE CM31 Schedule summary
MICE Project in the US: Completion of Efforts
MICE PM Report Progress with the Infrastructure A few problems
The DBD: Outline and Scope
DSC ChMC CSS update 11th December 2018
EST102: 17/11/17: Uptake of Customer References.
DSC ChMC CSS update 09th January 2019
Presentation transcript:

1 MICE PM Report Outcome of Reviews held at CM22 –Motivation for holding them –Outcomes & actions –Observations & follow-ups MICE Video Conference, 20 th November, 2008

2 Motivation During Spring & Summer this year, it became clearer what resources will be available for the UK Phase Two (to step five) project This is primarily the Focus coil modules (2+option 1) But there is a large engineering commitment for infrastructure to support the Phase Two subsystems and to ensure the installation goes smoothly Made a bottom-up estimate of this, which was predictably too high So we got squeezed in the approved fashion The most likely outcome is to spread the expenditure over four years, instead of three Two schedules are in progress: technically-limited Driven by external subsystem milestones (hopefully three years) –And resource-limited Driven by the enforced four year timescale So reviews scheduled to extract project planning data to construct the above

Motivation Four reviews were organised: –RF Power/infrastructure –RFCC PRR –Infrastructure –LH2 system Were held during CM22 –But the AFC PRR took place on November 4 th – provided useful information

Outcomes & Actions Close-out notes of the reviews are posted at: Too much detail to cover here, but the main points are as follows: RFCC PRR In good shape for manufacture, no real problems, delivery March/April 2010 Infrastructure Also in good shape: at least the work areas appear to be well-defined (more than we thought). The schedule is clearly dependent on other subsystems though

Outcomes & Actions RF Power Infrastructure Different options for the RF power distribution Various implications for Hall layout and other stuff Andy Moss agreed to present one scheme for agreement among MICE (early December) Then he gets opinion from ‘world’ experts – need an external review at that point (February ‘09?) This decision has to be taken before detailed design is started LH2 system Clearly suffering from reduced manpower R&D hardware needs to be progressed at AS Scientific Control system philosophy needs to be agreed within MICE before we can proceed Internal review for above planned for Jan ‘09 5

Outcomes & Actions LH2 system –LH2 project must be ‘owned’ by somebody –The work content definition should be strengthened –Currently the LH2 timescales are much too loosely defined –But the real problem is lack of effort to work on cryogenic systems in parallel –But a glimmer of hope: ASD Management are accelerating recruitment and PED have permission to get a Graduate Engineer AFC modules –Reasonably straight forward, good progress from FDR –Some problems with coil former being tidied up –Delivery date for AFC#1 November

Observations & Follow-ups Based on the review content, the hardware deliveries will be in advance of the resource-limited schedule, so some of them might be gathering dust The LH2 system is the biggest worry, but at least the review allowed us to define the problem and work out the actions Other than that, the subsystems seem to be following their plans AN will try to bring both overall schedules to the CM23 7