Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
HFT Technical Overview September 26, HFT 2013 TPC FGT 2011 STAR Detectors Fast and Full azimuthal particle identification EMC+EEMC+FMS (-1 ≤ 
HFT Safety --PXL detector September 26, Dana Beavis.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
L. Greiner 1IPHC meeting – September 5-6, 2011 STAR HFT Plans for the next year A short report on review results and plans for TPC – Time Projection.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
PHENIX Run-14 Status January 28, 2014 Klaus Dehmelt 1Klaus Dehmelt - Jan 28, 2014 RHIC Time meeting.
Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31,
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
PHENIX WEEKLY PLANNING 4/20/06 Don Lynch. Safety We have lost a whole week of running because of a violation of procedure and not because of the accident.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
November 18, 2008 John Haggerty 1 PHENIX In Run 9 John Haggerty Brookhaven National Laboratory.
Project Overview How to get here…. Half Way to the Test Run October 18, 2012HPS Project Overview2 …starting from here? John Jaros HPS Collaboration Meeting.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
11 SSD Power and Cooling on the Cone STAR Integration Workshop Howard Matis May 16, 2008 STAR Integration Workshop Howard Matis May 16, 2008.
Test beam setup: status report 02/03/2009 M. Alfonsi (CERN)
12/5/ PHENIX WEEKLY PLANNING Dec. 5, 2013 Don Lynch.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
October 3, 2008 John Haggerty 1 PHENIX Plan for Run 9 John Haggerty Brookhaven National Laboratory.
ECOOL Meeting 03/26/10 1 Low-E cooler baseline decisions: 1.FNAL’s cooling section “as is” – with weak solenoids, correctors, etc. (to prevent over focusing.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
MOLLER Collaboration Meeting May 2014 Hall A Update Thia Keppel 1.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
MICE CMPB Alain Blondel 1 Highlights on MICE.
2007 Run Update for STAR Jeff Landgraf For the STAR collaboration.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Hall D infrastructure and integration Elton Smith Hall D Collaboration Meeting September 9-11, 2004.
All Experimenters’ Meeting December 8, 2014 Photo by Greg Vogel.
H. MatisSTAR Inner Silicon Tracking Detector Review – July 8, SSD software and hardware maintainability Howard Matis.
TPC Collaboration Meeting Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
Bill Christie For the STAR Collaboration January 5, Outline Detector configuration for Run 16 Data set Goals Desired luminosity profile for Run.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
1 HBD: Responsibilities, Cost and Schedule Itzhak Tserruya EC/DC Meeting, BNL, March 9, 2005.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
DON LYNCH OCTOBER 28, October 28, 2014 sPHENIX Detector Integration & Assembly Concept.
PHENIX WEEKLY PLANNING 10/26/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
PHENIX WEEKLY PLANNING 3/30/06 Don Lynch. This Week MPC air flow started BLM source test HBD transparency monitor hutch work and cable tray 1 st MPC Card.
Bill Christie For the STAR Collaboration June 15,
1 11/25/2010 PHENIX WEEKLY PLANNING 11/25/2010 Don Lynch.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Operations meeting on FY07 Shutdown Date: June 27, W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
ELENA installation progress F. Butin / ELENA collaboration.
PHENIX WEEKLY PLANNING 2/16/06 Don Lynch. Prep for Run 6 Completed.
2007 Physics Run Status STAR Collaboration mtg June 12, 2007, Berkeley California Bill Christie Outline Overview of BUR/Goals for Fy07 Run Collider Performance.
HFT Overview Flemming Videbæk BNL 3/14/12 F2F LBNL.
Presentation transcript:

Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary

Status Update Decision was made in late July to Roll the STAR detector out of the Interaction Region (IR) for a partial installation of the Forward GEM Tracker (FGT). A schedule for the Roll out, Roll in, and installation effort was generated with input from all sub systems. With the installation of the FGT, and its support structure (new carbon fiber cones inside TPC Inner Field Cage) the Forward Time Projection Chambers (FTPCs) and the Photon Multiplicity Detector (PMD) were retired and have been removed. STAR Roll out went according to schedule. In addition to partial FGT installation for Run 12, we’ll be doing a partial installation of the Muon Telescope Detector (MTD). MTD modules expected to arrive at BNL this weekend. Also expect to install new GEM Monitor Trackers (GMT), but these will come late in the Shutdown. FGT construction held fairly well to the agreed upon schedule, but there has been about a three week delay in the delivery of prototype carbon fiber parts from LBNL that are necessary for the final assembly and installation of the FGT. Routine maintenance on other STAR sub systems (i.e. TPC, Trigger, BEMC, EEMC, DAQ, TOF, FMS) proceeding. No issues expected. FGT installation delay such that RHIC cool down schedule for January 2 nd can’t be met by STAR.

A few FGT images

Remove/move Beam pipe Assembly of New Cone, old Beam Pipe, & FGT Key Milestones for October: Last of the FGT cooling tube.spacers arrive at BNL on or before Oct. 21 st. Last FGT spacer arrives Move old cone & BP to Clean room roof Shrouds at BNL MTD & TOF trays arrive TODAY

Veteran’s Day Thanksgiving Day Install Shield Wall Connect vacuum pipe, setup bake out Install bridge & Stairs Connect vacuum pipe, starting with East Side Roll In & position Install seismic anchors Install Power Bridge MCW H2O pipes Magnet H2O pipes Remove rails & stanchions BNL Holiday Disassemble East Platform & Rig away Remove Power MCW H2O pipes Install E. Scaffolding Collaboration mtg at LBNL Connect various utilities, cables, gas lines, etc Between Platforms and walls & Floor racks (Who connects EEMC Trigger cables?) New Cone assembly on rails Install Cone into STAR, remove rails, HV test Contingency Assembly of New Cone, old Beam Pipe, & FGT Key Milestones for November: The last piece/item needed (shroud) to complete the assembly of the new cone structure with the FGT and new beam pipe will arrive at BNL on or before Nov. 1st. Cone assembly, with beampipe & supports, and FGT, complete on or before November 2 nd. STAR rolled into IR before Veteran’s Day. Lab Holidays on Nov. 11 th, 24 th, and 25 th. Collaboration mtg at LBNL Nov. 14 th – 18 th. Connect TOF gas lines no later than week of Nov. 21 st. Shrouds at BNL Finish Beam pipe Bakeout & remove equipment Connect various utilities, cables, gas lines, etc Between Platforms and walls & Floor racks

Certify Interlocks Half day BNL Holiday Sub System Check out period starts Sub System Check out period continues Remaining installation tasks Possible Remaining Installation tasks: MTD trays MTD utilities TOF/GMT trays GMT Cables GMT Gas system Install VPDs VPD cabling FGT Gas system Modify Air distribution system etc. STAR Upgrade Workshop & C. Whitten Memorial UCLA Sub System Check out period continues Install West Poletip? N.B.: West Poletip installation date will depend on amount of EEMC work still to do come December. Also shows up on January 3-4.

Install E&W Poletips, hook-up leads and start Mag. H2O MAG. P.S. testing MAG. P.S. testing & Heat Run TPC HV chk with Mag. on Install BBCs Sub System Check out period continues Contingency & Sub System Check out period continues RHIC Cool Down Starts ? Start Magnet H2O system

Summary Assuming no further delays with the FGT installation, the Roll in date for STAR will have a three week delay from our original schedule. An aggressive schedule has been put together which includes this delay. To hold this schedule STAR will need a high priority for C-AD resources when needed (i.e. Techs, Riggers, Carpenters, Vacuum grp., etc.). At this point, this new schedule indicates that STAR will need to request an ~ two week delay in the RHIC Cool down, from January 2 nd to January 17 th.